MaintenanceProgramme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain thefollowing: (a) The condition of the road in the format prescribed by the Authority’s Engineer; (b) the proposed maintenance Works;and (c) deployment of resources for maintenanceWorks.
Appears in 8 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
MaintenanceProgramme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint themonthinwhichtheMaintenanceistobecarriedout.Forthispurposeajoint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain thefollowingthe following:
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works;and
(c) deployment of resources for maintenanceWorks.
Appears in 1 contract
Samples: Engineering Procurement and Construction (Epc) Agreement
MaintenanceProgramme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain thefollowing:
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works;and
(c) deployment Deployment of resources for maintenanceWorks.
Appears in 1 contract
Samples: Engineering Procurement and Construction (Epc) Agreement
MaintenanceProgramme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain thefollowing:: State of Manipur” November 2020
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works;and
(c) deployment of resources for maintenanceWorks.
Appears in 1 contract
Samples: Contract Agreement
MaintenanceProgramme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain thefollowing:: Page 92 of 156
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works;and
(c) deployment of resources for maintenanceWorks.
Appears in 1 contract
Samples: Contract Agreement