Performance Tests and PPA Output Tests Sample Clauses

Performance Tests and PPA Output Tests. Once Mechanical Completion has been achieved and subject to the provisions of Section 6.2.1 hereof, Contractor shall perform the Performance Tests and the PPA Output Tests of the Facility in accordance with Appendix D hereto. Owner shall designate and make available qualified and authorized representatives to observe the Performance Tests and the PPA Output Tests and monitor the taking of measurements to determine the level of achievement of the Performance Guarantees, all in accordance with Appendix D hereto. The Utility and the Independent Engineer shall be permitted, upon the Owner's request, to observe the Performance Tests and the PPA Output Tests. Subject to Section 6.3.4 hereof, until Final Acceptance of the Facility has occurred, Contractor may undertake efforts to improve the performance of the Facility and may cause additional Performance Tests to be performed and re-performed in order to improve the performance results to reduce Contractor's liability for amounts payable as Performance Guarantee Payments with respect to the Facility. Contractor shall keep Owner's representative continuously apprised of the specific schedule, and changes therein, for the commencement and re-performance of Performance Tests or PPA Output Tests. Contractor, at its discretion, may prematurely terminate any Performance Test or PPA Output Tests in a manner consistent with Appendix D hereto, the Electrical Interconnection Requirements, the PPA Operating Requirements, Applicable Laws, Applicable Permits and Prudent Utility Practices. Prior to commencing any Performance Tests or PPA Output Tests hereunder, Owner and Contractor shall mutually and reasonably agree upon more detailed procedures and notice requirements regarding rescheduling or restarting any such tests, which procedures and notice requirements shall be subject to the approval of the Independent Engineer and the Utility. 6.2.1 Performance Test and PPA Output Test Criteria. Each Performance Test which is used in connection with achievement of Provisional Acceptance, Interim Acceptance and Final Acceptance shall consist of the operation of the Facility as a whole in accordance with the performance test terms and conditions set forth in Part A of Appendix D hereto while using Gas for fuel and, in connection with Final Acceptance only, while using Fuel Oil for fuel, in each case with such operation of the Facility to include the operation of each subsystem of the Facility with each other subsystem. Each PPA Outp...
AutoNDA by SimpleDocs

Related to Performance Tests and PPA Output Tests

  • Performance Tests Contractor shall perform Performance Tests in accordance with Section 11.2 of the Agreement and Attachment S.

  • Performance Testing 7.2.1 The Design-Builder shall direct and supervise the tests and, if necessary, the retests of the Plant using Design-Builder’s supervisory personnel and the Air Emissions Tester shall conduct the air emissions test, in each case, in accordance with the testing procedures set forth in Exhibit A (the “Performance Tests”), to demonstrate, at a minimum, compliance with the Performance Guarantee Criteria. Owner is responsible for obtaining Air Emissions Tester and for ensuring Air Emissions Tester’s timely performance. Design-Builder shall cooperate with the Air Emissions Tester to facilitate performance of all air emissions tests. Design-Builder shall not be held responsible for the actions of Owner’s employees and third parties involved in the Performance Testing, including but not limited to Air Emissions Tester. 7.2.2 No later than thirty (30) Days prior to the earlier of the Scheduled Substantial Completion Date or Substantial Completion, Design-Builder shall provide to Owner for review a detailed testing plan for the Performance Tests (other than for air emissions). Owner and Design-Builder shall agree upon a testing plan that shall be consistent with the Performance Test Protocol contained in Exhibit A hereto. After such agreement has been reached, Design-Builder shall notify the Owner five (5) business days prior to the date Design-Builder intends to commence the Performance Tests and shall notify the Owner upon commencement of the Performance Tests. Owner and Independent Engineer each have the right to witness all testing, including the Performance Tests and any equipment testing, whether at the Site or at the Subcontractor’s or equipment supplier’s premises during the course of this Agreement. Notwithstanding the foregoing sentence, Owner shall bear the costs of providing a witness to any such testing and all such witnesses shall comply at all times with Design-Builder’s, Subcontractor’s or equipment supplier’s safety and security procedures and other reasonable requirements, and otherwise conduct themselves in a manner that does not interfere with Design-Builder’s, Subcontractor’s or equipment supplier’s activities or operations. 7.2.3 Design-Builder shall provide to Owner a Performance Test report (excluding results from air emissions testing), including all applicable test data, calculations and certificates indicating the results of the Performance Tests and, within five (5) business days of Owner’s receipt of such results, Owner, Independent Engineer and Design-Builder will jointly inspect such Work and review the results of the Performance Tests to verify that the Performance Guarantee Criteria have been met. If Owner or Independent Engineer reasonably determines that the Performance Guarantee Criteria have not been met, Owner shall notify Design-Builder the reasons why Owner determined that the Performance Guarantee Criteria have not been met and Design-Builder shall promptly take such action or perform such additional work as will achieve the Performance Guarantee Criteria and shall issue to the Owner another notice in accordance with Section 7.2.2; provided however that if the notice relates to a retest, the notice may be provided no less than two (2) business days prior to the Performance Tests. Such procedure shall be repeated as necessary until Owner and Independent Engineer verifies that the Performance Guarantee Criteria have been met. 7.2.4 If Owner, for whatever reason, prevents Design-Builder from demonstrating the Performance Guarantee Criteria within thirty (30) Days of Design-Builder’s notice that the Plant is ready for Performance Testing, then Design-Builder shall be excused from demonstrating compliance with the Performance Guarantee Criteria during such period of time that Design-Builder is prevented from demonstrating compliance with the Performance Guarantee Criteria; provided however that Design-Builder will be deemed to have fulfilled all of its obligations to demonstrate that the Plant meets the Performance Guarantee Criteria should such period of time during which Design-Builder is prevented from demonstrating the Performance Criteria exceed thirty (30) Days or extend beyond the Final Completion Date.

  • Acceptance Tests 11.1 If the Contract provides acceptance tests for Goods and/or the result of Services after their completion and/or delivery to the Purchaser, the acceptance shall only be considered as definitive when such tests have demonstrated the compliance of the Goods and/or the result of the Services to the requirements in the Contract. 11.2 Where the Contract provides for an acceptance procedure in the presence of both parties, at the successful completion of such procedure, the Purchaser shall issue the Supplier with an acceptance certificate which shall authorise the Supplier to invoice the Purchaser for any payment due on such acceptance. 11.3 The Purchaser shall at its discretion be entitled to issue and acceptancecertificate with reserves. The Supplier shall be obliged to remedy any non-conformities within the period set out in the acceptance certificate. Any payment which would otherwise have been due on acceptance may be withheld by the Purchaser in whole or part until the non- conformities underlying the reserves have been remedied.

  • Stability Testing Patheon may be requested to conduct stability testing on the Products in accordance with the protocols set out in the Specifications for the separate fees and during the time periods set out in Schedule C to a Product Agreement. Patheon will not make any changes to these testing protocols without prior written approval from Client. If a confirmed stability test failure occurs, Patheon will notify Client within one Business Day, after which Patheon and Client will jointly determine the proceedings and methods to be undertaken to investigate the cause of the failure, including which party will bear the cost of the investigation. Patheon will not be liable for these costs unless it has failed to perform the Manufacturing Services in accordance with the Specifications, cGMPs, and Applicable Laws. Patheon will give Client ail stability test data and results at Client’s request.

  • Test The outer surface of the lamp lenses shall be subjected once or more than once to the action of the sand jet produced as described above. The jet shall be sprayed almost perpendicular to the surface to be tested. The deterioration shall be checked by means of one or more samples of glass placed as a reference near the lenses to be tested. The mixture shall be sprayed until the variation in the diffusion of light on the sample or samples measured by the method described in Appendix 2, is such that: Δ d = (T5 - T4) / T2 ≤ 0.0250 ± 0.0025 Several reference samples may be used to check that the whole surface to be tested has deteriorated homogeneously.

  • Meter Testing Company shall provide at least twenty-four (24) hours' notice to Seller prior to any test it may perform on the revenue meters or metering equipment. Seller shall have the right to have a representative present during each such test. Seller may request, and Company shall perform, if requested, tests in addition to the every fifth-year test and Seller shall pay the cost of such tests. Company may, in its sole discretion, perform tests in addition to the fifth year test and Company shall pay the cost of such tests. If any of the revenue meters or metering equipment is found to be inaccurate at any time, as determined by testing in accordance with this Section 10.2 (Meter Testing), Company shall promptly cause such equipment to be made accurate, and the period of inaccuracy, as well as an estimate for correct meter readings, shall be determined in accordance with Section 10.3 (Corrections).

  • Acceptance Testing At the time of installation of a LIS trunk group, and at no additional charge, acceptance tests will be performed to ensure that the service is operational and meets the applicable technical parameters.

  • CONTRACTOR PERFORMANCE AUDIT The Contractor shall allow the Authorized User to assess Contractor’s performance by providing any materials requested in the Authorized User Agreement (e.g., page load times, response times, uptime, and fail over time). The Authorized User may perform this Contractor performance audit with a third party at its discretion, at the Authorized User’s expense. The Contractor shall perform an independent audit of its Data Centers, at least annually, at Contractor expense. The Contractor will provide a data owner facing audit report upon request by the Authorized User. The Contractor shall identify any confidential, trade secret, or proprietary information in accordance with Appendix B, Section 9(a), Confidential/Trade Secret Materials.

  • Laboratory Testing All laboratories selected by UPS Freight for analyzing Controlled Substances Testing will be HHS certified.

  • Random Testing Notwithstanding any provisions of the Collective Agreement or any special agreements appended thereto, section 4.6 of the Canadian Model will not be applied by agreement. If applied to a worker dispatched by the Union, it will be applied or deemed to be applied unilaterally by the Employer. The Union retains the right to grieve the legality of any imposition of random testing in accordance with the Grievance Procedure set out in this Collective Agreement.