SCHEDULE METHODOLOGY Sample Clauses

SCHEDULE METHODOLOGY. A. The scheduling method to be used shall be a Critical Path Method schedule in the form of an activity on node Precedence Diagram Network (PDN) with capabilities of identifying the critical path.
AutoNDA by SimpleDocs

Related to SCHEDULE METHODOLOGY

  • Methodology 1. The price at which the Assuming Institution sells or disposes of Qualified Financial Contracts will be deemed to be the fair market value of such contracts, if such sale or disposition occurs at prevailing market rates within a predefined timetable as agreed upon by the Assuming Institution and the Receiver.

  • Calculation methodology No adjustment in the Conversion Price need be made unless the adjustment would require an increase or decrease of at least 1% in the Conversion Price then in effect, provided that any adjustment that would otherwise be required to be made shall be carried forward and taken into account in any subsequent adjustment. Except as stated in this Article VI, the Conversion Rate will not be adjusted for the issuance of Common Stock or any securities convertible into or exchangeable for Common Stock or carrying the right to purchase any of the foregoing. Any adjustments that are made shall be carried forward and taken into account in any subsequent adjustment. All calculations under Article V and Section 6.06 hereof and this Section 6.07 shall be made to the nearest cent or to the nearest 1/10,000th of a share, as the case may be.

  • Claims Review Methodology a. C laims Review Population. A description of the Population subject to the Quarterly Claims Review.‌

  • Cost for Service and Charge Methodology – POS to The NWSA Service Area and Department (Acct if appropriate) Service Item (from list above) Method of Charges1 Basis for Charge Hourly Rate, Fixed Percentage or Formula 2021 Budgeted Amount2 Commission Office Dept #1200 3.a Fixed Based upon agreed amount of $250,000 per year. $250,000

  • Payment Methodology The Contractor shall be compensated based on the Service Rates in Attachment for units of service authorized by the Institution in a total amount not to exceed the Contract Maximum Liability established in Section C.1. The Contractor’s compensation shall be contingent upon the satisfactory completion of units of service or project milestones identified in Attachment B. The Contractor shall submit invoices, in form and substance acceptable to the Institution with all of the necessary supporting documentation, prior to any payment. Such invoices shall be submitted for completed units of service or project milestones for the amount stipulated.

  • Schedule The Work shall be performed as expeditiously as possible in conformity with the schedule requirements contained herein and in the Statement of Work. The draft and final versions of all deliverables shall be submitted by the dates specified in the Exhibit A Schedule and Project Period noted in Item No. 7 of this Agreement. It is understood and agreed that the delivery of the draft and final versions of such deliverables by the Contractor shall occur in a timely manner and in accordance with the requirements of the Exhibit A Schedule.

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

  • GSA Benchmarked Pricing Additionally, where the NYS Net Price is based upon an approved GSA Supply Schedule:

  • RDO Schedule a) The Schedule of RDO’s to be observed each year will generally be as provided under the VBIA.

  • Particular Methods of Procurement of Goods Works and Services (other than Consultants’ Services)

Time is Money Join Law Insider Premium to draft better contracts faster.