Payment to Subcontractors. (If applicable) As required by Minnesota Statute § 16A.1245, the prime Contractor must pay all subContractors, less any retainage, within 10 calendar days of the prime Contractor’s receipt of payment from the State for undisputed services provided by the subContractor(s) and must pay interest at the rate of one and one-half percent per month or any part of a month to the subContractor(s) on any undisputed amount not paid on time to the subContractor(s).
Payment to Subcontractors. The agreement between the Contractor and its Subcontractor shall contain the same terms and conditions as to method of payment for Work, labor and materials, and as to retained percentages, as are contained in this Contract.
Payment to Subcontractors. (a) Payments by contractors to subcontractors associated with Authority contracts are subject to the time periods established in the Texas Prompt Payment Act, Tex. Gov’t Code § 2251.
(b) A false certification to the Authority under the provisions of the paragraph entitled "Invoicing and Payment" hereof may be a criminal offense in violation of Tex. Penal Code § 10.
Payment to Subcontractors. 8.3.1 No later than ten Days after receipt of payment from TxDOT, Maintenance Contractor shall promptly pay each Subcontractor, out of the amount paid to Maintenance Contractor on account of such Subcontractor’s portion of the Maintenance Services, the amount to which such Subcontractor is entitled, less any retainage provided for in the Subcontract, and any other offsets and deductions provided in the Subcontract or by Law. No later than ten days after satisfactory completion of all Maintenance Services to be performed by a Subcontractor, including provision of appropriate releases, certificates and other evidence of the Subcontractor’s compliance with its Subcontract and all applicable requirements of the CMA Documents, Maintenance Contractor shall pay to the Subcontractor moneys withheld in retention from the Subcontractor. Such payment shall be made promptly following satisfaction of the foregoing requirements, even if the Maintenance Services to be performed by Maintenance Contractor or other Subcontractors is not completed.
8.3.2 For the purpose of Section 8.3, satisfactory completion shall have been accomplished when:
(a) the Subcontractor has fulfilled the Subcontract requirements and the requirements under the CMA Documents for the subcontracted Maintenance Services, including the submission of all submittals required by the Subcontract and the CMA Documents; and
(b) the Maintenance Services performed by the Subcontractor have been inspected and approved in accordance with the CMA Documents and the final quantities of the Subcontractor’s work have been determined and agreed upon.
8.3.3 The inspection and approval of a Subcontractor’s work does not eliminate or impair Maintenance Contractor’s responsibility for the Maintenance Services. Any delay or postponement of payments to Subcontractors from the above-referenced time frames may occur only for good cause following written approval by TxDOT. TxDOT shall have no obligation to pay or to see to the payment of money to a Subcontractor, except as may otherwise be required by Law. Interest on late payments to Subcontractors shall be Maintenance Contractor's responsibility, and shall not be a part of the Maintenance Price.
Payment to Subcontractors. 1. Contractor awarded a contract under this solicitation is hereby obligated to pay the Subcontractor(s) within seven (7) days of the Contractor's receipt of payment from the Commonwealth for the proportionate share of the payment received for work performed by the Subcontractor(s) under the contract; or
2. To notify the agency and the Subcontractor(s), in writing, of the Contractor's intention to withhold payment and the reason.
3. The Contractor is obligated to pay the Subcontractor(s) interest at the rate of one percent per month (unless otherwise provided under the terms of the contract) on all amounts owed by the Contractor that remain unpaid seven (7) days following receipt of payment from the Commonwealth, except for amounts withheld as stated in 2. above. The date of mailing of any payment by U.S. Mail is deemed to be payment to the addressee. These provisions apply to each sub sub-tier Contractor performing under the primary contract. A Contractor's obligation to pay an interest charge to a Subcontractor may not be construed to be an obligation of the Commonwealth.
Payment to Subcontractors. Contractor shall pay all subcontractors for and on account of work performed by such subcontractors in accordance with the terms of their respective subcontracts and as provided for in Section 7108.5 of the California Business and Professions Code. Such payments to subcontractors shall be based on the measurements and estimates made and progress payments provided to Contractor pursuant to this Contract.
Payment to Subcontractors. A. Pay your DBE Subcontractor(s) and non-DBE Subcontractor(s) within seven (7) calendar days from receipt of each payment made to Contractor by the State.
B. Prior to the 15th of each month, submit documentation to Caltrans Contract Manager showing the amount paid to DBE trucking companies listed in Contractor’s DBE information. This monthly documentation shall indicate the portion of the revenue paid to DBE trucking companies, which is claimed toward DBE participation. Contractor shall also obtain and submit documentation to the Caltrans Contract Manager showing the amount paid by DBE trucking companies to all firms, including owner-operators, for the leasing of trucks. The DBE who leases trucks from a non-DBE truck leasing company must use its own employees as drivers in order to be eligible to receive credit for the total value of the hauling services. The records must confirm that amount of credit claimed toward DBE participation conforms to the requirements of Section 26 below entitled, “DBE Substitutions.”
C. Submit to Caltrans Contract Manager documentation showing the truck number, name of owner, California Highway Patrol CA number, and, if applicable, the DBE certification number of the truck owner for all trucks used during that month for which DBE participation will be claimed. This documentation shall be submitted on the Monthly DBE Trucking Verification form provided to Contractor by Caltrans Contract Manager.
D. Return all moneys withheld from a Subcontractor within 30 days after receiving payment for work satisfactorily completed, even if other Agreement work is not completed and has not been accepted in conformance with the terms of the Agreement. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies otherwise available to Contractor or a Subcontractor in the event of a dispute involving late payment or non-payment to Contractor or deficient performance or noncompliance by a Subcontractor.
Payment to Subcontractors. A. Within seven (7) days following receipt of payments made pursuant to this Agreement, the Contractor shall take one of the following actions with regard to subcontractors:
1) Pay the subcontractor its proportionate share of the total payment received from the City for the work performed by the subcontractor; or
2) Notify the City Manager and the subcontractor, in writing, of the Contractor’s intention to withhold all or a part of the subcontractor’s proportionate share of the payment from the City and the reason(s) for nonpayment.
B. The Contractor shall pay interest to all subcontractors on all amounts owed by the Contractor to subcontractors that remains unpaid after seven (7) days following receipt by the Contractor of a payment made pursuant to this Agreement by the City. The interest required by this Subsection will accrue at the rate of one percent (1%) per month. The interest requirement set forth in this Subparagraph shall not be construed to be an obligation of the City and this Agreement shall not be amended or modified for the purpose of providing reimbursement for such interest charges.
C. The Contractor shall include in each of its subcontracts a requirement that each subcontractor include or otherwise be subject to the payment and interest requirements of this Section with respect to sub-subcontracts.
Payment to Subcontractors. Payment by the Grantee to all subcontractors with approved third party contracts shall be in compliance with Section 287.0585, Florida Statutes. Each third party contract from the Grantee to a subcontractor for goods or services to be performed in whole or in part with Transportation Disadvantaged Trust Fund moneys, must contain the following statement:
Payment to Subcontractors. 12.5.1 DB Contractor shall pay each Subcontractor for Work performed within ten days after receiving payment from TxDOT for the Work performed by the Subcontractor, and shall pay any retainage on a Subcontractor's Work within ten days after satisfactory completion of all of the Subcontractor's Work. Completed Subcontractor Work includes vegetative establishment, test, maintenance, performance, and other similar periods that are the responsibility of the Subcontractor.
12.5.2 For the purpose of this Section 12.5, satisfactory completion shall have been accomplished when:
(a) the Subcontractor has fulfilled the Subcontract requirements and the requirements under the Contract Documents for the subcontracted Work, including the submission of all submittals required by the Subcontract and Contract Documents; and
(b) the Work done by the Subcontractor has been inspected and approved by DB Contractor and the final quantities of the Subcontractor’s Work have been determined and agreed upon.
12.5.3 The foregoing payment requirements apply to all tiers of Subcontractors and shall be incorporated into all Subcontracts.