Facility Output and Capacity Interconnection Rights Sample Clauses

Facility Output and Capacity Interconnection Rights i. For a new Generating Facility, provide the following information: Total Requested Capacity Interconnection Rights, in Megawatts ii. For a requested increase in generation capability of an existing Generating Facility, identify the Generating Facility and provide the following information: Existing Requested Increase Total Maximum Facility Output (maximum injection at the POI), in Megawatts Capacity Interconnection Rights, in Megawatts iii. For a new Behind the Meter Generating Facility, provide the following information: Behind the Meter Load in Megawatts (the sum of auxiliary load and any other load to be served behind the meter) Total Requested Maximum Facility Output (maximum injection at the POI), in Megawatts iv. For a requested increase in generation capability of an existing Behind the Meter Generating Facility, identify the Generating Facility and provide the following information: Existing Increase Total Gross Output in Megawatts Behind the Meter Load in Megawatts (the sum of auxiliary load and any other load to be served behind the meter) Maximum Facility Output (maximum injection at the POI), in Megawatts Capacity Interconnection Rights, in Megawatts
AutoNDA by SimpleDocs
Facility Output and Capacity Interconnection Rights i. For a new Generating Facility, provide the following information: Total Requested Capacity Interconnection Rights, in Megawatts ii. For a requested increase in generation capability of an existing Generating Facility, identify the Generating Facility and provide the following information: Existing Requested Increase Total Maximum Facility Output (maximum injection at the POI), in Megawatts Capacity Interconnection Rights, in Megawatts iii. For a new Behind the Meter Generating Facility, provide the following information: Behind the Meter Load in Megawatts (the sum of auxiliary load and any other load to be served behind the meter) Total Requested Maximum Facility Output (maximum injection at the POI), in Megawatts iv. For a requested increase in generation capability of an existing Behind the Meter Generating Facility, identify the Generating Facility and provide the following information: Existing Increase Total Gross Output in Megawatts Behind the Meter Load in Megawatts (the sum of auxiliary load and any other load to be served behind the meter) Maximum Facility Output (maximum injection at the POI), in Megawatts Capacity Interconnection Rights, in Megawatts g. Provide a description of the equipment configuration and electrical design specifications for the Generating Facility, as further defined in the PJM Manuals and reflected in the single-line diagram. h. Specify the fuel type of the Generating Facility. i. If the Generating Facility will be a multi-fuel Generating Facility, or if a proposed increase in generation capability of an existing Generating Facility will create a multi-fuel Generating Facility, describe the physical and electrical configuration in as much detail as possible. j. If the Generating Facility will include storage device(s), will the storage device(s) be charged using energy from the Transmission System at any time? If yes, specify the maximum that will be withdrawn from the Transmission System at any time: MWh (or kWh) If yes, provide other technical and operating information on the storage device(s) as set forth in the PJM Manuals, including MWh stockpile and hour class, as applicable. k. If the Generating Facility will include storage, provide the primary frequency response operating range for the electric storage component, as described in the PJM Manuals. Minimum State of Charge: Maximum State of Charge: l. For a Behind the Meter Generating Facility, provide the following information (note that all of the provisions in T...

Related to Facility Output and Capacity Interconnection Rights

  • Capacity Interconnection Rights Pursuant to and subject to the applicable terms of the Tariff, the Interconnection Customer shall have Capacity Interconnection Rights at the Point(s) of Interconnection specified in this Interconnection Service Agreement in the amount of 33.6

  • Interconnection Customer’s Interconnection Facilities The Interconnection Customer shall design, procure, construct, install, own and/or control the Interconnection Customer’s Interconnection Facilities described in Appendix A at its sole expense.

  • Interconnection Facility Options The Intercarrier Compensation provisions of this Agreement shall apply to the exchange of Exchange Service (EAS/Local) traffic between CLEC's network and Qwest's network. Where either Party acts as an IntraLATA Toll provider, each Party shall xxxx the other the appropriate charges pursuant to its respective tariff or price lists. Where either Party interconnects and delivers traffic to the other from third parties, each Party shall xxxx such third parties the appropriate charges pursuant to its respective tariffs, price lists or contractual offerings for such third party terminations. Absent a separately negotiated agreement to the contrary, the Parties will directly exchange traffic between their respective networks without the use of third party transit providers.

  • Interconnection Facilities 4.1.1 The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 of this Agreement. The NYISO, in consultation with the Connecting Transmission Owner, shall provide a best estimate cost, including overheads, for the purchase and construction of its Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, the NYISO, and the Connecting Transmission Owner. 4.1.2 The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with (1) owning, operating, maintaining, repairing, and replacing its own Interconnection Facilities, and

  • Participating TO’s Interconnection Facilities The Participating TO shall design, procure, construct, install, own and/or control the Participating TO’s Interconnection Facilities described in Appendix A at the sole expense of the Interconnection Customer. Unless the Participating TO elects to fund the capital for the Participating TO’s Interconnection Facilities, they shall be solely funded by the Interconnection Customer.

  • NYISO and Connecting Transmission Owner Obligations Connecting Transmission Owner and NYISO shall cause the New York State Transmission System and the Connecting Transmission Owner’s Attachment Facilities to be operated, maintained and controlled in a safe and reliable manner in accordance with this Agreement and the NYISO Tariffs. Connecting Transmission Owner and NYISO may provide operating instructions to Developer consistent with this Agreement, NYISO procedures and Connecting Transmission Owner’s operating protocols and procedures as they may change from time to time. Connecting Transmission Owner and NYISO will consider changes to their respective operating protocols and procedures proposed by Developer.

  • Interconnection Customer Obligations The Interconnection Customer shall maintain the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities in a safe and reliable manner and in accordance with this LGIA.

  • Interconnection Facilities Engineering Procurement and Construction Interconnection Facilities, Network Upgrades, and Distribution Upgrades shall be studied, designed, and constructed pursuant to Good Utility Practice. Such studies, design and construction shall be based on the assumed accuracy and completeness of all technical information received by the Participating TO and the CAISO from the Interconnection Customer associated with interconnecting the Large Generating Facility.

  • Interconnection Customer Drawings Within one hundred twenty (120) days after the date of Initial Operation, unless the Interconnection Parties agree on another mutually acceptable deadline, the Interconnection Customer shall deliver to the Transmission Provider and the Interconnected Transmission Owner final, “as-built” drawings, information and documents regarding the Customer Interconnection Facilities, including, as and to the extent applicable: a one-line diagram, a site plan showing the Customer Facility and the Customer Interconnection Facilities, plan and elevation drawings showing the layout of the Customer Interconnection Facilities, a relay functional diagram, relaying AC and DC schematic wiring diagrams and relay settings for all facilities associated with the Interconnection Customer's step-up transformers, the facilities connecting the Customer Facility to the step-up transformers and the Customer Interconnection Facilities, and the impedances (determined by factory tests) for the associated step-up transformers and the Customer Facility. As applicable, the Interconnection Customer shall provide Transmission Provider and the Interconnected Transmission Owner specifications for the excitation system, automatic voltage regulator, Customer Facility control and protection settings, transformer tap settings, and communications.

  • System Upgrade Facilities and System Deliverability Upgrades Connecting Transmission Owner shall design, procure, construct, install, and own the System Upgrade Facilities and System Deliverability Upgrades described in Appendix A hereto. The responsibility of the Developer for costs related to System Upgrade Facilities and System Deliverability Upgrades shall be determined in accordance with the provisions of Attachment S to the NYISO OATT.