Final Acceptance Deadline. DB Contractor shall achieve Final Acceptance on or before 120 days after Substantial Completion of the Project. Said deadline for achieving Final Acceptance, as it may be extended hereunder, is referred to herein as the “Final Acceptance Deadline.”
Final Acceptance Deadline. Developer shall achieve Final Acceptance on or before 120 days after Substantial Completion. Said deadline for achieving Final Acceptance, as it may be extended hereunder, is referred to herein as the “Final Acceptance Deadline.”
Final Acceptance Deadline. (+ or - days from base of calendar days after Substantial Completion) Justification for Request for Change Order with reference to the Design-Build Agreement: Change order required under Capital Maintenance Contract? Yes /No If yes, state reason:
8.3.1 6 For overhead, superintendence, profit, and small tools (see General Conditions Section 4.6.8.
1) 7 Revise list of Completion Deadlines if applicable to the Project The undersigned Authorized Representative of DB Contractor hereby certifies, under penalty of xxxxxxx, as follows:
(a) the above three sections represent a true and complete summary of all aspects of this Request for Change Order;
(b) the amount of time and/or compensation requested is justified as to entitlement and amount;
(c) this Request for Change Order includes all known and anticipated impacts or amounts, direct, indirect and consequential, which may be incurred as a result of the claim, event, occurrence or matter giving rise to the proposed change;
(d) the cost and pricing data forming the basis for the Request for Change Order is complete, accurate and current; and
(e) There has been no change to the disclosure of Interested Parties (as that term is defined in § 2252.908 of the Texas Government Code and in 1 T.A.C. § 46.4) that was made by DB Contractor in the most recent Form 1295 disclosure of interested parties form provided to TxDOT by DB Contractor. Alternatively, if there has been a change to the disclosure of Interested Parties or if the value of this Change Order is $1,000,000 or greater, DB Contractor has submitted with this Change Order a current Form 1295. This certification does not apply, and submission of a current Form 1295 is not required, in the event that DB Contractor is a publicly traded business entity, or is a wholly owned subsidiary of a publicly traded business entity. If the foregoing Request for Change Order includes claims of Subcontractors or Suppliers, the undersigned have reviewed such claims and have determined in good faith that the claims are justified as to both entitlement and amount.
Final Acceptance Deadline. 24 Developer shall achieve Final Acceptance of the Project not later than the Final 25 Acceptance Deadline.
Final Acceptance Deadline. Design-Build Contractor shall achieve Final Acceptance no later than [to be inserted from Form L of Proposer’s Proposal]. Such deadline, as it may be extended hereunder, is referred to herein as the “Final Acceptance Deadline.”
Final Acceptance Deadline. (+ or - days from base of calendar days after Substantial Completion) Justification for Request for Change Order with reference to the Agreement:
Final Acceptance Deadline. DBT shall achieve Final Acceptance of the Project no later than the Final Acceptance Deadline.
Final Acceptance Deadline. (+ or - days from base of calendar days after Substantial Completion)
Final Acceptance Deadline. Contractor shall achieve Final Acceptance no later than [120] days after it achieves Substantial Completion.
Final Acceptance Deadline. Integrator shall achieve Project Segment Final Acceptance of each Project Segment within 120 Days after Project Segment System Acceptance of such Project Segment. Each such deadline for achieving Final Acceptance, as it may be extended hereunder, is referred to herein as a Project Segment “Final Acceptance Deadline.”