System Descriptions Sample Clauses
System Descriptions. System descriptions shall be submitted to Purchaser for approval no less than four (4) months before the start of the operator training program. PG&E will provide the typical format to be used for draft system descriptions. Final system descriptions shall be revised to reflect as-built conditions.
System Descriptions. A. Ordering System: A communication session will be established with Customer's central data center at a predetermined, mutually agreed upon schedule, on a daily basis, and Customer will transmit to Equifax the appropriate product orders in mutually agreed upon formats. Micro 6X locations will call into the Equifax Network as necessary.
B. Return System: Equifax will return information reports to Customer in electronic formats to be mutually agreed upon by the parties. These reports will be batch transmitted electronically to Customer's cental data center on a daily basis at a predetermined, mutually agreed upon schedule, or if applicable, returned, via the mail, or to Customer on a magnetic tape/cartridge. It shall be Customer's responsibility to distribute all information reports to its appropriate field office.
System Descriptions. The system descriptions will be the final version of system design specifications and descriptions that were developed for the project design manual. This document shall be updated following the startup process to reflect the as-built status of the Facility systems and equipment. The document shall contain the as-built P&IDs and one-line Drawings (P&IDs and one-line drawings to be included separately). The document shall contain such items as the system function, major component descriptions, system description, basis of design and control and instrumentation philosophy.
System Descriptions. 4.1 Seawater District Cooling Cold seawater will be drawn from the ocean bottom and delivered to the pump house intake where it will be pumped to the plate and frame heat exchangers located in Baha Mar’s CUP to produce chilled water. The pump house intake will consist of an equalizing manhole, fish screen and sump for each of the three pumps. The seawater pumps will be provided with VFDs for startup and shutdown, but will otherwise be operated at constant speed. A pipeline will be installed to convey the cold seawater to the titanium plate and frame heat exchangers. The seawater will then be discharged into a series of disposal ▇▇▇▇▇ adjacent to the Baha Mar CUP. A Plant Control System will be provided to control and monitor the SDC equipment.
4.2 S&W Chilled Water Distribution The Sheraton and Wyndham Chilled Water Distribution System will consist of associated piping, electrical equipment and controls. The system will deliver chilled water from the Baha Mar’s chilled water system to the existing Sheraton and Wyndham facilities. Baha Mar will be responsible for upgrading their distribution piping and pumping infrastructure to accommodate the S&W CWD system.
System Descriptions. The following system descriptions shall be incorporated into the design of the facility:
A. Exterior wall system(s), including materials, thickness and R-value
a. Precast panels will be 9 3/4“ thick
b. Precast panels will be 12’ wide
c. Insulation 1.5# 3” with a R- value of 12 as a system
d. Insulation will be 3” EPS
e. Office will we made up of Precast and Glass as shown in the rendering provided
f. Top of precast panel is approx. 38’ but will vary on each side of the building due to the required roof slope.
B. Roof system(s)
a. Roof insulation will be installed in two layers and R value as a system is calculated as 20.