Request for early Equipment procurement Sample Clauses

Request for early Equipment procurement. (a) The Customer may ask ElectraNet in writing to procure Equipment at any time if the parties have agreed (in writing) to the specifications of the required Equipment and that the early procurement of such Equipment may expedite completion of the Project. (b) After receiving a request from the Customer pursuant to clause 9.2(a), ElectraNet will provide the Customer with an estimate of the Third Party Costs which may be incurred in relation to the procurement of the relevant Equipment (Estimated Third Party Costs) as soon as reasonably practicable. (c) The Customer must, within 10 Business Days of receiving the information in clause 9.2(b), Notify ElectraNet if it would like to proceed with procuring the relevant Equipment. If no such Notice is given, ElectraNet will not be required to procure the Equipment. (d) Subject to clause 9.4, the Customer acknowledges and agrees that it will be liable for all Third Party Costs incurred or otherwise payable by ElectraNet in connection with the procurement of any Equipment in accordance with this clause 9 as and when such Third Party Costs become due and payable.
AutoNDA by SimpleDocs
Request for early Equipment procurement. (a) The Customer may ask ElectraNet in writing to procure Equipment at any time if the parties have agreed (in writing) to the specifications of the required Equipment and that the early procurement of such Equipment may expedite completion of the Project. (b) After receiving a request from the Customer pursuant to clause 9.2(a), ElectraNet will provide the Customer with an estimate of the Third Party Costs which may be incurred in relation to the procurement of the relevant Equipment (Estimated Third Party Costs) as soon as reasonably practicable. (c) The Customer must, within 10 Business Days of receiving the information in clause 9.2(b), Notify ElectraNet if it would like to proceed with procuring the relevant Equipment. If no such Notice is given, ElectraNet will not be required to procure the Equipment.

Related to Request for early Equipment procurement

  • Equipment Procurement If responsibility for construction of the Connecting Transmission Owner’s Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades is to be borne by the Connecting Transmission Owner, then the Connecting Transmission Owner shall commence design of the Connecting Transmission Owner’s Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Developer and Connecting Transmission Owner otherwise agree in writing: 5.5.1 NYISO and Connecting Transmission Owner have completed the Interconnection Facilities Study pursuant to the Interconnection Facilities Study Agreement; 5.5.2 The NYISO has completed the required cost allocation analyses, and Developer has accepted his share of the costs for necessary System Upgrade Facilities and System Deliverability Upgrades in accordance with the provisions of Attachment S of the NYISO OATT; 5.5.3 The Connecting Transmission Owner has received written authorization to proceed with design and procurement from the Developer by the date specified in Appendix B hereto; and 5.5.4 The Developer has provided security to the Connecting Transmission Owner in accordance with Article 11.5 by the dates specified in Appendix B hereto.

  • Life support equipment (a) If a person living or intending to live at your premises requires life support equipment, you must: (i) register the premises with your retailer or with us; and (ii) provide medical confirmation for the premises. (b) Subject to satisfying the requirements in the Rules, your premises may cease to be registered as having life support equipment if medical confirmation is not provided to us or your retailer.

  • NETWORK INTERCONNECTION METHODS 3.1 The Interconnection provided herein may not be used solely for the purpose of originating a Party’s own interexchange traffic.

  • WORK ACCESS The Association shall provide a current, written list of its Association Representatives to all heads of departments, offices, or bureaus represented herein and the CAO. The Association shall be responsible for keeping the list current. An Association Representative shall have access to department, office, or bureau facilities where Unit members are employed during regular working hours to assist employees covered under this MOU in addressing grievances when such Association assistance is requested by a grievant(s) or to investigate matters arising out of the application of the provisions of this MOU. The Association Representative shall request authorization for such visits by contacting the designated Management representative of the head of the office, department, or bureau. In the event immediate access cannot be authorized, the designated Management representative shall inform the Association Representative as to the earliest time when access can be granted. This Article shall not be construed as a limitation on the power of the head of a department, office, or bureau to restrict access to areas designated for security or confidential purposes.

  • Contract Schedule The information set forth in the Contract Schedule is true and correct.

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • The Performance Improvement Process (a) The Performance Improvement Process will focus on the risks of non- performance and problem-solving. It may include one or more of the following actions: (1) a requirement that the HSP develop and implement an improvement plan that is acceptable to the LHIN; (2) the conduct of a Review; (3) a revision and amendment of the HSP’s obligations; and (4) an in-year, or year end, adjustment to the Funding, among other possible means of responding to the Performance Factor or improving performance. (b) Any performance improvement process begun under a prior service accountability agreement that was not completed under the prior agreement will continue under this Agreement. Any performance improvement required by a LHIN under a prior service accountability agreement will be deemed to be a requirement of this Agreement until fulfilled or waived by the LHIN.

  • Equipment Use Lessee agrees that the Equipment will be operated by competent, qualified personnel in connection with Lessee's business for the purpose for which the Equipment was designed and in accordance with applicable operating instructions, laws, and government regulations, and that Lessee shall use all reasonable precautions to prevent loss or damage to the Equipment from fire and other hazards. Lessee shall procure and maintain in effect all orders, licenses, certificates, permits, approvals, and consents required by federal, state, or local laws or by any governmental body, agency, or authority in connection with the delivery, installation, use, and operation of the Equipment.

  • Personal Protective Equipment (PPE Each employee responding to or engaged in fire suppression activities will use the appropriate safety clothing and equipment. Each department is responsible for seeing that CAL/OSHA standards for safety clothing and equipment are provided and used for wildland firefighting. Wildland fire suppression safety clothing and equipment includes:  Safety helmet that meets the minimum standards required by California Code of Regulations (CCR), Title 8, Section 3410.  Goggles, protection that meets the minimum requirements for design, construction and use as required by CCR, Title 8, Sections 3382 and 3404.  Ear protection to comply with CCR, Title 8, Sections 3405 and 3410(c).  Nomex hood, shroud, or equivalent face and neck protection.  Nomex shirt  Nomex pants  Gloves, CAL/OSHA approved for wildland firefighting.  Safety work boots, heavy-duty, lace-type, with deeply lugged soles and heels, and leather tops at least eight inches in height.  Wildland fire shelter

  • Equipment Provided County shall provide all tools and equipment it deems essential to complete assigned duties.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!