Examples of Project Commercial Operation Date in a sentence
Project Commercial Operation Date Prudent Utility Practices means the last date on which all Units of the Project have been Commissioned in accordance with the terms of this PPA.
No later than sixty (60) days prior to the earlier of the first Unit Group Commercial Operation Date and the Project Commercial Operation Date, if the Seller shall not be the operator of the Project, Seller shall notify Buyer of such operator, and shall confirm that the agreement between Seller and such operator shall require the operator to operate the Project in accordance with the terms of this Agreement.
At least three (3) months prior to issuance of the EPC Notice to Proceed by Seller to the EPC Contractor, Seller shall provide Buyer a construction schedule detailing the schedule and construction milestones for completing the Project and each of the Units and reaching the Project Commercial Operation Date, the Initial Delivery Date and each Unit Group Commercial Operation Date.
Seller shall provide Buyer with monthly progress reports, including projected time to the Project Commercial Operation Date and each Unit Group Commercial Operation Date, and Buyer shall have the right, during business hours and upon reasonable Notice, to inspect the construction site and monitor construction of the Project.
In connection with the sale of Pre-Initial Delivery Date Products, Seller shall provide Buyer with a schedule (which shall be non-binding but shall be prepared in good faith) of the projected Project Commercial Operation Date and Unit Group Commercial Operation Dates for all Units and the projected quantities of Products to be delivered from such Units on and after their Unit Group Commercial Operation Dates no later than thirty (30) days after the first of the Turbine Contracts are executed.
Seller shall conduct an Initial Performance Test for purposes of establishing the Unit Group Commercial Operation Date or Project Commercial Operation Date for each Unit, and Subsequent Performance Tests during the term of, and the extent provided for in, the Turbine Supply Agreement after the achievement of such Commercial Operation Dates.
Seller shall provide Buyer regular updates on the process of finalizing this Appendix 1 which appendix shall be finalized no later than the Project Commercial Operation Date.
Interconnection Customer: Task Dates Initial Back-feed through Project Substation Date May 1, 2022 Project Commercial Operation Date for 274MWac December 15, 2022 The Interconnection Customer shall complete all Customer Interconnection Facilities and Transmission Owner Interconnection Facilities to be built by Interconnection Customer pursuant to Option to Build set forth in Schedules D, G and I of this CSA by May 1, 2022.
The schedule of work for the Interconnection Customer is: Task Dates Initial Back-feed through Project Substation Date 09/01/2022 Project Commercial Operation Date 12/31/2022 SCHEDULE K APPLICABLE TECHNICAL REQUIREMENTS AND STANDARDS “EKPC Facility Connection Requirements” rev.
At any time following the Project Commercial Operation Date, Borrower may require, subject as provided in this Agreement, that amounts standing to the credit of any Project Account shall be applied in the acquisition of Authorised Investments in accordance with this Section 24 (Authorised Investments).