Common use of Weather Days Clause in Contracts

Weather Days. A. Weather days are excusable delays. When weather conditions at the site prevent work from proceeding, immediately notify the Owner’s Project Manager for confirmation of the conditions. At the end of each calendar month, submit to the Owner’s Project Manager a list of Weather Days occurring in that month along with documentation of the impact on critical activities. Based on confirmation by the Owner’s Project Manager, any time extension granted will be issued by Change Order. If the Contractor and Owner cannot agree on the time extension, the Owner may issue a Unilateral Change Order for fair and reasonable time extension.

Appears in 13 contracts

Samples: Construction Services Agreement, Construction Services Agreement, Construction Services Agreement