Examples of Key Milestone Schedule in a sentence
In no event shall Contractor be entitled to any adjustment to the Key Milestone Schedule, Guaranteed Substantial Completion Date, Required Final Completion Date and the Contract Price for that portion of delay to the extent Contractor could have taken, but failed to take, commercially reasonable actions to mitigate such delay.
If Owner reasonably determines that such critical path method schedule does not conform with this Agreement, in any respect, including the Key Milestone Schedule, the Guaranteed Substantial Completion Date or the Required Final Completion Date, Contractor shall revise and resubmit such schedule to Owner within ten (10) Days.
This plan covers a three (3) year period and is updated on an annual basis.
If it is later determined that the Work was not Defective, then Owner shall reimburse Contractor for all costs incurred in connection with such repair or replacement and a Change Order shall be issued for such amount and shall address any impact the repair or replacement may have had on the Key Milestone Schedule, Guaranteed Substantial Completion Date and Required Final Completion Date, as applicable.
Contractor shall be entitled to request a Change Order (which acceptance of such Change Order shall not be unreasonably withheld by Owner and will be subject to the limitations referenced in Section 22.20) in order for Contractor, using GECP, to re-sequence the Work and adjust Key Milestone Dates to improve schedule, efficiency and resource allocation; provided that such changes to the Key Milestone Schedule shall not adjust the Guaranteed Substantial Completion Date.
Contractor’s relief for any material differences between the Soil Report and the Final Geotechnical Report shall be limited to an adjustment in the Contract Price, the Key Milestone Schedule, the Guaranteed Substantial Completion Date and the Required Final Completion Date; provided, however, Contractor shall use best efforts to prevent any extension to the Key Milestone Schedule, Guaranteed Substantial Completion Date and Required Final Completion Date as a result of such differences.
The Key Milestone Dates set forth in the Key Milestone Schedule may only be adjusted by Change Order.
No provision of this section shall be construed as requiring a consumer reporting agency to prevent a Federal, State, or local law enforcement agency from accessing blocked information in a consumer file to which the agency could otherwise obtain access under this title.
The Parties agree that only significant differences in subsurface conditions that would cause a major change in the manner, means or methods of constructing the foundations would require an extension to the Key Milestone Schedule, Guaranteed Substantial Completion Date and Required Final Completion Date, but mere changes in the number or type of piles would not entitle Contractor to such an extension.
The Contractor shall maintain the CPM Performance Measurement Baseline Schedule which shall contain the Key Milestone Schedule, Guaranteed Substantial Completion Date and Required Final Completion Date (as such dates may be adjusted by Change Order in accordance with this Agreement) as well as cost loading data corresponding to the Payment Milestones (as such Payment Milestones may be adjusted by Change Order in accordance with this Agreement).