Interconnection Delays Sample Clauses

Interconnection Delays. If on or after the date that is 120 days after Target COD, the Seller’s Plant has satisfied all requirements for COD, other than those requirements that depend on completion of Interconnection Facilities and if the Seller cannot achieve COD solely as a result of a delay in completion of Interconnection Facilities and such delay is solely caused by BC Hydro or the Distribution Authority or the Transmission Authority, then from and after 24:00 PPT on the later of: (a) 120 days after Target COD and (b) the date on which all other conditions for COD were satisfied, BC Hydro shall pay to the Seller an amount equal to the price payable for post-COD Delivered Energy under section 6.2 multiplied by the amount of Energy, not exceeding , that could have been generated and delivered at the POI but for the delay described above less any costs the Seller avoided or, acting reasonably, could have avoided during the delay in completion of the Interconnection Facilities The Seller shall maintain accurate and complete records of all avoided or avoidable costs and shall report all such costs to BC Hydro and provide BC Hydro with all information required to calculate such costs. BC Hydro or its designated representative may audit such costs and in that event the provisions of section 8.2 apply. Except for the payments provided for pursuant to this section, the Seller shall have no other rights or remedies against BC Hydro, and BC Hydro shall have no other liability, with respect to any delay in completion of the Interconnection Facilities. If within 30 days after completion of the Interconnection Facilities, the Seller’s Plant satisfies the requirements for COD, COD will be deemed to have occurred on the date on which BC Hydro’s payment obligations commenced under this section. If the Seller’s Plant fails to satisfy the requirements for COD within 30 days after completion of the Interconnection Facilities, the Seller shall within 30 days after receipt of an invoice from BC Hydro, refund to BC Hydro all payments made by BC Hydro to the Seller under this section. For greater certainty, this section will not apply if a delay in completion of Interconnection Facilities is due to Force Majeure, Transmission/Distribution Force Majeure or any act or omission of the Seller, including any change made to the Seller’s Plant whether or not consented to by BC Hydro.
AutoNDA by SimpleDocs
Interconnection Delays. The Interconnection Agreement outlines, or will outline, the expected duration to secure Permits associated with the Interconnection Facilities and to construct the Interconnection Facilities. If (i) according to the Interconnection Agreement, the expected duration to secure Permits or to construct the Interconnection Facilities extends beyond the Facility Milestones, or (ii) the Permits associated with the Facility or the interconnection to the Facility are not in place for reasons associated with the interconnection and not solely caused by any action or inaction on the part of Seller, the Facility Milestones shall be extended on a day-to-day basis based on such delays (“Interconnection Delays”).

Related to Interconnection Delays

  • Interconnection Service Interconnection Service allows the Interconnection Customer to connect the Large Generating Facility to the Participating TO’s Transmission System and be eligible to deliver the Large Generating Facility’s output using the available capacity of the CAISO Controlled Grid. To the extent the Interconnection Customer wants to receive Interconnection Service, the Participating TO shall construct facilities identified in Appendices A and C that the Participating TO is responsible to construct. Interconnection Service does not necessarily provide the Interconnection Customer with the capability to physically deliver the output of its Large Generating Facility to any particular load on the CAISO Controlled Grid without incurring congestion costs. In the event of transmission constraints on the CAISO Controlled Grid, the Interconnection Customer's Large Generating Facility shall be subject to the applicable congestion management procedures in the CAISO Tariff in the same manner as all other resources.

  • Interconnection 2.1.10 Startup Testing and Commissioning

  • Interconnection Facilities 4.1.1 The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 of this Agreement. The NYISO, in consultation with the Connecting Transmission Owner, shall provide a best estimate cost, including overheads, for the purchase and construction of its Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, the NYISO, and the Connecting Transmission Owner.

  • Interconnection Point The point hereby designated as “Middletown Junction #2”.

  • Interconnection Customer Interconnection Facilities Interconnection Customer shall design, procure, construct, install, own and/or control Interconnection Customer Interconnection Facilities described in Appendix A, Interconnection Facilities, Network Upgrades and Distribution Upgrades, at its sole expense.

  • Interconnection Customer’s Interconnection Facilities The Interconnection Customer shall design, procure, construct, install, own and/or control the Interconnection Customer’s Interconnection Facilities described in Appendix A at its sole expense.

  • One-Way Interconnection Trunks 2.3.1 Where the Parties use One-Way Interconnection Trunks for the delivery of traffic from iNetworks to Verizon, iNetworks, at iNetworks’ own expense, shall:

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!