Common use of Queue Position for Pending Requests Clause in Contracts

Queue Position for Pending Requests. 5.1.1 Any Interconnection Customer assigned a Queue Position prior to the effective date of this LGIP shall retain that Queue Position. 5.1.1.1 If an Interconnection Study Agreement has not been executed as of the effective date of this LGIP, then such Interconnection Study, and any subsequent Interconnection Studies, shall be processed in accordance with this LGIP. 5.1.1.2 If an Interconnection Study Agreement has been executed prior to the effective date of this LGIP, such Interconnection Study shall be completed in accordance with the terms of such agreement. With respect to any remaining studies for which an Interconnection Customer has not signed an Interconnection Study Agreement prior to the effective date of the LGIP, Transmission Provider must offer Interconnection Customer the option of either continuing under Transmission Provider's existing interconnection study process or going forward with the completion of the necessary Interconnection Studies (for which it does not have a signed Interconnection Studies Agreement) in accordance with this LGIP. 5.1.1.3 If an LGIA has been executed by the Parties before the effective date of the LGIP, then the LGIA would be grandfathered.

Appears in 4 contracts

Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Procedures (Lgip) and Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

Queue Position for Pending Requests. 5.1.1 Any Interconnection Customer assigned a Queue Position prior to the effective date of this LGIP shall retain that Queue Position. 5.1.1.1 If an Interconnection Study Agreement has not been executed as of the effective date of this LGIP, then such Interconnection Study, and any subsequent Interconnection Studies, shall be processed in accordance with this LGIP. 5.1.1.2 If an Interconnection Study Agreement has been executed prior to the effective date of this LGIP, such Interconnection Study shall be completed in accordance with the terms of such agreement. With respect to any remaining studies for which an Interconnection Customer has not signed an Interconnection Study Agreement prior to the effective date of the LGIP, Transmission Provider must offer Interconnection Customer the option of either continuing under Transmission Provider's existing interconnection study process or going forward with the completion of the necessary Interconnection Studies (for which it does not have a signed Interconnection Studies Agreement) in accordance with this LGIP. 5.1.1.3 If an LGIA has been executed by the Parties before the effective date of the LGIP, then the LGIA would be grandfathered.

Appears in 3 contracts

Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

Queue Position for Pending Requests. 5.1.1 Any Interconnection Customer assigned a Queue Position prior to the effective date of this LGIP shall retain that Queue Position. 5.1.1.1 If an Interconnection Study Agreement has not been executed as of the effective date of this LGIP, then such Interconnection Study, and any subsequent Interconnection Studies, shall be processed in accordance with this LGIP. 5.1.1.2 If an Interconnection Study Agreement has been executed prior to the effective date of this LGIP, such Interconnection Study shall be completed in accordance with the terms of such agreement. With respect to any remaining studies for which an Interconnection Customer has not signed an Interconnection Study Agreement prior to the effective date of the LGIP, Transmission Provider must offer Interconnection Customer the option of either continuing under Transmission Provider's existing interconnection study process or going forward with the completion of the necessary Interconnection Studies (for which it does not have a signed Interconnection Studies Agreement) in accordance with this LGIP. 5.1.1.3 If an LGIA has been executed by the Parties submitted to FERC for approval before the effective date of the LGIP, then the LGIA would be grandfathered.

Appears in 2 contracts

Samples: Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Procedures (Lgip)

Queue Position for Pending Requests. 5.1.1 Any Interconnection Customer assigned a Queue Position prior to the effective date of this LGIP shall retain that Queue Position. 5.1.1.1 If an Interconnection Study Agreement has not been executed as of the effective date of this LGIP, then such Interconnection Study, and any subsequent Interconnection Studies, shall be processed in accordance with this LGIP. 5.1.1.2 If an Interconnection Study Agreement has been executed prior to the effective date of this LGIP, such Interconnection Study shall be completed in accordance with the terms of such agreement. With respect to any remaining studies for which an Interconnection Customer has not signed an Interconnection Study Agreement prior to the effective date of the LGIP, the Transmission Provider must offer the Interconnection Customer the option of either continuing under the Transmission Provider's existing interconnection study process or going forward with the completion of the necessary Interconnection Studies (for which it does not have a signed Interconnection Studies Agreement) in accordance with this LGIP. 5.1.1.3 If an LGIA has been executed by submitted to the Parties Commission for approval before the effective date of the LGIP, then the LGIA would be grandfathered.

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement (Lgia)

Queue Position for Pending Requests. 5.1.1 Any Interconnection Customer assigned a Queue Position prior to the effective date of this LGIP shall retain that Queue Position. 5.1.1.1 If an Interconnection Study Agreement has not been executed as of the effective date of this LGIP, then such Interconnection Study, and any subsequent Interconnection Studies, shall be processed in accordance with this LGIP. 5.1.1.2 If an Interconnection Study Agreement has been executed prior to the effective date of this LGIP, such Interconnection Study shall be completed in accordance with the terms of such agreement. With respect to any remaining studies for which an Interconnection Customer has not signed an Interconnection Study Agreement prior to the effective date of the LGIP, Transmission Provider must offer Interconnection Customer the option of either continuing under Transmission Provider's existing interconnection study process or going forward with the completion of the necessary Interconnection Studies (for which it does not have a signed Interconnection Studies Agreement) in accordance with this LGIP. 5.1.1.3 If an LGIA has been executed by the Parties Partiessubmitted to FERC for approval before the effective date of the LGIP, then the LGIA would be grandfathered.

Appears in 1 contract

Samples: Standard Large Generator Interconnection Procedures (Lgip)

Queue Position for Pending Requests. 5.1.1 Any Interconnection Customer assigned a Queue Position prior to the effective date of this LGIP shall retain that Queue Position. 5.1.1.1 If an Interconnection Study Agreement has not been executed as of the effective date of this LGIP, then such Interconnection Study, and any subsequent Interconnection Studies, shall be processed in accordance with this LGIP. 5.1.1.2 If an Interconnection Study Agreement has been executed prior to the effective date of this LGIP, such Interconnection Study shall be completed in accordance with the terms of such agreement. With respect to any remaining studies for which an Interconnection Customer has not signed an Interconnection Study Agreement prior to the effective date of the LGIP, Transmission Provider must offer Interconnection Customer the option of either continuing under Transmission Provider's existing interconnection study process or going forward with the completion of the necessary Interconnection Studies (for which it does not have a signed Interconnection Studies Agreement) in accordance with this LGIP. 5.1.1.3 If an LGIA has been executed by the Parties before the effective date of the LGIP, then the LGIA would be grandfathered.

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement (Lgia)

Queue Position for Pending Requests. 5.1.1 Any Interconnection Customer assigned a Queue Position prior to the effective date of this LGIP LGIPLGIP-OR shall retain that Queue Position. 5.1.1.1 If an Interconnection Study Agreement has not been executed as of the effective date of this LGIPLGIPLGIP- OR, then such Interconnection Study, and any subsequent Interconnection Studies, shall be processed in accordance with this LGIPLGIPLGIP-OR. 5.1.1.2 If an Interconnection Study Agreement has been executed prior to the effective date of this LGIPLGIPLGIP- OR, such Interconnection Study shall be completed in accordance with the terms of such agreement. With respect to any remaining studies for which an Interconnection Customer has not signed an Interconnection Study Agreement prior to the effective date of the LGIPLGIPLGIP-OR, Transmission Provider must offer Interconnection Customer the option of either continuing under Transmission Provider's existing interconnection study process or going forward with the completion of the necessary Interconnection Studies (for which it does not have a signed Interconnection Studies Agreement) in accordance with this LGIPLGIPLGIP-OR. 5.1.1.3 If an LGIA has been executed by the Parties submitted to FERC for approval before the effective date of the LGIP, then the LGIA would be grandfathered.

Appears in 1 contract

Samples: Standard Large Generator Interconnection Procedures