Determination of Cost. The Design Professional shall review the Contractor’s proposed cost of the work, time to complete, effect upon the Overall Progress Schedule, and effect upon time dependent costs, and provide appropriate comments within fourteen calendar days concerning such proposed costs and expenses.
Determination of Cost. An increase or decrease in a GMP resulting from a change in the Work shall be determined by one or more of the following methods:
Determination of Cost. 49.1 Subject to Section 49.2 whenever it is necessary for the purposes of this Agreement to determine the cost of a Change, the cost will be the amount agreed upon by the Design-Builder and the Owner within a reasonable time after the issue arises in any given instance.
Determination of Cost. 9.3.1 An increase or decrease in the GMP or the Date of Substantial Completion or Date of Final Completion resulting from a change in the Work shall be determined by one or more of the following methods:
Determination of Cost. The amount of the increase or decrease in the Contract Price from a CO or COR, if any, shall be determined in one or more of the following ways as applicable to a specific situation:
Determination of Cost. An increase or decrease in the Contract Price resulting from a change in the Work shall be determined by one or more of the following methods:
Determination of Cost. An increase or decrease in the Job Order Contractor’s compensation resulting from a change in the Work shall be determined by one or more of the following methods: (A) unit prices set forth in this Contract or as subsequently agreed; (B) mutually accepted, itemized lump sum; (C) costs determined as defined in Article 3 above; or
Determination of Cost. 9.5.1 An increase or decrease in the GMP and/or estimated Cost of the Work resulting from a change in the Work shall be determined be Time and Material Costs per Exhibit B as defined in Paragraph 7.2, Article 8 and subparagraph 7.4.1.
Determination of Cost. The terms and conditions of the Wetlands Mitigation Agreement Shall include the payment of wetland credits by the developer to the PDA. The cost of the Wetlands credits shall he based on the cost of implementing the mitigation project, but in no case shall be less than $3.00/SF of approved impact with a $1500 minimum fee.
Determination of Cost. 14.4.1 An increase or decrease in the Cost of the Work resulting from a change in the Work shall be determined by one or more of the following methods: