Without prejudice to Clauses 40 (DBFM Co Event of Default), 42 (Authority Voluntary Termination), 46 (Compensation on Termination) and 47 (Consequences of Termination) the Authority shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the Completion Date [Phase Completion Date] and the Actual Completion Date [relevant Phase Actual Completion Date].
The following chart presents the projected data for each phase of the Project: Phase # of Homes Effective Date Phase Completion Date Minimum Phase Valuation Phase Approx.
Notwithstanding that the Works [relating to a Phase] may have been completed in accordance with this Agreement, the Actual Completion Date [Phase Actual Completion Date] may only occur on a date on or after the Completion Date [Phase Completion Date] unless the Authority, in its absolute discretion, agrees otherwise in writing.
Without prejudice to Clauses 40 (Sub-hubco Event of Default), 42 (Authority Voluntary Termination), 46 (Compensation on Termination) and 47 (Consequences of Termination) the Authority shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the Completion Date [Phase Completion Date] and the Actual Completion Date [relevant Phase Actual Completion Date].
Not less than [sixty (60)] Business Days prior to the [first Phase] Completion Date and each subsequent renewal date in respect of each of the Operational Insurances, Project Co must inform the Authority’s Representative of the forthcoming requirement to place or renew an Operational Insurance and its proposals for obtaining competitive quotations from at least ([three (3)] suitable insurers.
Without prejudice to Clause 40 (Project Co Event of Default), 42 (Authority Voluntary Termination), 46 (Compensation on Termination) and 47 (Consequences of Termination) the Authority shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the Completion Date [Phase Completion Date] and the Actual Completion Date [relevant Phase Actual Completion Date].
If and to the extent that a delay pertaining to one or more of the Phases of the Renovation Work delays the commencement or completion of another Phase of the Renovation Work, then the Required Phase Commencement Date and/or Required Phase Completion Date, as applicable, for the later Phase shall be extended by the actual delay caused by such Force Majeure event pertaining to the preceding Phase or Phases, it being understood that the Phases are intended to be completed sequentially.
Sub-hubco shall complete the Works [relating to a Phase] by the Completion Date [relevant Phase Completion Date].
If Lessee is delayed in the commencement of construction or completion of a Phase of the Renovation Work due to Force Majeure, then the Required Phase Commencement Date and/or the Required Phase Completion Date (if and to the extent that the event actually causes a delay in the commencement or completion of construction of the applicable Phase of the Renovation Work) shall be extended by the period of the delay caused by such Force Majeure.
Upon commencement of construction of the Renovation Work, Lessee shall thereafter diligently pursue the completion of each Phase of the Renovation Work by the Required Phase Completion Date for such Phase and the completion of all of the Renovation Work by the Required Completion Date.