Failure to Meet Commercial Operation Deadline Sample Clauses

Failure to Meet Commercial Operation Deadline. Subject to Seller’s right to extend the Commercial Operation Deadline as provided in Section 1.04, Section 3.06(c), and Section 5.03 (for Force Majeure where Seller is the Claiming Party), in the event that (i) Seller and SCE mutually agree that Commercial Operation will not occur on or before the Commercial Operation Deadline; (ii) the Commercial Operation Date will not occur due to any termination of this Agreement as a result of an Event of Default by Seller occurring on or before the Commercial Operation Deadline; or (iii) Seller abandons the Generating Facility, SCE shall be entitled to: (A) The entire Development Security, including the right to draw on and retain for its sole benefit any Letter of Credit and the proceeds thereof, as well as any cash, posted as Development Security; and (B) Terminate this Agreement; If SCE terminates this Agreement pursuant to this Section 3.06(d), any amount of Development Security that Seller has not yet posted with SCE will be immediately due and payable by Seller to SCE. In addition, subject to Section 2.04(b), if SCE terminates this Agreement pursuant to this Section 3.06(d), neither Party shall have liability for damages for failure to deliver or purchase Product after the effective date of such termination, and the Forward Settlement Amount will be Zero dollars ($0).
AutoNDA by SimpleDocs
Failure to Meet Commercial Operation Deadline. Subject to Seller’s right to extend the Commercial Operation Deadline as provided in Section 3.06(c), Section 1.04, and Section 5.03 (for Force Majeure where Seller is the Claiming Party), in the event that (A) the Commercial Operation Date does not occur, or Seller and SCE mutually agree will not occur, on or before the Commercial Operation Deadline (including due to any termination of this Agreement as a result of an Event of Default by Seller occurring prior to the Commercial Operation Deadline); (B) an interconnection request application is not submitted within one hundred twenty (120) days after the applicable date set forth in the Milestone Schedule; (C) groundbreaking for the Generating Facility does not occur within ninety (90) days after the applicable date set forth in the Milestone Schedule; (D) the procurement of [the applicable electrical generating equipment] for the Generating Facility does not occur within ninety (90) days after the applicable date set forth in the Milestone Schedule; (E) close of construction financing for the Generating Facility is not completed within one hundred twenty (120) days after the applicable date set forth in the Milestone Schedule; or (F) abandonment of the Generating Facility, SCE shall be entitled to: 1. Retain the entire Development Security, including the right to draw on and retain for its sole benefit any Letter of Credit and the proceeds thereof, as well as any cash, posted as Development Security; and 2. Terminate this Agreement. In addition, subject to Section 2.06(b), neither Party shall have liability for damages for failure to deliver or purchase Product after the effective date of such termination.
Failure to Meet Commercial Operation Deadline. Subject to Seller’s right to extend the Commercial Operation Deadline as provided in Section 1.03, Section 3.06(c), and Section 5.03(for Force Majeure where Seller is the Claiming Party), in the event that the Commercial Operation Date does not occur on or before the Commercial Operation Deadline, then Anaheim shall, subject to the proviso following Section 3.06(d)(ii), be entitled to: (i) Retain the entire Development Security, including the right to draw on and retain for its sole benefit any Letter of Credit and the proceeds thereof, posted as Development Security; and (ii) Terminate this Agreement; (iii) If Anaheim terminates this Agreement pursuant to this Section 3.06(d), any amount of Development Security that Seller has not yet posted with Anaheim will be immediately due and payable by Seller to Anaheim. (iv) In addition, subject to Section 2.06(b), neither Party shall have liability for damages for failure to deliver or purchase Product after the effective date of such termination; provided however, such termination does not alter Seller's obligation to deliver the RECs that are associated with previously sold and purchased Product.
Failure to Meet Commercial Operation Deadline. Subject to Seller’s right to extend the Commercial Operation Deadline as provided in Section 1.04, Section 3.06(c), and Section 5.03 (for Force Majeure where Seller is the Claiming Party), in the event that (A) the Commercial Operation Date does not occur, or (B) Anaheim reasonably determines that the Commercial Operation Date will be unlikely to occur (including due to any termination of this Agreement as a result of an Event of Default by Seller occurring prior to the Commercial Operation Deadline) on or before the Commercial Operation Deadline, then, in either case (A) or (B), Anaheim shall, subject to the proviso following Section 3.06(d)(ii), be entitled to: (i) Retain the entire Development Security, including the right to draw on and retain for its sole benefit any Letter of Credit and the proceeds thereof, posted as Development Security; and (ii) Terminate this Agreement; provided, Anaheim shall give Notice to Seller of Anaheim’s determination under this Section 3.06(d) that the Commercial Operation Date is unlikely to occur on or before the Table of Contents Commercial Operation Deadline, and if within thirty (30) days from the date of such Notice Seller can establish to Anaheim’s reasonable satisfaction that Commercial Operation Date is likely to occur on or before the Commercial Operation Deadline, Anaheim may not terminate the Agreement prior to the Commercial Operation Deadline or retain the Development Security at that time, but shall retain all other rights under this Agreement, including the right to terminate the Agreement and retain the entire Development Security if the Commercial Operation Date does not occur on or before the Commercial Operation Deadline in accordance with clause (A) of the first paragraph of this Section 3.06(d). (iii) If Anaheim terminates this Agreement pursuant to this Section 3.06(d), any amount of Development Security that Seller has not yet posted with Anaheim will be immediately due and payable by Seller to Anaheim. (iv) In addition, subject to Section 2.06(b), neither Party shall have liability for damages for failure to deliver or purchase Product after the effective date of such termination; provided however, such termination does not alter Seller’s obligation to deliver the RECs that are associated with previously sold and purchased Product. (v) Notwithstanding anything to the contrary within this Section 3.06(d), the Commercial Operation Deadline shall not be extended beyond the date set forth in Section 1...
Failure to Meet Commercial Operation Deadline. Subject to Seller’s right to extend the Commercial Operation Deadline as provided in Section 1.04, Section 3.06(c), and Section 5.03 (for Force Majeure where Seller is the Claiming Party), in the event that (A) the Commercial Operation Date does not occur, or (B) SCE reasonably determines that the Commercial Operation Date will be unlikely to occur (including due to any termination of this Agreement as a result of an Event of Default by Seller occurring prior to the Commercial Operation Deadline) on or before the Commercial Operation Deadline, then, in either case (A) or (B), SCE shall, subject to the proviso following Section 3.06(d)(ii), be entitled to: (i) Retain the entire Development Security, including the right to draw on and retain for its sole benefit any Letter of Credit and the proceeds thereof, as well as any cash, posted as Development Security; and (ii) Terminate this Agreement. In addition, subject to Section 2.06(b), neither Party shall have liability for damages for failure to deliver or purchase Product after the effective date of such termination.
Failure to Meet Commercial Operation Deadline. (a) Subject to Seller’s right to extend the Guaranteed Commercial Operation Date as provided in Section 2.4 and Section 2.5, in the event that (1) Seller and Buyer mutually agree that Commercial Operation will not occur on or before the Guaranteed Com... (i) The entire Development Security, including the right to draw on and retain for its sole benefit any Letter of Credit and the proceeds thereof, as well as any cash, posted as Development Security; and (ii) Terminate this Agreement. (b) If Buyer terminates this Agreement pursuant to this Section 12.6, any amount of Development Security that Seller has not yet posted with Buyer will be immediately due and payable by Seller to Buyer. In addition, if Buyer terminates this Agreement...

Related to Failure to Meet Commercial Operation Deadline

  • Commercial Operation Date 6.4.1 The SPV shall ensure that the Project Commercial Operation Date is achieved on or prior to the Scheduled Commercial Operation Date. The SPV shall provide a written notice to MSEDCL at least 30 (thirty) days in advance intimating MSEDCL of the proposed date on which the Commercial Operation Date of a Unit or the Project is proposed to be achieved. 6.4.2 If the Commercial Operation Date for the Units having a capacity equivalent to at least 75% (seventy five percent) of the Contracted Capacity is achieved before the Scheduled Commercial Operation Date, then all Units in respect of which the Commercial Operation Date has been achieved prior to the Scheduled Commercial Operation Date would be eligible for incentives as follows: (a) the Unit(s) injecting energy at 11 kV /22 kV shall be given an incentive of Rs. 0.25/ kWh; and (b) the Unit(s) injecting energy at 33 kV shall be given an incentive of Rs. 0.15/ kWh, for the power sold to MSEDCL for the first 3 (three) years from the Commercial Operation Date. To receive such incentives from MSAPL, which shall be over and above the Tariff, the SPV shall follow the process agreed to by the SPV under the Implementation Agreement. 6.4.3 It is hereby clarified that the aforementioned incentive shall not be available: (i) in respect of any Unit if the Commercial Operation Date for such Unit has not been achieved prior to the Scheduled Commercial Operation Date; and (ii) if the aggregate capacity of the Units for which the Commercial Operation Date has been achieved prior to Scheduled Commercial Operation Date is less than 75% (seventy five percent) of the Contracted Capacity. 6.4.4 In the event that Commercial Operation Date for any of the Units is achieved after the Scheduled Commercial Operation Date, the SPV shall be liable to pay Liquidated Damages as per the provisions set out below. 6.4.5 Without prejudice to any other rights of MSEDCL under this PPA, in case one or more Units of the SPV are unable to achieve Commercial Operation Date within a period of 2 (two) months from the Scheduled Commercial Operation Date, the capacity of such Units shall be annulled, and the Contracted Capacity shall be reduced to that extent. For Illustration: The Project has a Contracted Capacity of 100 MW and comprises of 10 Units of 10 MW each. If at the end of the aforementioned period of 14 (fourteen) months from the Effective Date, the SPV has achieved Commissioning for only 8 out of 10 Units, then the Contracted Capacity of the Project will stand reduced for the capacity of the 2 Units which have not been Commissioned, i.e. the Contracted Capacity will be 80 (100 (original Contracted Capacity)) – 10 (capacity of each Unit)*2 (number of Units not Commissioned).

  • Commercial Operation (i) On or before December 31, 2021, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by October 31, 2024.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.

  • Cure Period Prior to any claim for default being made, either the Buyer or Seller will have an opportunity to cure any alleged default. If either Buyer or Seller fails to comply with any provision of this Agreement, the other party will deliver written notice to the non- complying party specifying such non-compliance. The non-complying party shall have calendar days after delivery of such notice to cure the non-compliance.

  • Move-in; Inspection; Delay Before Resident may access or occupy the premises, any required installments or other payments then due (including any Administrative Fee, which is earned and payable upon mutual execution of this Agreement) must be paid in full with cleared funds and guaranty or prepayment requirements satisfied. The application fee (if any) is non-refundable and is not applicable toward any other payments required of Resident under this Agreement. Prior to Resident’s taking possession of the assigned bedroom space (and any re-assigned bedroom space), Resident will conduct an inspection of the assigned bedroom space and apartment and will note on the Check-In/Check-Out Inspection Report (“Inspection Report”) any defects, damage or other conditions observed, if not already identified by Owner on such report; upon completion and approval by Owner, the Inspection Report will become part of this Agreement. At the time of move-out, Resident is encouraged to inspect the bedroom space and apartment with Owner’s representative by making an appointment during business hours at least 48 hours in advance. Within three business days following Resident’s move-out (or, as applicable, following the move-out of all residents of an apartment) at the termination of this Agreement, or within a reasonable time if Resident moves out without notifying Owner, Owner will note the then-present condition of the assigned bedroom space and apartment, including all appliances and fixtures, and any damages incurred and/or extraordinary cleaning deemed necessary by Owner or extraordinary wear as determined by Owner. Resident will promptly pay all costs of restoring the bedroom space and apartment to the same condition upon move-in, less normal wear. Resident acknowledges that except as provided in the Inspection Report, each bedroom space and apartment are being delivered in "as-is" condition, and Resident’s acceptance of the assigned bedroom space and apartment at the beginning of the Term constitutes Resident’s acknowledgment that the bedroom space and apartment and all fixtures are in good repair and condition. Owner will not be responsible for any damages or consequences suffered by Resident as a result of Owner’s inability to timely deliver possession of the apartment or assigned bedroom space to Resident on the anticipated Start Date; in such event, the rent payable will be abated until Owner tenders possession and such delay will not extend or decrease the term or change the End Date. Resident acknowledges that any model apartment at the Property shown to Resident in person, online or through other means is intended to be representative of the general quality and type of construction and materials within apartments. Specific items of décor and furnishings and the actual colors, styles, materials, upholstery and other treatments in the apartment assigned to Resident may vary from those in the model apartment. The actual apartment assigned to Resident may also vary in approximate size, square footage and layout. Resident’s apartment will not include custom lighting, lamps, decorations, linens, unattached appliances or other personal property as may be shown in the model apartment.

  • Response Time PROVIDING PARTY shall respond to and resolve any problems in connection with the Corporate Services for RECEIVING PARTY within a commercially reasonable period of time, using response and proposed resolution times consistent with its response and resolution of such problems for itself.

  • Extended Reporting Period If any required insurance coverage is on a claims-made basis (rather than occurrence), Contractor shall maintain such coverage for a period of no less than three (3) years following expiration or termination of the Contract.

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least fifteen (15) days written notice to the SLDC / ALDC / DISCOM as the case may be, of the date on which it intends to synchronize the Power Project to the Grid System. 4.1.2 Subject to Article 4.1.1, the Power Project may be synchronized by the Power Producer to the Grid System when it meets all the connection conditions prescribed in the Grid Code and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 4.1.3 The synchronization equipment and all necessary arrangements / equipment including Remote Terminal Unit (RTU) for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the Power Producer at its generation facility of the Power Project at its own cost. The Power Producer shall synchronize its system with the Grid System only after the approval of GETCO / SLDC / ALDC and GEDA. 4.1.4 The Power Producer shall immediately after each synchronization / tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. 4.1.5 The Power Producer shall commission the Project within SCOD. 4.1.6 The Power Producer shall be required to obtain Developer and/ or Transfer Permission, Key Plan drawing etc, if required, from GEDA. In cases of conversion of land from Agricultural to Non-Agriculture, the commissioning shall be taken up by GEDA only upon submission of N.A. permission by the Power Producer. 4.1.7 The Power Producer shall be required to follow the Forecasting and Scheduling procedures as per the Regulations issued by Hon’ble GERC from time to time. It is to clarify that in terms of GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2019 the procedures for Forecasting, Scheduling & Deviation Settlment are applicable to all solar generators having combined installed capacity above 1 MW connected to the State Grid / Substation including those connected via pooling stations.