Prompt Progress Payment to Subcontractors Sample Clauses

Prompt Progress Payment to Subcontractors. A prime contractor or subcontractor shall pay a subcontractor not later than ten (10) days of receipt of each progress payment in accordance with the provision in Section 7108.5 of the California Business and Professions Code concerning prompt payment to subcontractors. The ten (10) days is applicable unless a longer period is agreed to in writing. Any violation of Section 7108.5 shall subject the violating contractor or subcontractor to the penalties, sanction and other remedies of that Section. Federal regulation (49 CFR 26.29) requires that any delay or postponement of payment over thirty (30) days of receipt of each payment may take place only for good cause and with the TJPA’s prior written approval. These requirements shall not be construed to limit or impair any contractual, administrative, or judicial remedies otherwise, available to the prime contractor or subcontractor in the event of a dispute involving late payment, or nonpayment by the prime contractor, deficient subcontract performance, or noncompliance by a subcontractor. This provision applies to both DBE/SBE and non-DBE/SBE prime contractors and subcontractors.
AutoNDA by SimpleDocs
Prompt Progress Payment to Subcontractors. A prime contractor or subcontractor shall pay to any subcontractor not later than 10-days of receipt of each progress payment, in accordance with the provision in Section 7108.5 of the California Business and Professions Code concerning prompt payment to subcontractors. The 10-days is applicable unless a longer period is agreed to in writing. Any delay or postponement of payment over 30-days may take place only for good cause and with the agency’s prior written approval. Any violation of Section 7108.5 shall subject the violating contractor or subcontractor to the penalties, sanctions, and other remedies of that Section. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies, otherwise available to the contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the contractor, deficient subcontractor performance, and/or noncompliance by a subcontractor. This clause applies to both DBE and non-DBE subcontractors.
Prompt Progress Payment to Subcontractors. Attention is directed to the provisions in Sections 10262 and 10262.5 of the Public Contract Code and Section 7108.5 of the Business and Professions Code concerning prompt payment to subcontractors. Prompt Payment of Withheld Funds to Subcontractors. The Contractor shall return all moneys withheld in retention from the subcontractor within 30 days after receiving payment for work satisfactorily completed, even if the other contract work is not completed and has not been accepted in conformance with the acceptance of the project. Contractual, administrative, or judicial remedies otherwise available to the Contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the Contractor or deficient subcontract performance or noncompliance by a subcontractor shall not be limited or impaired by this provision.
Prompt Progress Payment to Subcontractors. A prime contractor or subcontractor shall pay any subcontractor not later than 7 days from receipt of each progress payment in accordance with the provision in Section 7108.5 of the California Business and Professions Code concerning prompt payment to subcontractors. The 7 days is applicable unless a longer period is agreed to in writing. Any delay or postponement of payment over 30 days may take place only for good cause and with the County’s prior written approval. Any violation of Section 7108.5 shall subject the violating contractor or subcontractor to the penalties, sanctions and other remedies of that section. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies otherwise available to the contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the prime contractor, deficient subcontract performance, or noncompliance by a subcontractor.
Prompt Progress Payment to Subcontractors. The Local Agency shall require contractors and subcontractors to pay their subcontractors within seven (7) days for construction contracts, and within fifteen (15) days for consultant contracts, after receiving each progress payment. Any delay or postponement of payment may take place only for good cause and with the Local Agency’s prior written approval. Any violation of these provisions shall subject the violating contractor or subcontractor to the penalties, sanctions and remedies specified in Section 7108.5 of the CBPC and Section 10262 of the CPCC for construction contract, and Section 3321 of the CCC for consultant contract. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies, otherwise available to the contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the contractor, deficient subcontractor performance, and/or noncompliance by a subcontractor. This clause applies to both DBE and non-DBE subcontractors.
Prompt Progress Payment to Subcontractors. A prime contractor or subcontractor shall pay to any subcontractor not later than 10-days of receipt of each progress payment, in accordance with the provision in Section 7108.5 of the California Business and Professionals Code concerning prompt payment to subcontractors. The 10-day rule is applicable unless a longer period is agreed to in writing. Any delay or postponement of payment over 30 days may take place only for good cause and with the agency’s prior written approval. Any violation of Section 7108.5 shall subject the violating contractor or subcontractor to the penalties, sanctions, and other remedies of that Section. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies, otherwise available to the contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the Consultant, deficient subcontractor performance, and/or noncompliance by a subcontractor. This clause applies to both DBE and non-DBE subcontractors.
Prompt Progress Payment to Subcontractors. The Parties or any of their subcontractors shall pay to any subcontractor not later than 10 days of receipt of each progress payment, in accordance with the provision in Section 7108.5 of the California Business and Professions Code concerning prompt payment to subcontractors. The 10 days is applicable unless a longer period is agreed to in writing. Any delay or postponement of payment over 30 days may take place only for good cause and with the contracting Party’s prior written approval. Any violation of Section 7108.5 shall subject the violating contractor or subcontractor to the penalties, sanctions, and other remedies of that Section. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies, otherwise available to the Parties or any of their subcontractors in the event of a dispute involving late payment or non-payment by either Party, deficient subcontractor performance, and/or non-compliance by a subcontractor. This clause applies to both DBE and non-DBE subcontractors.
AutoNDA by SimpleDocs

Related to Prompt Progress Payment to Subcontractors

  • Prompt Payment to Subcontractors (a) Within 7 days of receipt by the Contractor of each payment from the City under this contract, the Contractor shall pay all Subcontractors (which term includes subconsultants and suppliers) based on work completed or service provided under the subcontract. Should any payment to the Subcontractor be delayed by more than 7 days after receipt of payment by the Contractor from the City under this contract, the Contractor shall pay the Subcontractor interest, beginning on the 8th day, at the rate of 1% per month or fraction thereof on such unpaid balance as may be due. By appropriate litigation, Subcontractors shall have the right to enforce this subsection (a) directly against the Contractor, but not against the City of Durham.

  • Payment to Subcontractors (If applicable) As required by Minnesota Statute § 16A.1245, the prime Contractor must pay all subContractors, less any retainage, within 10 calendar days of the prime Contractor’s receipt of payment from the State for undisputed services provided by the subContractor(s) and must pay interest at the rate of one and one-half percent per month or any part of a month to the subContractor(s) on any undisputed amount not paid on time to the subContractor(s).

  • PAYMENT TO SUB-CONTRACTORS 12.1 Transnet reserves the right, in its sole discretion, to make payment directly to the sub-contractor of the Supplier/Service Provider, subject to the following conditions:

  • Payments to Subcontractors Develop and implement a procedure for the review, processing and payment of applications by subcontractors for progress and final payments.

  • To Subcontractor(s) a. Within seven (7) days of the Contractor’s receipt of payment from the County for the proportionate share of the payment received for work performed by the subcontractor(s) under the contract a Contractor awarded a contract under this solicitation is hereby obligated:

  • APPLICABILITY TO SUBCONTRACTORS Respondent agrees that all contracts it awards pursuant to the contract awarded as a result of this Agreement will be bound by the foregoing terms and conditions.

  • Right to Subcontract The Carrier at its discretion may subcontract on any terms the whole or any part of the Carriage.

  • Subcontractor Payments Subject to Agency’s prior approval, Agency will reimburse Outside Counsel for the actual, reasonable and necessary expenses relating to Outside Counsel’s use of subcontractors. Outside Counsel shall be responsible for any payments and other claims due to subcontractors for work performed under this OCC. Outside Counsel, in subcontracting for any performances or in support of any of the performances specified herein (e.g., expert services, local counsel, and other services), expressly understands and agrees that Agency shall not be directly liable in any manner to Outside Counsel’s subcontractor(s).

  • PAYMENT OF SUBCONTRACTORS The Contractor is obligated to take one of the two following actions within seven days after receipt of payment by the County for work performed by any subcontractor under this Contract:

  • Solicitations for Subcontractors, Including Procurements of Materials and Equipment In all solicitations either by competitive bidding or negotiation made by the contractor for work to be performed under a subcontract, including procurements of materials or leases of equipment, each potential subcontractor or supplier shall be notified by the contractor of the contractor's obligations under this contract and the Regulations relative to nondiscrimination on the grounds of race, color, or national origin, sex, age, and disability/handicap.