General Coordination. 5.1.1 Contractor’s Pre-Construction Phase Services team shall attend Project Team meetings with Owner, Owner representatives, and A/E at regularly scheduled intervals throughout the Pre-Construction Phase. Frequent Project Team meetings are anticipated prior to Owner acceptance of the GMP and during completion of the Construction Documents. 5.1.2 Provide a preliminary evaluation of “Facility Design Guidelines”, Program of Requirements and the AACC, each in terms of the other. 5.1.3 Review and understand the standards and requirements in Owner’s Specifications and perform all services in accordance with those standards and requirements. 5.1.4 Visit the site and inspect the existing facilities, systems and conditions to ensure an accurate understanding of the existing conditions as required. 5.1.5 Participate as a member of the Project Team in the development of the Program of Requirements if such program has not been developed prior to the Effective Date of this Agreement. 5.1.6 Provide recommendations and information to the Project Team on: site usage and site improvements; building systems, equipment and construction feasibility; selection and availability of materials and labor; time requirements for installation and construction; assignment of responsibilities for safety precautions and programs; temporary Project facilities; equipment, materials and services for common use of Contractor and Owner’s separate contractors, if any; cost factors, including costs of alternative materials or designs, preliminary budgets, and possible cost savings; recognizing and tracking the resolution of conflicts in the proposed Drawings and Specifications; methods of delivery of materials, systems, and equipment; and any other matters necessary to accomplish the Project in accordance with the Work Progress Schedule (as defined below) and the AACC. Notwithstanding the above, Contractor shall not be required to provide A/E services unless specifically required by the Contract Documents and Contractor’s recommendations and information are furnished in its capacity as a Contractor. 5.1.7 Assist Owner in selecting and directing the services of existing facility surveys, testing and balancing, environmental surveys or other special consultants hired by Owner to develop additional information for the design or construction of the Project. 5.1.8 At Owner’s request, attend public meetings and hearings concerning the development and schedule of the Project. 5.1.9 Contractor shall use all Construction Documents returned to A/E from the Subcontractor proposers.
Appears in 39 contracts
Samples: Construction Manager at Risk Agreement, Construction Management Agreement, Construction Management Agreement
General Coordination. 5.1.1 Contractor’s Pre-Construction Phase Services team shall attend Project Team meetings with Owner, Owner representatives, and A/E at regularly scheduled intervals throughout the Pre-Construction Phase. Frequent Project Team meetings are anticipated prior to Owner acceptance of the GMP and during completion of the Construction Documents.
5.1.2 Provide a preliminary evaluation of “Facility Design Guidelines”, Program of Requirements and the AACC, each in terms of the other.
5.1.3 Review and understand the standards and requirements in Owner’s Specifications and perform all services in accordance with those standards and requirements.
5.1.4 Visit the site and inspect the existing facilities, systems and conditions to ensure an accurate understanding of the existing conditions as required.
5.1.5 Participate as a member of the Project Team in the development of the Program of Requirements if such program has not been developed prior to the Effective Date of this Agreement.
5.1.6 Provide recommendations and information to the Project Team on: site usage and site improvements; building systems, equipment and construction feasibility; selection and availability of materials and labor; time requirements for installation and construction; assignment of responsibilities for safety precautions and programs; temporary Project facilities; equipment, materials and services for common use of Contractor and Owner’s separate contractors, if any; cost factors, including costs of alternative materials or designs, preliminary budgets, and possible cost savings; recognizing and tracking the resolution of conflicts in the proposed Drawings and Specifications; methods of delivery of materials, systems, and equipment; and any other matters necessary to accomplish the Project in accordance with the Work Progress Schedule (as defined below) and the AACC. Notwithstanding the above, Contractor shall not be required to provide A/E services unless specifically required by the Contract Documents and Contractor’s recommendations and information are furnished in its capacity as a Contractor.
5.1.7 Assist Owner in selecting and directing the services of existing facility surveys, testing and balancing, environmental surveys or other special consultants hired by Owner to develop additional information for the design or construction of the Project.
5.1.8 At Owner’s request, attend public meetings and hearings concerning the development and schedule of the Project.
5.1.9 Contractor shall use all Construction Documents returned to A/E from the Subcontractor proposers.
Appears in 17 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract
General Coordination. 5.1.1 Contractor’s Pre-Construction Phase Services team shall attend Project Team meetings with Owner, Owner representatives, and A/E at regularly scheduled intervals throughout the Pre-Construction Phase. Frequent Project Team meetings are anticipated prior to Owner acceptance of the GMP and during completion of the Construction Documents.
5.1.2 Provide a preliminary evaluation of “Facility Design Guidelines”, Program of Requirements and the AACC, each in terms of the other.
5.1.3 Review and understand the standards and requirements in Owner’s Specifications and perform all services in accordance with those standards and requirements.
5.1.4 Visit the site and inspect the existing facilities, systems and conditions to ensure an accurate understanding of the existing conditions as required.
5.1.5 Participate as a member of the Project Team in the development of the Program of Requirements if such program has not been developed prior to the Effective Date of this Agreement.
5.1.6 Provide recommendations and information to the Project Team on: site usage and site improvements; building systems, equipment and construction feasibility; selection and availability of materials and labor; time requirements for installation and construction; assignment of responsibilities for safety precautions and programs; temporary Project facilities; equipment, materials and services for common use of Contractor and Owner’s separate contractors, if any; cost factors, including costs of alternative materials or designs, preliminary budgets, and possible cost savings; recognizing and tracking the resolution of conflicts in the proposed Drawings and Specifications; methods of delivery of materials, systems, and equipment; and any other matters necessary to accomplish the Project in accordance with the Work Progress Schedule (as defined below) and the AACC. Notwithstanding the above, Contractor shall not be required to provide A/E services unless specifically required by the Contract Documents and Contractor’s recommendations and information are furnished in its capacity as a Contractor.
5.1.7 Assist Owner in selecting and directing the services of existing facility surveys, testing and balancing, environmental surveys or other special consultants hired by Owner to develop additional information for the design or construction of the Project.
5.1.8 At Owner’s request, attend public meetings and hearings concerning the development and schedule of the Project.
5.1.9 Contractor shall use all Construction Documents returned to A/E from the Subcontractor proposers.the
Appears in 6 contracts
Samples: Construction Contract, Construction Management Agreement, Construction Contract
General Coordination. 5.1.1 ContractorThe Construction Manager’s Pre-Construction construction Phase Services team shall attend Project Team meetings with the Owner, Owner the Owner’s representatives, and A/E the Project Architect at regularly scheduled intervals throughout the Pre-Construction Phase. Frequent Project Team meetings are anticipated prior to Owner the Owner’s acceptance of the GMP and during completion of the Construction Documents.
5.1.2 Provide a preliminary evaluation of “Facility the Owner’s Design Guidelines”, Program of Requirements Criteria and the AACCConstruction Cost Limitation, each in terms of the other.
5.1.3 Review and understand the standards and requirements in Owner’s Specifications and perform all services in accordance with those standards and requirements.
5.1.4 Visit the site and inspect the existing facilities, systems and conditions to ensure insure an accurate understanding of the existing conditions as required.
5.1.5 Participate as a member of the Project Team in the development of the Project Facility Program of Requirements if such program has not been developed prior to the Effective Date of this Agreement.
5.1.6 Provide recommendations and information to the Project Team on: site usage and site improvements; building systems, equipment and construction feasibility; selection and availability of materials and labor; time requirements for installation and construction; assignment of responsibilities for safety precautions and programs; temporary Project facilities; equipment, materials and services for common use of Contractor the Construction Manager and Owner’s separate contractors, if any; cost factors, including costs of alternative materials or designs, preliminary budgets, and possible cost savings; recognizing and tracking the resolution of conflicts in the proposed Drawings and Specifications; methods of delivery of materials, systems, and equipment; and any other matters necessary to accomplish the Project in accordance with the Work Progress Project Schedule (as defined below) and the AACC. Notwithstanding the above, Contractor shall not be required to provide A/E services unless specifically required by the Contract Documents and Contractor’s recommendations and information are furnished in its capacity as a ContractorCCL.
5.1.7 Assist the Owner in selecting and directing the services of surveyors, soils engineers, existing facility surveys, testing and balancing, environmental surveys or other special consultants hired by the Owner to develop additional information for the design or construction of the Project.
5.1.8 At Owner’s request, attend public meetings and hearings concerning the development and schedule of the Project.
5.1.9 Contractor shall use all Construction Documents returned to A/E from the Subcontractor proposers.
Appears in 5 contracts
Samples: Construction Manager at Risk Agreement, Construction Manager Agreement, Construction Manager Agreement
General Coordination. 5.1.1 ContractorConstruction Manager’s Pre-Construction Phase Services team shall attend Project Team meetings with Owner, Owner Owner’s representatives, and Project A/E at regularly scheduled intervals throughout the Pre-Construction Phase. Frequent Project Team meetings are anticipated prior to Owner Owner’s acceptance of the GMP and during completion of the Construction Documents.
5.1.2 Provide a preliminary evaluation of “Facility Owner’s Design Guidelines”, Program of Requirements Criteria and the AACCConstruction Cost Limitation, each in terms of the other.
5.1.3 Review and understand the standards and requirements in Owner’s Specifications and perform all services in accordance with those standards and requirements.
5.1.4 Visit the site and inspect the existing facilities, systems and conditions to ensure insure an accurate understanding of the existing conditions as required.
5.1.5 Participate as a member of the Project Team in the development of the Project Facility Program of Requirements if such program has not been developed prior to the Effective Date of this Agreement.
5.1.6 Provide recommendations and information to the Project Team on: site usage and site improvements; building systems, equipment and construction feasibility; selection and availability of materials and labor; time requirements for installation and construction; assignment of responsibilities for safety precautions and programs; temporary Project facilities; equipment, materials and services for common use of Contractor Construction Manager and Owner’s separate contractors, if any; cost factors, including costs of alternative materials or designs, preliminary budgets, and possible cost savings; recognizing and tracking the resolution of conflicts in the proposed Drawings and Specifications; methods of delivery of materials, systems, and equipment; and any other matters necessary to accomplish the Project in accordance with the Work Progress Project Schedule (as defined below) and the AACC. Notwithstanding the above, Contractor shall not be required to provide A/E services unless specifically required by the Contract Documents and Contractor’s recommendations and information are furnished in its capacity as a ContractorCCL.
5.1.7 Assist Owner in selecting and directing the services of surveyors, soils engineers, existing facility surveys, testing and balancing, commissioning, environmental surveys or other special consultants hired by Owner to develop additional information for the design or construction of the Project.
5.1.8 At Owner’s request, attend public meetings and hearings concerning the development and schedule of the Project.
5.1.9 Contractor shall use all Construction Documents returned to A/E from the Subcontractor proposers.
Appears in 5 contracts
Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Manager at Risk Agreement
General Coordination. 5.1.1 ContractorThe Construction Manager’s Pre-Construction Phase Services team shall attend Project Team meetings with the Owner, Owner the Owner’s representatives, and A/E the Project Architect at regularly scheduled intervals throughout the Pre-Construction Phase. Frequent Project Team meetings are anticipated prior to Owner the Owner’s acceptance of the GMP and during completion of the Construction Documents.
5.1.2 Provide a preliminary evaluation of “Facility the Owner’s Design Guidelines”, Program of Requirements Criteria and the AACCConstruction Cost Limitation, each in terms of the other.
5.1.3 Review and understand the standards and requirements in Owner’s Specifications and perform all services in accordance with those standards and requirements.
5.1.4 Visit the site and inspect the existing facilities, systems and conditions to ensure insure an accurate understanding of the existing conditions as required.
5.1.5 Participate as a member of the Project Team in the development of the Project Facility Program of Requirements if such program has not been developed prior to the Effective Date of this Agreement.
5.1.6 Provide recommendations and information to the Project Team on: site usage and site improvements; building systems, equipment and construction feasibility; selection and availability of materials and labor; time requirements for installation and construction; assignment of responsibilities for safety precautions and programs; temporary Project facilities; equipment, materials and services for common use of Contractor the Construction Manager and Owner’s separate contractors, if any; cost factors, including costs of alternative materials or designs, preliminary budgets, and possible cost savings; recognizing and tracking the resolution of conflicts in the proposed Drawings and Specifications; methods of delivery of materials, systems, and equipment; and any other matters necessary to accomplish the Project in accordance with the Work Progress Project Schedule (as defined below) and the AACC. Notwithstanding the above, Contractor shall not be required to provide A/E services unless specifically required by the Contract Documents and Contractor’s recommendations and information are furnished in its capacity as a ContractorCCL.
5.1.7 Assist the Owner in selecting and directing the services of surveyors, soils engineers, existing facility surveys, testing and balancing, commissioning, environmental surveys or other special consultants hired by the Owner to develop additional information for the design or construction of the Project.
5.1.8 At Owner’s request, attend public meetings and hearings concerning the development and schedule of the Project.
5.1.9 Contractor shall use all Construction Documents returned to A/E from the Subcontractor proposers.
Appears in 3 contracts
Samples: Construction Manager Agreement, Construction Manager Agreement, Construction Manager Agreement
General Coordination. 5.1.1 Contractor8.1.1 The Construction Manager’s Pre-Construction Phase Services team shall attend Project Team meetings with the Owner, Owner the Owner’s representatives, and A/E the Project Architect at regularly scheduled intervals throughout the Pre-Construction Phase. Frequent DocuSign Envelope ID: 7E438A0C-1BA8-4AEC-AAE6-5E3C9E00ED77 Project Team meetings are anticipated prior to Owner the Owner’s acceptance of the GMP and during completion of the Construction Documents.
5.1.2 8.1.2 Provide a preliminary evaluation of “Facility Design Guidelines”, Program the Project’s proposed Scope of Requirements Work cost components and the AACC, each in terms of the otherCity’s adopted Construction Budget related thereto.
5.1.3 8.1.3 Review and understand the standards and requirements in Owner’s Specifications Geenral Conditions of the Construction Contract and perform all services in accordance with those standards and requirements.
5.1.4 8.1.4 Visit the site and inspect the existing facilitieson-site and off-site conditions, systems and conditions as well as perform preliminary due diligence investigation with regards to ensure an accurate understanding of existing utilities available for the existing conditions as requiredProject.
5.1.5 8.1.5 Participate as a member of the Project Team in the development of the Program of Requirements Project facilities program, if such program has not been developed prior to the Effective Date effective date of this Agreement.
5.1.6 8.1.6 Provide recommendations and information to the Project Team on: site usage and site improvements; building systems, equipment and construction feasibility; selection and availability of materials and labor; time requirements for installation and construction; assignment of responsibilities for safety precautions and programs; temporary Project facilities; equipment, materials and services for common use of Contractor the Construction Manager and Owner’s separate contractorsContractors, if any; cost factors, including costs of alternative materials or designs, preliminary budgets, and possible cost savings; recognizing and tracking the resolution of conflicts in the proposed Drawings and Specifications; methods of delivery of materials, systems, and equipment; and any other matters necessary to accomplish the Project in accordance with the Work Progress Project Schedule (as defined below) approved by the City and the AACC. Notwithstanding the above, Contractor shall not be required to provide A/E services unless specifically required by the Contract Documents and Contractor’s recommendations and information are furnished in its capacity as a Contractoradopted Construction Budget.
5.1.7 8.1.7 Assist Owner the Owner, if needed, in selecting and directing the services of surveyors, soils engineers, existing facility surveys, testing and balancing, commissioning, environmental surveys or other special consultants hired by Owner to develop additional information for the design or construction of the Project.
5.1.8 8.1.8 At Owner’s request, attend public meetings and hearings concerning the development and schedule progress of the Project.
5.1.9 Contractor shall use all Construction Documents returned to A/E from the Subcontractor proposers.
Appears in 1 contract
General Coordination. 5.1.1 Contractor’s Pre-Construction Phase Services team shall attend Project Team meetings with Owner, Owner representatives, and A/E at regularly scheduled intervals throughout the Pre-Construction Phase. Frequent Project Team meetings are anticipated prior to Owner acceptance of the GMP and during completion of the Construction Documents.
5.1.2 Provide a preliminary evaluation of “Facility Design Guidelines”, Program of Requirements and the AACC, each in terms of the other.
5.1.3 Review and understand the standards and requirements in Owner’s Specifications and perform all services in accordance with those standards and requirements.
5.1.4 Visit the site and inspect the existing facilities, systems and conditions to ensure an accurate understanding of the existing conditions as required.
5.1.5 Participate as a member of the Project Team in the development of the Program of Requirements if such program has not been developed prior to the Effective Date of this Agreement.
5.1.6 Provide recommendations and information to the Project Team on: site usage and site improvements; building systems, equipment and construction feasibility; selection and availability of materials and labor; time requirements for installation and construction; assignment of responsibilities for safety precautions and programs; temporary Project facilities; equipment, materials and services for common use of Contractor and Owner’s separate contractors, if any; cost factors, including costs of alternative materials or designs, preliminary budgets, and possible cost savings; recognizing and tracking the resolution of conflicts in the proposed Drawings and Specifications; methods of delivery of materials, systems, and equipment; and any other matters necessary to accomplish the Project in accordance with the Work Progress Schedule (as defined below) and the AACC. Notwithstanding the above, Contractor shall not be required to provide A/E services unless specifically required by the Contract Documents and Contractor’s recommendations and information are furnished in its capacity as a Contractor.
5.1.7 Assist Owner in selecting and directing the services of existing facility surveys, testing and balancing, environmental surveys or other special consultants hired by Owner to develop additional information for the design or construction of the Project.
5.1.8 At Owner’s request, attend public meetings and hearings concerning the development and schedule of the Project.. XXXX BIM Contract No. 5912 03/16 Project No. 04-3195
5.1.9 Contractor shall use all Construction Documents returned to A/E from the Subcontractor proposers.
Appears in 1 contract
General Coordination. 5.1.1 Contractor8.1.1 The Construction Manager’s Pre-Construction Phase Services team shall attend Project Team meetings with Ownerthe Town, Owner the Town’s representatives, and A/E the Project Architect at regularly scheduled intervals throughout the Pre-Construction Phase. Frequent Project Team meetings are anticipated prior to Owner the Town’s acceptance of the GMP and during completion of the Construction Documents.
5.1.2 8.1.2 Provide a preliminary evaluation of “Facility Design Guidelines”, Program the Project’s proposed Scope of Requirements Work cost components and the AACC, each in terms of the otherTown’s adopted Construction Budget related thereto.
5.1.3 8.1.3 Review and understand the standards and requirements in OwnerTown’s Specifications General Conditions of the Construction Contract and perform all services in accordance with those standards and requirements.
5.1.4 8.1.4 Visit the site and inspect the existing facilitieson-site and off-site conditions, systems and conditions as well as perform preliminary due diligence investigation with regards to ensure an accurate understanding of existing utilities available for the existing conditions as requiredProject.
5.1.5 8.1.5 Participate as a member of the Project Team in the development of the Program of Requirements Project facilities program, if such program has not been developed prior to the Effective Date effective date of this Agreement.
5.1.6 8.1.6 Provide recommendations and information to the Project Team on: site usage and site improvements; building systems, equipment and construction feasibility; selection and availability of materials and labor; time requirements for installation and construction; assignment of responsibilities for safety precautions and programs; temporary Project facilities; equipment, materials and services for common use of Contractor the Construction Manager and OwnerTown’s separate contractorsContractors, if any; cost factors, including costs of alternative materials or designs, preliminary budgets, and possible cost savings; recognizing and tracking the resolution of conflicts in the proposed Drawings and Specifications; methods of delivery of materials, systems, and equipment; and any other matters necessary to accomplish the Project in accordance with the Work Progress Project Schedule (as defined below) approved by the Town and the AACC. Notwithstanding the above, Contractor shall not be required to provide A/E services unless specifically required by the Contract Documents and Contractor’s recommendations and information are furnished in its capacity as a Contractoradopted Construction Budget.
5.1.7 8.1.7 Assist Owner the Town, if needed, in selecting and directing the services of surveyors, soils engineers, existing facility surveys, testing and balancing, commissioning, environmental surveys or other special consultants hired by Owner to develop additional information for the design or construction of the Project.
5.1.8 8.1.8 At OwnerTown’s request, attend public meetings and hearings concerning the development and schedule progress of the Project.
5.1.9 Contractor shall use all Construction Documents returned to A/E from the Subcontractor proposers.
Appears in 1 contract
Samples: Construction Management Agreement
General Coordination. 5.1.1 ContractorConstruction Manager’s Pre-Construction Phase Services team shall attend Project Team meetings with Owner, Owner Owner’s representatives, and Project A/E at regularly scheduled intervals throughout the Pre-Construction Phase. Frequent Project Team meetings are anticipated prior to Owner Owner’s acceptance of the GMP and during completion of the Construction Documents.
5.1.2 Provide a preliminary evaluation of “Facility Owner’s Design Guidelines”, Program of Requirements Criteria and the AACCConstruction Cost Limitation, each in terms of the other.
5.1.3 Review and understand the standards and requirements in Owner’s Specifications and perform all services in accordance with those standards and requirements.
5.1.4 Visit the site and inspect the existing facilities, systems and conditions to ensure an accurate understanding of the existing conditions as required.
5.1.5 Participate as a member of the Project Team in the development of the Project Facility Program of Requirements if such program has not been developed prior to the Effective Date of this Agreement.
5.1.6 Provide recommendations and information to the Project Team on: site usage and site improvements; building systems, equipment and construction feasibility; selection and availability of materials and labor; time requirements for installation and construction; assignment of responsibilities for safety precautions and programs; temporary Project facilities; equipment, materials and services for common use of Contractor Construction Manager and Owner’s separate contractors, if any; cost factors, including costs of alternative materials or designs, preliminary budgets, and possible cost savings; recognizing and tracking the resolution of conflicts in the proposed Drawings and Specifications; methods of delivery of materials, systems, and equipment; and any other matters necessary to accomplish the Project in accordance with the Work Progress Project Schedule (as defined below) and the AACC. Notwithstanding the above, Contractor shall not be required to provide A/E services unless specifically required by the Contract Documents and Contractor’s recommendations and information are furnished in its capacity as a ContractorCCL.
5.1.7 Assist Owner in selecting and directing the services of surveyors, soils engineers, existing facility surveys, testing and balancing, commissioning, environmental surveys or other special consultants hired by Owner to develop additional information for the design or construction of the Project.
5.1.8 At Owner’s request, attend public meetings and hearings concerning the development and schedule of the Project.
5.1.9 Contractor shall use all Construction Documents returned to A/E from the Subcontractor proposers.
Appears in 1 contract
Samples: Construction Manager Agreement
General Coordination. 5.1.1 ContractorThe Construction Manager’s Pre-Construction construction Phase Services team shall attend Project Team meetings with the Owner, Owner the Owner’s representatives, and A/E the Project Architect at regularly scheduled intervals throughout the Pre-Construction Phase. Frequent Project Team meetings are anticipated prior to Owner the Owner’s acceptance of the GMP and during completion of the Construction Documents.
5.1.2 Provide a preliminary evaluation of “Facility the Owner’s Design Guidelines”, Program of Requirements Criteria and the AACCConstruction Cost Limitation, each in terms of the other.
5.1.3 Review and understand the standards and requirements in Owner’s Specifications and perform all services in accordance with those standards and requirements.
5.1.4 Visit the site and inspect the existing facilities, systems and conditions to ensure insure an accurate understanding of the existing conditions as required.
5.1.5 Participate as a member of the Project Team in the development of the Project Facility Program of Requirements if such program has not been developed prior to the Effective Date of this Agreement.
5.1.6 Provide recommendations and information to the Project Team on: site usage and site improvements; building systems, equipment and construction feasibility; selection and availability of materials and labor; time requirements for installation and construction; assignment of responsibilities for safety precautions and programs; temporary Project facilities; equipment, materials and services for common use of Contractor the Construction Manager and Owner’s separate contractors, if any; cost factors, including costs of alternative materials or designs, preliminary budgets, and possible cost savings; recognizing and tracking the resolution of conflicts in the proposed Drawings and Specifications; methods of delivery of materials, systems, and equipment; and any other matters necessary to accomplish the Project in accordance with the Work Progress Project Schedule (as defined below) and the AACC. Notwithstanding the above, Contractor shall not be required to provide A/E services unless specifically required by the Contract Documents and Contractor’s recommendations and information are furnished in its capacity as a ContractorCCL.
5.1.7 Assist the Owner in selecting and directing the services of surveyors, soils engineers, existing facility surveys, testing and balancing, commissioning, environmental surveys or other special consultants hired by the Owner to develop additional information for the design or construction of the Project.
5.1.8 At Owner’s request, attend public meetings and hearings concerning the development and schedule of the Project.
5.1.9 Contractor shall use all Construction Documents returned to A/E from the Subcontractor proposers.
Appears in 1 contract
General Coordination. 5.1.1 Contractor’s Pre-Construction construction Phase Services team shall attend Project Team meetings with Owner, Owner representatives, and A/E CM at regularly scheduled intervals throughout the Pre-Construction Phase. Frequent Project Team meetings are anticipated prior to Owner acceptance of the GMP and during completion GMP. Consideration will be given to online meetings to minimize travel time or utilize remote staff prior to start of the Construction Documentsconstruction.
5.1.2 Provide a preliminary evaluation of “Facility Design Guidelines”, Program of Requirements and the AACC, each in terms of the other.
5.1.3 Review and understand the standards and requirements in Owner’s Specifications and perform all services in accordance with those standards and requirements.
5.1.4 Visit the site and inspect 5.1.3 Inspect the existing facilities, systems and conditions to ensure an accurate understanding of the existing conditions as required.
5.1.5 Participate as a member of the Project Team in the development of the Program of Requirements if such program has not been developed prior to the Effective Date of this Agreement.
5.1.6 5.1.4 Provide recommendations and information to the Project Team on: site usage and site improvementsusage; building systems, equipment and construction feasibility; selection and availability of materials and labor; time requirements for installation and construction; assignment of responsibilities for safety precautions and programs; temporary Project facilities; equipment, materials and services for common use of Contractor and Owner’s separate contractors, if any; cost factors, including costs of alternative materials or designs, preliminary budgets, and possible cost savings; recognizing identifying and tracking the resolution of conflicts in the proposed Drawings and Specifications; methods of delivery of materials, systems, and equipment; and any other matters necessary to accomplish the Project in accordance with the Work Progress Schedule (as defined in section 5.3.1 below) and the AACCBudgeted Construction Cost. Notwithstanding The recommendations of the aboveContractor with respect to cost factors, Contractor shall not be required to provide A/E services unless specifically required by the Contract Documents preliminary budgets, and Contractor’s recommendations and information possible cost savings, are furnished made solely in its capacity as a contractor and are advisory only. Notwithstanding any such recommendations by the Contractor, the CM shall be solely responsible with respect to the design sufficiency of any such recommendations which are incorporated into the Work on the Project. The services to be provided by the Contractor, as set forth above, shall in no manner be construed to be professional design services.
5.1.7 5.1.5 Prepare a detailed preliminary Construction Schedule based on 5.1.4 above.
5.1.6 Assist Owner in selecting and directing the services of existing facility surveys, testing and balancing, environmental surveys or other special consultants hired by Owner to develop additional information for the design or construction of the Project.
5.1.8 At Owner’s request, attend public meetings and hearings concerning the development and schedule of the Project.
5.1.9 Contractor shall use all Construction Documents returned to A/E from the Subcontractor proposers.
Appears in 1 contract
Samples: CMR Services Contract