Project Feature definition

Project Feature means features or elements of the Project that Developer has voluntarily agreed to construct or include that are not Community Benefits or Base Requirements and that provide a benefit to the public.
Project Feature or “Feature” means a discrete portion of a Project Element identified as such in the Overall Work Plan. These are not specific parts of the design-build process; rather, they are discrete physical portions of the actual construction.
Project Feature means a project component or subpart that in and of itself, meets priority project criteria. For example, a greater than 5000 sq. ft. parking lot within a non-priority project.

Examples of Project Feature in a sentence

  • If the Project has multiple Project Elements or Project Features, the Quarterly Work Plan should clearly indicate which costs will be incurred for each Project Element or Project Feature.

  • A final accounting of Real Estate Capital Outlay costs for a Project, Project Element, or Project Feature shall be included with the Final Statement of Costs and Project Completion Report.

  • From each disbursement of funds for Eligible Project Costs, with the exception of funds disbursed pursuant Real Estate Capital Outlay and Eligible Project Costs Advances, the State shall withhold ten percent (10%) of the State share until the Project Element of the Project for which the payment is made is completed or, if the work on a particular Project Element is further divided into Project Features, until the work on a Project Feature is completed.

  • In circumstances where one particular Project Element or Project Feature is ready to begin construction, this approval letter may be issued, but only for the phase that is ready.

  • Table 1 – Project Feature Summary Feature Improvement Description Applicable Reaches Quantity New Levee New Levee with Seepage Berm Q (Partial), R, S 3.9 Miles New Levee with RSP New Levee with Seepage Berm and Rock Slope Protection P, Q (Partial) 1.7 Miles Improve Existing Levee Improve existing levee with cutoff wall N, O 2.3 Miles Drainage Channel New drainage channel and culverts.

  • An additional approval letter will be required from the Department for each subsequent Project Element or Project Feature.

  • Funding Recipient may submit the Project Real Estate Plan by Project, Project Element, or Project Feature.

  • If any Project Element can be further divided into Project Features, Funding Recipient shall define the Project Features and provide separate budgets and schedules for each Project Feature.

  • The Funding Recipient may begin design work before its environmental documents are complete, but may not begin the construction portion of the approved Project until all environmental work for the Project Element or Project Feature has concluded.

  • Project Feature Description Demolition The following existing structures and equipment will be demolished: Influent lift station #2 and oxidation ditch.


More Definitions of Project Feature

Project Feature means features or elements of the Project that Developer has voluntarily agreed to construct or include beyond elements of the Project required to satisfy state and/or City statutory or regulatory requirements, including, but not limited to, payment of fees, CEQA mitigation measures set forth in the MMRP, City-Dedicated Open Space,
Project Feature. A discrete portion of a Project Element identified in the Overall Work Plan. These are not specific parts of the design-build process; rather, they are discrete physical portions of the actual construction.

Related to Project Feature

  • The Project Plan means the document to be developed by the Supplier and approved by the Purchaser, pursuant to GCC Clause 19, based on the requirements of the Contract and the Preliminary Project Plan included in the Supplier’s bid. The “Agreed and Finalized Project Plan” is the version of the Project Plan approved by the Purchaser, in accordance with GCC Clause 19.2. Should the Project Plan conflict with the Contract in any way, the relevant provisions of the Contract, including any amendments, shall prevail.

  • Project Plan means the document to be developed by the Contractor and approved by Webel Technology Ltd., based on the requirements of the Contract and the Preliminary Project Plan included in the Contractor’s bid. For the sake of clarity, the Agreed and Finalized Project Plan” refers to the version of the Project Plan submitted by the contractor after receiving the letter of Award and the same approved by Webel Technology Ltd. The project plan may be changed/ modified during the course of the project. Should the Project Plan conflict with the provisions of the Contract in any way, the relevant provisions of the Contract, including any amendments, shall prevail.

  • Project Work means the work required to complete the Project.

  • MSAA Indicator Technical Specifications document means, as the context requires, either or both of the document entitled “Multi-Sector Service Accountability Agreement (MSAA) 2019-20 Indicator Technical Specifications November 5, 2018 Version 1.3” and the document entitled “Multi-Sector Service Accountability Agreement (MSAA) 2019-20 Target and Corridor-Setting Guidelines” as they may be amended or replaced from time to time;

  • Programme of work means the Programme of work submitted by the contractor and approved by the Engineer-in-charge and includes and amendment thereto made from time to time and approved by the Engineer-in-charge;

  • Customization means any customer-specific modification to software that requires changes to the software’s source code.

  • Cost of work , in table above, shall mean the agreement amount of the work.

  • Project Schedule means a document that, with respect to each Phase of the Project, identifies, coordinates and integrates the anticipated design and construction schedules, the Contracting Authority’s and Owner's responsibilities, government authority reviews and other activities as are necessary for the timely completion of the Work.

  • Supplier System means the information and communications technology system used by the Supplier in performing the Services including the Software, the Equipment and related cabling (but excluding the Customer System);

  • Development Schedule shall have the meaning set forth in Section 1.1.

  • Statement of Work means the description of activities performed in completing the Project, as specified in the Contract and as may be amended.

  • DESCRIPTION OF WORK [INSERT] SUBMISSION DEADLINE: [INSERT] APPROXIMATE SPECIFICATIONS: [ ] words; [ ] pages; [ ] images/drawings/figures

  • Project Data means all proprietary data of the Project generated out of the Project operations and transactions, documents and related information including but not restricted to user data which the Bidder obtains, possesses or processes in the context of providing the Services to the users pursuant to this RFP including the SLA;

  • Project means the goods or Services described in the Signature Document or a Work Order of this Contract.

  • Design Criteria means the design criteria set out in the Ministry’s publication “Design Criteria for Sanitary Sewers, Storm Sewers and Forcemains for Alterations Authorized under Environmental Compliance Approval”, (as amended from time to time).

  • The Works/ Project means the works to be executed or done under this contract.

  • Maintenance Schedule means a document which describes the specific scheduled maintenance tasks and their frequency of completion necessary for the safe operation of those aircraft to which it applies;

  • Project Cost means the price payable to Service Provider over the entire period of Agreement (i.e. Rs. <in words>) for the full and proper performance of its contractual obligations.

  • technical specification means, with respect to any Software, the document setting forth the technical specifications for such Software and included in the Statement of Work.

  • Scope of Work means the description of Services and Deliverables specified in the Contract and as may be amended.

  • Schedule of Work means that schedule attached to the Interconnection Construction Service Agreement setting forth the timing of work to be performed by the Constructing Entity pursuant to the Interconnection Construction Service Agreement, based upon the Facilities Study and subject to modification, as required, in accordance with Transmission Provider’s scope change process for interconnection projects set forth in the PJM Manuals. Scope of Work:

  • The Works/Project means the works to be executed or done under this contract.

  • Project Plans mean the plans for the Project that are attached to this Agreement as Exhibit “B.”

  • Design Criteria Package means concise, performance-oriented drawings or specifications for a public construction project. The purpose of the Design Criteria Package is to furnish sufficient information to permit Design-Build Firms to prepare a bid or a response to the District’s Request for Proposals, or to permit the District to enter into a negotiated Design- Build Contract. The Design Criteria Package must specify performance- based criteria for the public construction project, including the legal description of the site, survey information concerning the site, interior space requirements, material quality standards, schematic layouts and conceptual design criteria of the project, cost or budget estimates, design and construction schedules, site development requirements, provisions for utilities, stormwater retention and disposal, and parking requirements applicable to the project. Design Criteria Packages shall require firms to submit information regarding the qualifications, availability, and past work of the firms, including the partners and members thereof.

  • Development Work means the conduct of preclinical and clinical trials, the compilation of the regulatory dossier concerning Licensed Products and the conduct of other work necessary or useful for obtaining Regulatory Approval of Licensed Products.

  • Completion of work means completion of the entire contracted work. Exhaustion of quantity of any particular item mentioned in the bid document shall not imply completion of work or any component thereof.