CONNECTION ENTRY CAPACITY AND TRANSMISSION ENTRY CAPACITY Sample Clauses

CONNECTION ENTRY CAPACITY AND TRANSMISSION ENTRY CAPACITY. 7.1 The Connection Entry Capacity in relation to the Generating Units and the Connection Site and the Transmission Entry Capacity in relation to the Connection Site, are specified in Appendix C.
AutoNDA by SimpleDocs
CONNECTION ENTRY CAPACITY AND TRANSMISSION ENTRY CAPACITY. Company: Connection Site: Part 1 Connection Entry Capacity Connection Entry Capacity (CEC) expressed as an instantaneous MW figure CEC(MW) Interconnector [ ]
CONNECTION ENTRY CAPACITY AND TRANSMISSION ENTRY CAPACITY. [AND MAXIMUM EXPORT CAPACITY AND MAXIMUM IMPORT CAPACITY - ET Offshore Transmission System only] Company: Grid Supply Point/Connection Site: Part 1 Connection Entry Capacity Connection Entry Capacity (CEC) expressed as an instantaneous MW figure Power Station Generating Unit [ ] Genset 1 [ ] Genset 3 [ ] Genset 4 [ ] Part 2 Transmission Entry Capacity Transmission Entry Capacity (TEC) expressed in average MW taken over a half hour settlement period TEC(MW) Power Station [ ]
CONNECTION ENTRY CAPACITY AND TRANSMISSION ENTRY CAPACITY. Company: Grid Supply Point/Connection Site: Part 1 Connection Entry Capacity Connection Entry Capacity (CEC) expressed as an instantaneous MW figure Power Station Generating Unit [ ] Genset 1 [ ] Genset 3 [ ] Genset 4 [ ] Part 2 Transmission Entry Capacity Transmission Entry Capacity (TEC) expressed in average MW taken over a half hour settlement period TEC(MW) Power Station [ ]
CONNECTION ENTRY CAPACITY AND TRANSMISSION ENTRY CAPACITY. Formatted Formatted Formatted Formatted

Related to CONNECTION ENTRY CAPACITY AND TRANSMISSION ENTRY CAPACITY

  • Contract Capacity The generation capability designated for the Project shall be the contract capacity in MW designated in the Cover Sheet, net of all auxiliary loads, station electrical uses, and Electrical Losses (the “Contract Capacity”). Throughout the Delivery Term, Seller shall sell and deliver all Product produced by the Project solely to Buyer. In no event shall Buyer be obligated to receive, in any Settlement Interval, any Surplus Delivered Energy. Seller shall not receive payment for any Surplus Delivered Energy. To the extent Seller delivers Surplus Delivered Energy to the Delivery Point in a Settlement Interval in which the Real-Time Price for the applicable PNode is negative, Seller shall pay Buyer an amount equal to the Surplus Delivered Energy (in MWh) during such Settlement Interval, multiplied by the absolute value of the Real-Time Price per MWh for such Settlement Interval.]

  • Interconnection Customer (1) Interconnection Customer shall construct and, unless otherwise indicated, shall own, the following Interconnection Facilities: None

  • Interconnection Service Interconnection Service allows the Interconnection Customer to connect the Large Generating Facility to the Participating TO’s Transmission System and be eligible to deliver the Large Generating Facility’s output using the available capacity of the CAISO Controlled Grid. To the extent the Interconnection Customer wants to receive Interconnection Service, the Participating TO shall construct facilities identified in Appendices A and C that the Participating TO is responsible to construct. Interconnection Service does not necessarily provide the Interconnection Customer with the capability to physically deliver the output of its Large Generating Facility to any particular load on the CAISO Controlled Grid without incurring congestion costs. In the event of transmission constraints on the CAISO Controlled Grid, the Interconnection Customer's Large Generating Facility shall be subject to the applicable congestion management procedures in the CAISO Tariff in the same manner as all other resources.

  • Transmission Service Point-To-Point Transmission Service provided under Part II of the Tariff on a firm and non-firm basis.

  • Right to Contracted Capacity & Energy 4.4.1 The SPD will declare the CUF of the project and will be allowed to revise the same once within first year after COD of the project. Thereafter, the CUF for the Project shall remain unchanged for the entire term of the PPA. The declared annual CUF shall in no case be less than 17%. It shall be the responsibility of the SPD, entirely at its cost and expense to install such number of Solar panels and associated infrastructure(like project equipment)as may be necessary to achieve the required CUF, and for this purpose SPD shall make its own study and investigation of the GHI and other factors prevalent in the area which have implication on the quantum of generation. Further, arrangement of extra land for such installation shall be intimated to MSPDCL in advance and MSPDCL shall have to reply for the same in 7 days in the best interest of the project generation. However,non- availability of land shall not absolve SPD from his obligations under the PPA. SPD shall maintain generation so as to achieve annual CUF within + 10% and -15% of the declared value till the end of 10 years from COD, subject to the annual CUF remaining minimum of 15%, and within +10% and -20% of the declared value of the annual CUF thereafter till the end of the PPA duration of 25 years. The lower limit will, however, be relaxable by MSPDCL to the extent of non-availability of grid for evacuation which is beyond the control of the SPD. The annual CUF will be calculated every Contract Year. The compensation due to shortfall in generation shall be applied to the amount of shortfall in generation during the Contract Year. The amount of compensation shall be equal to the compensation payable (including equivalent amount of Electricity purchased from the grid for meeting load demand due to short fall in solar power) by the buying Entity, which shall ensure that the buying Entity is offset for all potential costs associated with low generation and supply of power under the PPA, subject to a minimum of 50% (fifty per cent) of the cost of this shortfall in energy terms, calculated at PPA tariff. The amount, being equal to the compensation payable, by the buying Entity for not meeting load requirements is only a measure of damage. It shall not be construed that the compensation is payable by SPD only if the buying Entity are required to pay compensation for such not meeting of load requirements or that the buying Entity or the SPD shall be required to prove or establish such payment of compensation for not meeting the load. SPD shall agree that the methodology specified herein above for calculation of liquidated damages payable by the SPD for shortfall in generation is a genuine and accurate pre-estimation of the actual loss that will be suffered by buying Entity. SPD shall further acknowledge that a breach of any of the obligations contained herein result in injuries and that the amount of the liquidated damages or the method of calculating the liquidated damages specified in this document is a genuine and reasonable pre-estimate of the damages that may be suffered by buying Entity in each case specified under this Agreement. However, this compensation shall not be applicable in events of Force Majeure identified under the PPA with MSPDCL, affecting supply of power by the SPD to the Buying Entity.

  • Interconnection Customer Authority Consistent with Good Utility Practice, this LGIA, and the CAISO Tariff, the Interconnection Customer may take actions or inactions with regard to the Large Generating Facility or the Interconnection Customer’s Interconnection Facilities during an Emergency Condition in order to (i) preserve public health and safety, (ii) preserve the reliability of the Large Generating Facility or the Interconnection Customer’s Interconnection Facilities,

  • SS7 Network Interconnection 9.7.1 SS7 Network Interconnection is the interconnection of Global Connection local signaling transfer point switches or Global Connection local or tandem switching systems with BellSouth signaling transfer point switches. This interconnection provides connectivity that enables the exchange of SS7 messages among BellSouth switching systems and databases, Global Connection local or tandem switching systems, and other third-party switching systems directly connected to the XxxxXxxxx XX0 network.

  • Network Interconnection 26.1 Interconnection between the networks of different SERVICE PROVIDERs shall be as per National Standards of CCS No.7 issued from time to time by Telecom Engineering Centre (TEC) and also subject to technical feasibility and technical integrity of the Networks and shall be within the overall framework of interconnection regulations issued by the TRAI from time to time. However, if situation so arises, INTERCONNECTION with R2MF signaling may be permitted by LICENSOR.

  • Interconnection Customer Interconnection Facilities Interconnection Customer shall design, procure, construct, install, own and/or control Interconnection Customer Interconnection Facilities described in Appendix A, Interconnection Facilities, Network Upgrades and Distribution Upgrades, at its sole expense.

  • Interconnection Customer’s Interconnection Facilities The Interconnection Customer shall design, procure, construct, install, own and/or control the Interconnection Customer’s Interconnection Facilities described in Appendix A at its sole expense.