Completion Deadlines Sample Clauses

Completion Deadlines. CMR shall achieve Substantial Completion and Final Completion within the time periods specified in the GMP Amendment. In the event the Project is to be constructed in phases (or with interim construction milestones), each phase (or with interim construction milestones) must be constructed within the period of time specified by TFC.
Completion Deadlines. Member shall have said home and, weather permitting, landscaping open and ready for display on the opening date as established by the Association. If the Member starts construction and is unable or unwilling to have the show house and landscaping open and ready for display at the opening date, the Member agrees to continue to work on said house, only during non-show hours, until completion.
Completion Deadlines. The ITP requires the DB Contractor to propose the Completion Deadlines as described in Exhibit B. All references in the Contract Documents to the Completion Deadlines shall be deemed to be to those deadlines set forth in Exhibit B. Substantial Completion, Final Completion, and Final Acceptance shall be in accordance with the terms and conditions set forth in Section 22.
Completion Deadlines. 4.3.1 Abutment B Completion Deadline
Completion Deadlines. DB shall achieve Substantial Completion and Final Completion within the time periods specified in the Design-Build Proposal. In the event the Project is to be constructed in phases (or with interim construction milestones), each phase (or with interim construction milestones) must be constructed within the period of time specified by TFC.
Completion Deadlines. TRG shall comply with the deadlines in the SEP proposal. The deadlines shall begin with the effective date of this Order.
Completion Deadlines. ESG funds have specific expenditure deadlines and failure to meet these deadlines may result in de-obligation of funds by HUD and cancellation of this contract by Brazoria County. Contractor shall supply a project schedule of completion and shall be attached hereto and expressly incorporated herein by reference and made a part hereof. Brazoria County has allocated the following funds to this project as a whole: FY 2019 ESG $48,998.82; FY 2020 ESG funds $80,000.00 and $1,125,985.00 in ESG-CV (CARES Act) funding for a project total of $1,254,983.82, (Engineering, Asbestos Abatement, and soft costs are also included in this figure). The following expenditure deadlines must be strictly adhered to. FY 2019 ESG funds of $48,998.82 and 20% of the ESG-CV funds ($225,197.00) must be expended by September 30, 2021. The remaining 80% of ESG-CV funds ($900,788.00) must be expended by March 31, 2022, with all other remaining funds ($80,000.00) expended by September 30, 2022. In the even that expenditure deadlines have not been met and HUD de-obligates funds, The Salvation Army shall be responsible to repay all expenditures to Brazoria County and any outstanding invoices to the contractor.
Completion Deadlines. Under the Vendor Contracts , the Contractor performing construction work is obligated to commence construction upon the receipt of all necessary Permits and to thereafter diligently prosecute same to Final Completion, all in accordance with the Project Schedule, the Plans and the Project Budget. The current estimated substantial completion date for the Wireless Towers, Fiber, and Microwaves in the Project Schedule is between , and , which is the “On Air Milestone 19” in the Project Schedule for the Wireless Towers, Fiber, and Microwaves (the “Substantial Completion Deadlines”), and the current estimated Final Completion Deadline for all of the Wireless Towers, Fiber, and Microwaves is (the “Final Completion Deadline”), subject to extension for Excusable Conditions and Excusable Delays under this Agreement. In the event that Excusable Conditions create an increase in the Project Budget or an extension of the Project Schedule, Developer will submit an estimate of the impact of the Excusable Conditions on the Project Schedule and/or Project Budget, which the Parties will agree upon in a Change Order.
Completion Deadlines. 17.2.1 Deadlines for Substantial Completion and Final Completion
Completion Deadlines. 4.1 Work section 1, Optimization of the H.320-MVP Codec, Type "A" Ready for approval: 10/16/95 -------------------------------------------------------------------------------- 7 General Cooperation Agreement concerning Joint Further Development of the IAT/Deutsche Telekom Software Codec on the Basis of the Texas Instruments Parallel Processor TMS320C8x -------------------------------------------------------------------------------- 4.2 Work section 2, Integration of JPEG Codec and H.320, Type "B" Ready for approval: 4/30/96 4.3 Work section 3, Integration of MPEG1 Decoder and H.320, Type "B" Ready for approval: 6/30/96 4.4 Work section 4, MVP Codec for MFKS, Type "A" Ready for approval: 10/31/95 4.5 Work section 5, MPEG1 Decoder, Type "B" Ready for approval: 6/30/96 4.6 Work section 6, Expansion of H.320 multi-point capable, Type "A" Ready for approval: 6/30/96 4.7 Work section 7, MPEG2 Decoder, Type "C" Ready for approval: 6/30/96