Examples of Project Commercial Operation Date in a sentence
Seller shall provide Buyer with monthly progress reports, including projected time to the Project Commercial Operation Date and each Unit Group Commercial Operation Date, and Buyer shall have the right, during business hours and upon reasonable Notice, to inspect the construction site and monitor construction of the Project.
In this third request, TBE requested the Project Commercial Operation Date be extended another two years to June 2023.
A year later, in December 2017, TBE requested a subsequent 3-year extension of the Project Commercial Operation Date from April 15, 2018 to April 15, 2021.
At least three (3) months prior to issuance of the EPC Notice to Proceed by Seller to the EPC Contractor, Seller shall provide Buyer a construction schedule detailing the schedule and construction milestones for completing the Project and each of the Units and reaching the Project Commercial Operation Date, the Initial Delivery Date and each Unit Group Commercial Operation Date.
Its competence shall embrace the programme measures within the limits of the Community aid granted.
Section 30.4.4.5.2 of Attachment X to the OATT.determined that TBE had demonstrated a sufficient amount of progress to allow extension of the Project Commercial Operation Date under the “reasonable progress” standard in Section 30.4.4.5.2 of Attachment X to the OATT.
In connection with the sale of Pre-Initial Delivery Date Products, Seller shall provide Buyer with a schedule (which shall be non-binding but shall be prepared in good faith) of the projected Project Commercial Operation Date and Unit Group Commercial Operation Dates for all Units and the projected quantities of Products to be delivered from such Units on and after their Unit Group Commercial Operation Dates no later than thirty (30) days after the first of the Turbine Contracts are executed.
No later than sixty (60) days prior to the earlier of the first Unit Group Commercial Operation Date and the Project Commercial Operation Date, if the Seller shall not be the operator of the Project, Seller shall notify Buyer of such operator, and shall confirm that the agreement between Seller and such operator shall require the operator to operate the Project in accordance with the terms of this Agreement.
The Contract Fee shall be paid on the following schedule:• 50% of Contract Fee paid upon execution of a Net Meter Credit Agreement, Purchase & Sales Agreement (“PNS”), or whatever other similar agreement is entered into between East Providence and Respondent.• 50% of Contract Fee paid upon Project Commercial Operation Date (“COD”).
The schedule of work for the Interconnection Customer is: Initial Back-feed through Project Substation Date 09/01/2022 Project Commercial Operation Date 12/31/2022 “EKPC Facility Connection Requirements” rev.