Cost of General Conditions. The Cost of General Conditions shall have the meaning set forth in Section 8.2 of this Agreement.
Cost of General Conditions. Items included in the Cost of General Conditions are all items necessary to perform Construction Phase Services described herein including, but not limited to:
.1 Cost of construction staff (only staff stationed in the field is reimbursable; however, exceptions will be made for scheduling, cost estimating and accounting services if such functions are normally provided by the Design-Builder’s regional and/or home office personnel)
.2 Fringe Benefits associated with field staff costs .3 Payroll taxes and payroll insurance associated with field staff costs .4 Staff costs associated with obtaining permits and approvals .5 Out-of-house consultants .6 Field office for CM including but not limited to: (i) trailer purchase and/or rent;
Cost of General Conditions. The Design-Builder’s general condition costs shall be reimbursable at cost and without xxxx-up. Only the following items, however are reimbursable: (Any other items or expenses are non-reimbursable and the Design-Builder shall use its fee to cover any additional cost items):
Cost of General Conditions. Items included in the Cost of General Conditions are all items necessary to perform Construction Phase Services described herein including, but not limited to:
9.2.1. Cost of Construction Staff, as defined below. Only staff stationed in the field is reimbursable; however, exceptions may be made for Project executive personnel, purchasing scheduling, cost estimating, local participation oversight and reporting and accounting services if such functions are normally provided by the Design-Builder’s regional and/or home office personnel and/or if Design-Builder deems that such functions are more efficiently performed at the regional and/or home office(s). The term “Construction Staff” shall mean the Project executive, project managers and superintendents assigned to the project, administrative and professional staff performing scheduling, cost estimating and accounting services assigned on a full-time basis to the Project site;
Cost of General Conditions. Items included in the Cost of General Conditions are all items necessary to perform Construction Phase Services described herein including, but not limited to:
Cost of General Conditions. The Contractor’s general conditions costs shall be reimbursable at cost and without mark-up. Only the following items, however, are reimbursable (any other items or expenses are non- reimbursable and the Contractor shall use its fee to cover any additional cost items):
9.2.1 Cost of Construction Staff, as defined below. Only staff stationed in the field is reimbursable; however, exceptions may be made for Project executive personnel, purchasing scheduling, cost estimating, local participation oversight and reporting and accounting services if such functions are normally provided by the Contractor’s regional and/or home office personnel and/or if Contractor deems that such functions are more efficiently performed at the regional and/or home office(s). The term “Construction Staff” shall mean the Project executive, project managers and superintendents assigned to the project, administrative and professional staff performing scheduling, cost estimating and accounting services assigned on a full-time basis to the Project site;
Cost of General Conditions. Items included in the Cost of General Conditions are all items necessary to perform Construction Phase Services described herein including, but not limited to:
9.2.1 Cost of Construction Staff, as defined below. Only staff stationed in the field is reimbursable; however, exceptions may be made for Project executive personnel, purchasing scheduling, cost estimating, local participation oversight and reporting and accounting services if such functions are normally provided by the Design-Builder’s regional and/or home office personnel and/or if Design-Builder deems that such functions
Cost of General Conditions. The Design-Builder’s general condition costs shall be reimbursable at cost and without mark-up. Only the following items, however, are reimbursable: (Any other items or expenses are non- reimbursable, and the Design-Builder shall use its fee to cover any additional cost items)
9.2.1 The cost of “construction staff”. The term construction staff shall mean the Project Executive, project managers and superintendents assigned to the Project, administrative and professional staff performing scheduling, cost estimating and accounting services assigned on a full-time basis to the Project site;
9.2.2 Fringe Benefits associated with construction staff;
9.2.3 Payroll taxes and payroll insurance associated with construction staff;
9.2.4 Staff costs associated with obtaining permits and approvals;
9.2.5 Out-of-house consultants;
9.2.6 Field office for the Design-Builder including but not limited to: (i) trailer purchase and/or rent; (ii) field office installation, relocation and removal;
Cost of General Conditions. The Design-Builder’s general condition costs shall be reimbursable at cost and without xxxx-up. Only the following items, however are reimbursable: (Any other items or expenses are non-reimbursable and the Design-Builder shall use its fee to cover any additional cost items):
9.2.1 The cost of “construction staff”. The term construction staff shall mean the Project Executive, project managers and superintendents assigned to the Project, administrative and professional staff performing scheduling, cost estimating and accounting services assigned on a full-time basis to the Project site;
9.2.2 Fringe Benefits associated with construction staff;
9.2.3 Payroll taxes and payroll insurance associated with construction staff;
9.2.4 Staff costs associated with obtaining permits and approvals; 9.
Cost of General Conditions. The Design-Builder’s Lump Sum General Conditions Cost shall be the extent of what the Design- Builder is entitled to recover for the cost of General Conditions. General Conditions may include, but are not limited to:
a) Cost of construction staff;
b) Fringe Benefits associated with construction staff;
c) Payroll taxes and payroll insurance associated with construction staff;
d) Staff costs associated with obtaining permits and approvals;
e) Out-of-house consultants, including permit expeditors;
f) Job vehicles;
g) The field office(s) for the Design-Builder and Department, including, but not limited to:
(i) trailer purchase and/or rental; (ii) field office installation, relocation and removal; (iii) utility connections and charges during the Construction Phase; (iv) furniture; (v) office supplies;
h) Office equipment including, but not limited to: (i) computer hardware and software; (ii) fax machines; (iii) copying machines; (iv) voice/data system installation and use charges;