Interconnection with Electric Distribution Grid. Cooperative shall obtain at its sole cost all Permits and agreements required for Cooperative’s interconnection of the PV System to the electric distribution grid maintained by the Distribution Company. Cooperative shall promptly inform Host Town of all significant developments relating to such interconnection matters. Host Town shall provide Cooperative with such information as Cooperative may reasonably request in connection with Cooperative’s procurement of such Permits and agreements. If any material changes in plans and/or specifications to the PV System are required by the applicable electric distribution company, then Cooperative shall submit such changes, if any, to Host Town for its approval, which shall not be unreasonably withheld.
Interconnection with Electric Distribution Grid. Owner will obtain at its sole cost all approvals and agreements required for Owner’s interconnection of the System to the LDC System. Owner will promptly inform User of all significant developments relating to such interconnection matters.
Interconnection with Electric Distribution Grid. Lessee will obtain at its sole cost all approvals and agreements required for Lessee’s interconnection of the System to the LDC System. Lessee will promptly inform Lessor of all significant developments relating to such interconnection matters.
Interconnection with Electric Distribution Grid. Developer shall obtain at its sole cost all Permits and agreements required for Developer’s interconnection of the PV System to the electric distribution grid maintained by the Distribution Company. Developer shall promptly inform Host and CVEC of all significant developments relating to such interconnection matters. Host shall provide Developer with such information as Developer may reasonably request in connection with Developer’s procurement of such Permits and agreements. If any material changes in plans and/or specifications to the PV System are required by the applicable electric distribution company, then Developer shall submit such changes, if any, to Host for its approval, which shall not be unreasonably withheld, with a copy to CVEC.
Interconnection with Electric Distribution Grid. Developer will obtain at its sole cost all approvals and agreements required for Developer’s interconnection of the System to the LDC System. Developer will promptly inform Town of all significant developments relating to such interconnection matters.
Interconnection with Electric Distribution Grid. Contractor will obtain at its sole cost all approvals and agreements required for Contractor’s interconnection of the System to the LDC System. Contractor will promptly inform County of all significant developments relating to such interconnection matters.
Interconnection with Electric Distribution Grid. (a) Contractor shall secure interconnection approval from the LDC and complete all required tasks to interconnect each System to the LDC System at no cost to Customer, except as stated in Section 4.14(b), including filing interconnection applications and paying application and impact study fees (if required).