Payments for Additional Shifts Sample Clauses

Payments for Additional Shifts. 22.2.1 If an employee covers extra shifts, e.g. covering for sick leave or staff shortage, then the day rate as specified in Clause 9.3.5 will be paid as per this agreement.
AutoNDA by SimpleDocs

Related to Payments for Additional Shifts

  • Fees for Additional Services You agree to pay Company’s then-current rates and expenses, including the cost of Company’s vendors, for any requests related to information retrieval, subpoenas, consulting and advisory services, or similar work.

  • Weekly Overtime An Employee required to work in excess of forty (40) hours per week shall be paid at the rate of time and one-half (1 1/2) for the first eight (8) hours of work in excess of the forty (40) hours and double time thereafter.

  • Overtime Calculation For the purpose of overtime calculation only, approved or scheduled time off work will be considered the same as time worked.

  • Compensation for Additional Services Additional Services shall be compensated as set forth on Exhibit A for the stipulated payment amounts set forth therein. Other Additional Services not set forth on Exhibit A that are required or requested by the Owner shall be compensated as agreed, using the methodology set forth on Exhibit A, prior to the Design Professional undertaking such Additional Services; provided, however, that if such compensation cannot be agreed, the Additional Services shall be performed at the hourly rates set forth and listed in Exhibit B, plus reimbursable expenses pursuant to Article 4.1.3 below, with a limitation as to maximum amount specified.

  • Overtime Pay Calculation Overtime shall not be claimed or received for less than fifteen (15) minutes. If overtime amounts to fifteen (15) minutes, or more, it shall be paid for the total period.

  • CLAIMS FOR ADDITIONAL COST 12.3.1 If the Contractor wishes to make a claim for an increase in the Contract Sum, he shall give the Architect written notice thereof within twenty days after the occurrence of the event giving rise to such claim. This notice shall be given by the Contractor before proceeding to execute the Work, except in an emergency endangering life or property in which case the Contractor shall proceed in accordance with Paragraph 10.3 of these General Conditions. No such claim shall be valid unless so made. If the State and the Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined by the Architect. Any change in the Contract Sum resulting from such claim shall be authorized by Change Order.

  • Claims for Additional Costs 11.3.1 If the Contractor wishes to make a claim for an increase in the Contract Sum not related to a requested change, it shall give the Owner and the A/E written notice thereof within twenty-one (21) days after the occurrence of the event giving rise to such claim, but, in any case before proceeding to execute the work considered to give rise to the additional cost or time, except in an emergency endangering life or property in which case the Contractor shall act in accordance with Article 7.2.1. No such claim shall be valid unless so made. If the Owner and the Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined as set forth under Article 15. Any change in the Contract Sum resulting from such claim shall be authorized by Change Order.

  • For Additional Services OWNER shall pay CONSULTANT for Additional Services rendered under Section 2 as follows:

  • Calculation of Overtime If the overtime work has been carried out before as well as after the regular working hours during a certain day, the overtime periods shall be added together. Only full half hours are included in the calculation.

  • Claims for Additional Time § 14.1.6.1 If the Design-Builder intends to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.