Seller shall ensure that the conceptual design and detailed design conforms to the Scope Book, as well as the other requirements of this Agreement, and will enable the Project to meet the Guaranteed LD Performance Test Requirements, Guaranteed PV Plant Availability, and Guaranteed ▇▇▇▇ Availability and Seller to achieve Final Completion.
High Any issue that appears to be reducing PV Plant production by 25% or more; or any issue that appears to be reducing ▇▇▇▇ capacity or charge/discharge rates by more than 25%.
For each year during the Term, within thirty (30) days after the anniversary of the Commencement Date, O&M Contractor shall deliver to Owner a written report containing the Measured Availability for the PV Plant during the prior twelve (12) month period and such information and data requested by Owner reasonably necessary to confirm the results of such determinations.
Production statistics for the PV Plant, including energy generation, auxiliary load consumed, ambient conditions (temperature, wind speed/direction, solar insolation, etc.) and availability shall be collected by SCADA system and O&M Contractor shall make such production statistics generated by the SCADA system available to Owner at all times.
O&M Contractor’s operation and maintenance personnel as a group, including any Persons engaged by O&M Contractor pursuant to Section 2.3, shall be qualified in operating and maintaining solar generating facilities similar to the PV Plant and battery energy storage facilities similar to the ▇▇▇▇, and any Persons engaged by O&M Contractor pursuant to Section 2.3 shall be qualified and experienced in the duties to which they are assigned.
If the Measured Availability for the PV Plant is equal to or greater than ninety-eight percent (98%) (the “Guaranteed Performance”) for any annual reporting period (or, if shorter, the initial reporting period), then the Guaranteed Performance for the PV Plant shall be deemed satisfied for such period and O&M Contractor shall have no liability to Owner in relation to the Guaranteed Performance for the PV Plant.
The power output for the PV Plant Capacity Test shall be measured at the Electrical Interconnection Point Meter.
All calibration certificates shall be submitted to Purchaser for review within six (6) months of the commencement of the PV Plant Capacity Tests.
Any adjustments made to the PV Plant or test measurement devices during any PV Plant Capacity Test shall be fully documented and shall be allowed only with Purchaser approval.
The Seller shall submit the above documentation to Purchaser for Purchaser review at least thirty (30) Business Days prior to commencing the PV Plant Capacity Tests.