Computation of Time / Adverse Weather Sample Clauses

Computation of Time / Adverse Weather. 15.2.1 Developer will only be allowed a time extension for Adverse Weather conditions if requested by Developer in compliance with the time extension request procedures herein and only if all of the following conditions are met: 15.2.1.1 The weather conditions constitute Adverse Weather, as defined herein; 15.2.1.2 Developer can verify that the Adverse Weather caused delays in excess of five (5) hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 15.2.1.3 Developer’s crew is dismissed as a result of the Adverse Weather; 15.2.1.4 Said delay adversely affect the critical path in the Construction Schedule; and 15.2.1.5 Exceeds twelve (12) days of delay per year. 15.2.2 If the aforementioned conditions are met, a non-compensable day-for- day extension will only be allowed for those days in excess of those indicated herein. 15.2.3 Developer shall work seven (7) days per week, if necessary, irrespective of inclement weather, to maintain access and the Construction Schedule, and to protect the Work under construction from the effects of Adverse Weather, all at no further cost to the District. 15.2.4 The Contract Time has been determined with consideration given to the average climate weather conditions prevailing in the County in which the Project is located.
AutoNDA by SimpleDocs
Computation of Time / Adverse Weather. 15.1.1. The Contractor will only be allowed a time extension for Adverse Weather conditions if requested by Contractor and only if all of the following conditions are met: 15.1.1.1. The weather conditions constitute Adverse Weather, as defined herein; 15.1.1.2. Contractor can verify that the Adverse Weather caused delays in excess of five hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 15.1.1.3. The Contractor’s crew is dismissed as a result of the Adverse Weather; and 15.1.1.4. The number of days of delay for the month exceeds the following parameters, or twenty nine (29) days annually. The District and Contractor may negotiate a different minimum number of days, which shall be as indicated in Exhibit K to the Master Facilities Lease: January 7 July 0 February 7 August 0 March 4 September 0 April 3 October 2 May 1 November 2 June 1 December 2 15.1.2. A day-for-day extension will only be allowed for those days in excess of those indicated herein. 15.1.3. The Contract Time has been determined with consideration given to the average climate weather conditions prevailing in the County in which the Project is located.
Computation of Time / Adverse Weather. 16.3.6.1. The Contractor will only be allowed a time extension for Adverse Weather conditions if requested by Contractor within five (5) calendar days of the Adverse Weather event, and only if all of the following conditions are met – thereby making the resulting delay an Excusable Delay. 16.3.6.1.1. The weather conditions constitute Adverse Weather, as defined herein and further specified in the Special Conditions; 16.3.6.1.2. Contractor can verify that the Adverse Weather caused delays in excess of five (5) hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 16.3.6.1.3. The Contractor’s crew is dismissed as a result of the Adverse Weather; and 16.3.6.1.4. The number of days of delay for the month exceed those indicated in the Special Conditions. 16.3.6.2. A day-for-day extension will only be allowed for those days in excess of those indicated in the Special Conditions. 16.3.6.3. The Contractor shall work seven (7) days per week, if necessary, irrespective of inclement weather, to maintain access and the Construction Schedule, and to protect the Work under construction from the effects of Adverse Weather, all at no further cost to the District. 16.3.6.4. The Contract Time has been determined with consideration given to the average climate weather conditions prevailing in the County in which the Project is located.
Computation of Time / Adverse Weather. 13.14.1 The Contractor will only be allowed a time extension for Adverse Weather conditions if requested by Contractor in compliance with the time extension request procedures and only if all of the following conditions are met: (a) The weather conditions constitute Adverse Weather, as defined herein and further specified in the Project Specific Conditions; (b) Contractor can verify that the Adverse Weather caused delays in excess of four (4) hours of the indicated labor required to complete the critical scheduled tasks of Work on the day affected by the Adverse Weather, which includes residual weather effects of flooding, mud and other impacts as a result of the Adverse Weather; (c) The Contractor's crew is dismissed as a result of the Adverse Weather; (d) Said delay adversely affects the critical path in the Construction Schedule; and (e) The number of days for delay caused by Adverse Weather for the month(s) in which the delay occurs exceeds the following:
Computation of Time / Adverse Weather. 15.2.1 Developer will only be allowed a time extension for Adverse Weather conditions if requested by Developer in compliance with the time extension request procedures herein and only if all of the following conditions are met: 15.2.1.1 The weather conditions constitute Adverse Weather, as defined herein; 15.2.1.2 Developer can verify that the Adverse Weather caused delays in excess of five (5) hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 15.2.1.3 Developer’s crew is dismissed as a result of the Adverse Weather;
Computation of Time / Adverse Weather. 15.5.5.1. The Contractor will only be allowed a time extension as an Excusable Delay for Adverse Weather conditions if requested by Contractor within FIVE (5) Days of the Adverse Weather event, and only if all of the following conditions are met in addition to those for an Excusable Delay above: 15.5.5.1.1. The weather conditions constitute Adverse Weather, as defined herein and further specified in Exhibit K; 15.5.5.1.2. Contractor can verify that the Adverse Weather caused delays in excess of five (5) hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 15.5.5.1.3. The Contractor’s crew is dismissed as a result of the Adverse Weather; and 15.
Computation of Time / Adverse Weather. 15.1.1. The Developer will only be allowed a time extension for Adverse Weather conditions if requested by Developer and only if all of the following conditions are met: 15.1.1.1. The weather conditions constitute Adverse Weather, as defined herein; 15.1.1.2. Developer can verify that the Adverse Weather caused delays in excess of five hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 15.1.1.3. The Developer’s crew is dismissed as a result of the Adverse Weather; and 15.1.1.4. The number of days of delay for the month exceeds the following parameters. The District and Developer may negotiate a different minimum number of days, which shall be as indicated in Exhibit K to the Facilities Lease:
AutoNDA by SimpleDocs
Computation of Time / Adverse Weather. 14.1.1 The Developer will only be allowed a time extension for Adverse Weather conditions if requested by Developer and only if all of the following conditions are met: 14.1.1.1 The weather conditions constitute Adverse Weather, as defined herein; 14.1.1.2 Developer can verify that the Adverse Weather caused delays in excess of five hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 14.1.1.3 The Developer’s crew is dismissed as a result of the Adverse Weather; and 14.1.1.4 The number of days of delay for the month exceed the following parameters: January [6] July [0] February [5] August [0] March [5] October [1] April [4] October [1] May [1] November [3] June [0] December [5] 14.1.2 A day-for-day extension will only be allowed for those days in excess of those indicated herein. 14.1.3 The Contract Time has been determined with consideration given to the average climate weather conditions prevailing in the County in which the Project is located.
Computation of Time / Adverse Weather. 15.1.1. The Contractor will only be allowed a time extension for Adverse Weather conditions if requested by Contractor and only if all of the following conditions are met: 15.1.1.1. The weather conditions constitute Adverse Weather, as defined herein; 15.1.1.2. Contractor can verify that the Adverse Weather caused delays in excess of five hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 15.1.1.3. The Contractor’s crew is dismissed as a result of the Adverse Weather; and 15.1.1.4. The number of days of delay for the month exceeds the following parameters, or twenty nine (29) days annually. January 7 July 0 February 7 August 0 March 4 September 0 April 3 October 2 May 1 November 2 June 1 December 2 15.1.2. The District and Contractor may negotiate a different minimum number of days or a cumulative number of days for the duration of the Project, which shall be as indicated in Exhibit K2 to the Facilities Lease. 15.1.3. A day-for-day extension will only be allowed for those days in excess of those indicated herein. 15.1.4. The Contract Time has been determined with consideration given to the average climate weather conditions prevailing in the County in which the Project is located.
Computation of Time / Adverse Weather. The Contractor will only be allowed a time extension for Adverse Weather conditions if requested by Contractor and only if all of the following conditions are met: The weather conditions constitute Adverse Weather, as defined herein; Contractor can verify that the Adverse Weather caused delays in excess of five hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; The Contractor’s crew is dismissed as a result of the Adverse Weather; and The number of days of delay for the month exceeds the following parameters, or twenty nine (29) days annually. The District and Contractor may negotiate a different minimum number of days or a cumulative number of days for the duration of the Project, which shall be as indicated in Exhibit K to the Facilities Lease: January 7 July 0 February 7 August 0 March 4 September 0 April 3 October 2 May 1 November 2 June 1 December 2 A day-for-day extension will only be allowed for those days in excess of those indicated herein. The Contract Time has been determined with consideration given to the average climate weather conditions prevailing in the County in which the Project is located.
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!