Adjustment Only Through Change Order Sample Clauses

Adjustment Only Through Change Order. Unless otherwise provided in this Agreement, no change in the requirements of this Agreement, whether an addition to, deletion from, suspension of or modification to this Agreement, including any Work, shall be the basis for an adjustment for any change in the Contract Price, the Project Schedule, Payment Schedule, any Work, any of the Minimum Acceptance Criteria or Performance Guarantee or any other obligations of Contractor or right of Owner under this Agreement unless and until such addition, deletion, suspension or modification has been authorized by a Change Order executed and issued in accordance with and in strict compliance with the requirements of this Section 6.7. Contractor shall not perform any change in the Work unless and until such change is authorized pursuant to this Section 6.7, and should Contractor perform or claim to perform any changes in the Work prior to authorization by Change Order, all such costs and expenses incurred by Contractor shall be for Contractor’s account. No course of conduct or dealings between the Parties, nor implied acceptance of additions, deletions, suspensions or modifications to this Agreement, including any Work, and no claim that Owner has been unjustly enriched by any such addition, deletion, suspension or modification to this Agreement, whether or not there is in fact any such unjust enrichment, shall be the basis for any claim for an adjustment in the Contract Price, the Project Schedule, the Payment Schedule, any Work, any of the Minimum Acceptance Criteria or Performance Guarantee or any other obligations of Contractor under this Agreement.
AutoNDA by SimpleDocs
Adjustment Only Through Change Order. No change in the requirements of this Agreement, whether an addition to, deletion from, suspension of or modification to this Agreement, including any Work, shall be the basis for an adjustment for any change in the Guaranteed Maximum Price, the Milestone Dates (including the Guaranteed Substantial Completion Date or Guaranteed Final Completion Date), any Work, the Payment Schedule, any of the Minimum Acceptance Criteria, or any other obligations of Contractor or right of Owner under this Agreement unless and until such addition, deletion, suspension or modification has been authorized by a Change Order executed and issued in accordance with and in strict compliance with the requirements of this Article 6.
Adjustment Only Through Change Order. Willbros shall not perform a Change of any kind, except as authorized in a Change Order. Adjustments to the Guaranteed Maximum Price, the Preparation and Material Receipt Commencement Date, the Construction Commencement Date or the Scheduled Mechanical Completion Date shall only be made by Change Order. No course of conduct or dealings between the Parties, nor express or implied acceptance of additions, deletions, suspensions or modifications to this Agreement, the Drawings or the Specifications, including any Work, and no claim that Cheniere has been unjustly enriched by any such addition, deletion, suspension or modification of this Agreement, the Drawings or the Specifications, whether or not there is in fact any such unjust enrichment, shall be the basis for any claim for an adjustment in the Guaranteed Maximum Price, the Preparation and Material Receipt Commencement Date, the Construction Commencement Date, the Scheduled Mechanical Completion Date or any other obligations of Willbros under this Agreement.
Adjustment Only Through Change Order. No change in the requirements of this Agreement, whether an addition to, deletion from, suspension of or modification to this Agreement, including any Work, shall be the basis for an adjustment for any change in the Contract Amount, the Project Schedule (including the Guaranteed Commercial Operation Date, Guaranteed Substantial Completion Date or Guaranteed Final Completion Date), any Work, the Milestone Payment Schedule, any of the Minimum Performance Standards or Performance Guarantees or any other obligations of Contractor or right of Owner under this Agreement unless and until such addition, deletion, suspension or modification has been authorized by a Change Order executed and issued in accordance with and in strict compliance with the requirements of this ARTICLE XI. Contractor shall not perform any change in the Work unless and until such change is authorized pursuant to this ARTICLE XI, and should Contractor perform or claim to perform any changes in the Work prior to authorization by Change Order, all such costs and expenses incurred by Contractor shall be for Contractor's account
Adjustment Only Through Change Order. Except as provided in Section 10.4 and without limiting Contractor’s entitlement to any Change Order as expressly provided in this Agreement, no change in the requirements of this Agreement, whether an addition to, deletion from or modification to this Agreement, including any Work, shall be the basis for an adjustment for any change in the Contract Price, the Baseline Schedule, the Baseline Cash Flow Plan, any Work or any other obligations of Contractor or right of Owner under this Agreement unless and until such addition, deletion or modification has been authorized by a Change Order number assigned by Owner in respect to the final PAR for such addition, deletion or modification (whether with or without qualifications by Owner) in accordance with and in strict compliance with the requirements of this Article. Contractor shall not 302093599 v11 perform any Change in the Work unless and until such Change is authorized pursuant to this Article, and should Contractor perform or claim to perform any Change in the Work prior to authorization by Change Order or pursuant to Section 10.4, all costs and expenses incurred by Contractor in performing such Change or, if required by Owner, reversing or cancelling such Change, if performed, shall be for Contractor’s account unless otherwise agreed to by Owner. No course of conduct or dealings between the Parties, nor implied acceptance of additions, deletions or modifications to this Agreement, including any Work, and no claim that Owner or any of its Affiliates have been unjustly enriched by any such addition, deletion or modification to this Agreement, whether or not there is in fact any such unjust enrichment, shall be the basis for any claim for an adjustment in the Contract Price, the Baseline Schedule, the Baseline Cash Flow Plan or any other obligations of Contractor under this Agreement.

Related to Adjustment Only Through Change Order

  • Section 754 Adjustment To the extent an adjustment to the adjusted tax basis of any Partnership asset pursuant to Code Section 734(b) or Code Section 743(b) is required, pursuant to Regulations Section 1.704-1(b)(2)(iv)(m)(2) or Regulations Section 1.704-1(b)(2)(iv)(m)(4), to be taken into account in determining Capital Accounts as the result of a distribution to a Holder in complete liquidation of his interest in the Partnership, the amount of such adjustment to the Capital Accounts shall be treated as an item of gain (if the adjustment increases the basis of the asset) or loss (if the adjustment decreases such basis) and such gain or loss shall be specially allocated to the Holders in accordance with their interests in the Partnership in the event that Regulations Section 1.704-1(b)(2)(iv)(m)(2) applies, or to the Holders to whom such distribution was made in the event that Regulations Section 1.704-1(b)(2)(iv)(m)(4) applies.

  • Adjustment, etc Any adjustment, indulgence, forbearance or compromise that might be granted or given by any of the Lenders to Borrower or Guarantor or any Person liable on the Liabilities;

  • Adjustments Not Yet Effective Notwithstanding anything to the contrary in this Indenture or the Notes, if:

  • Audit Adjustment If any audit of the records, books or accounts relating to the Properties discloses an overpayment or underpayment of Management Fees, Owner or Manager shall promptly pay to the other party the amount of such overpayment or underpayment, as the case may be. If such audit discloses an overpayment of Management Fees for any fiscal year of more than the correct Management Fees for such fiscal year, Manager shall bear the cost of such audit.

  • ADJUSTMENT OF CONTRACT PRICE The Contract Price shall be subject to adjustment, as hereinafter set forth, in the event of the following contingencies (it being understood by both parties that any reduction of the Contract Price is by way of liquidated damages and not by way of penalty):

  • Section 754 Adjustments To the extent an adjustment to the adjusted tax basis of any Company asset, pursuant to Code Section 734(b) or Code Section 743(b) is required, pursuant to Regulations Section 1.704-1(b)(2)(iv)(m)(2) or 1.704-1(b)(2)(iv)(m)(4), to be taken into account in determining Capital Accounts as the result of a distribution to a Unit Holder in complete liquidation of such Unit Holder’s interest in the Company, the amount of such adjustment to Capital Accounts shall be treated as an item of gain (if the adjustment increases the basis of the asset) or loss (if the adjustment decreases such basis) and such gain or loss shall be specially allocated to the Unit Holders in accordance with their interests in the Company in the event Regulations Section 1.704-1(b)(2)(iv)(m)(2) applies, or to the Unit Holder to whom such distribution was made in the event Regulations Section 1.704-1(b)(2)(iv)(m)(4) applies.

  • Additional Adjustment If, in Dealer’s commercially reasonable judgment, the actual cost to Dealer (or an affiliate of Dealer), over any [10] consecutive Scheduled Trading Day period, of borrowing a number of Shares equal to the Number of Shares to hedge in a commercially reasonable manner its exposure to the Transaction exceeds a weighted average rate equal to [25] basis points per annum, the Calculation Agent shall reduce the Forward Price to compensate Dealer for the amount by which such cost exceeded a weighted average rate equal to [25] basis points per annum during such period. The Calculation Agent shall notify Counterparty prior to making any such adjustment to the Forward Price. Extraordinary Events: In lieu of the applicable provisions contained in Article 12 of the Equity Definitions, the consequences of any Extraordinary Event (including, for the avoidance of doubt, any Merger Event, Tender Offer, Nationalization, Insolvency, Delisting, or Change In Law) shall be as specified below under the headings “Acceleration Events” and “Termination Settlement” in Paragraphs 7(f) and 7(g), respectively. Notwithstanding anything to the contrary herein or in the Equity Definitions, no Additional Disruption Event will be applicable except to the extent expressly referenced in Paragraph 7(f)(iv) below. The definition of “Tender Offer” in Section 12.1(d) of the Equity Definitions is hereby amended by replacing “10%” with “15%.” Dividends: No adjustment shall be made if, on any day occurring after the Trade Date, Counterparty declares a distribution, issue or dividend to existing holders of the Shares of (i) any cash dividend (other than an Extraordinary Dividend) to the extent all cash dividends having an ex-dividend date during the period from and including any Forward Price Reduction Date (with the Trade Date being a Forward Price Reduction Date for purposes of this clause (i) only) to but excluding the next subsequent Forward Price Reduction Date differs from, on a per Share basis, the Forward Price Reduction Amount set forth opposite the first date of any such period on Schedule I, (ii) share capital or securities of another issuer acquired or owned (directly or indirectly) by Counterparty as a result of a spin-off or other similar transaction or (iii) any other type of securities (other than Shares), rights or warrants or other assets, for payment (cash or other consideration) at less than the prevailing market price as determined by Dealer. Non-Reliance: Applicable Agreements and Acknowledgments: Regarding Hedging Activities: Applicable

  • Adjustment Procedure (a) Sellers will prepare and will cause , the Company's certified public accountants, to audit consolidated financial statements ("Closing Financial Statements") of the Company as of the Closing Date and for the period from the date of the Balance Sheet through the Closing Date, including a computation of consolidated stockholders' equity as of the Closing Date. Sellers will deliver the Closing Financial Statements to Buyer within sixty days after the Closing Date. If within thirty days following delivery of the Closing Financial Statements, Buyer has not given Sellers notice of its objection to the Closing Financial Statements (such notice must contain a statement of the basis of Buyer's objection), then the consolidated stockholders' equity reflected in the Closing Financial Statements will be used in computing the Adjustment Amount. If Xxxxx gives such no xxxx of objection, then the issues in dispute will be submitted to , certified public accountants (the "Accountants"), for resolution. If issues in dispute are submitted to the Accountants for resolution, (i) each party will furnish to the Accountants such workpapers and other documents and information relating to the disputed issues as the Accountants may request and are available to that party or its Subsidiaries (or its independent public accountants), and will be afforded the opportunity to present to the Accountants any material relating to the determination and to discuss the determination with the Accountants; (ii) the determination by the Accountants, as set forth in a notice delivered to both parties by the Accountants, will be binding and conclusive on the parties; and (iii) Buyer and Sellers will each bear 50% of the fees of the Accountants for such determination.

  • CPI Adjustment In this Agreement, “CPI-Adjusted” in reference to an amount means that amount is adjusted under the following formula: N  C  (1 CPIn  CPIc ) CPIc where: ”N” is the new amount being calculated; and “C” is the current amount being adjusted; and

  • Adjustment of Impositions Impositions imposed in respect of the tax-fiscal period during which the Term terminates shall be adjusted and prorated between Lessor and Lessee, whether or not such Imposition is imposed before or after such termination, and Lessee’s obligation to pay its prorated share thereof after termination shall survive such termination.