CONSTRUCTION BY OWNER OR OTHER CONTRACTORS. 3.3.1 The Owner reserves the right to award separate contracts in connection with other parts of the Project to other contractors and to perform work with its Personnel. Such work by other contractors or Owner’s Personnel may include utility relocation and surveying, testing, sampling and quality assurance estimates prior to, and possibly during, the Work.
3.3.2 Subject to and without limitation to 4.2 – HEALTH AND SAFETY, when separate contracts are awarded for other parts of the Project, or when work is performed by the Owner’s Personnel, the Contractor shall: .1 co-ordinate, schedule and sequence the activities and work of other contractors and Owner's Personnel on the Project with the Work; and
CONSTRUCTION BY OWNER OR OTHER CONTRACTORS. 3.2.1 The Owner reserves the right to award separate contracts in connection with work related to the Project to other contractors and to perform work related to the Project with its own forces. The Owner may assign the coordination, scheduling and safety training of the work of the Owner’s other contractors or the Owner’s own forces to the Contractor.
3.2.2 When separate contracts are awarded for work related to the Project, or when such work is performed by the Owner’s own forces, the Owner shall:
CONSTRUCTION BY OWNER OR OTHER CONTRACTORS. (a) Owner reserves the right to award separate contracts in connection with work related to the Project to other contractors and to perform work related to the Project with its own forces. Owner may assign the coordination and scheduling of the work and the safety training in respect of the work of Owner’s other contractors or Owner’s own forces to Project Co.
(b) When separate contracts are awarded for work related to the Project, or when such work is performed by Owner’s own forces, Owner shall:
(i) cause Owner’s other contractors or Owner’s own forces to comply with the instructions of Project Co relating to coordination and scheduling of the activities and work of such contractors or Owner’s own forces with the Work to be performed under this Project Agreement;
(ii) enter into separate contracts with other contractors under conditions of contract which are compatible with the conditions of this Project Agreement and provide for compliance by such other contractors with Section 11.19(c) and all directions of Project Co in respect of any matter regarding site safety;
(iii) ensure that insurance coverage is provided as would be required by a prudent owner similarly situated and coordinate such insurance with the insurance coverage of Project Co as it affects the Work and in any event, such insurance shall provide for liability insurance of not less than $[REDACTED]; and
(iv) take all necessary steps to avoid labour disputes or other disputes on the Project arising from the work of Owner’s other contractors or Owner’s own forces.
(c) When separate contracts are awarded for work related to the Project, or when work is performed by Owner’s own forces, Project Co shall:
(i) subject to the performance by Owner of its obligations under Section 11.19(b)(i) and 11.19(b)(ii), provide for the coordination and scheduling of the activities and work of Owner’s other contractors and Owner’s own forces with the Work to be performed under this Project Agreement;
(ii) afford Owner and Owner’s other contractors reasonable opportunity to introduce and store their products and use their construction machinery and equipment to execute their work;
(iii) participate with Owner’s other contractors and Owner in reviewing their construction schedules when directed to do so by Owner, the Owner’s Project Manager and/or the Consultant;
(iv) where part of the Work is affected by or depends upon, for its proper execution, the work of Owner’s other contractors or Owner’s own forces, pro...
CONSTRUCTION BY OWNER OR OTHER CONTRACTORS. Delete paragraph 3.2.2.2 in its entirety and replace with the following:
CONSTRUCTION BY OWNER OR OTHER CONTRACTORS. 3.2.1 The Owner reserves the right to award separate contracts in connection with other parts of the Project to other contractors and to perform work with own forces.
3.2.2 When separate contracts are awarded for other parts of the Project, or when work is performed by the Owner's own forces, the Owner shall:
.1 provide for the co-ordination of the activities and work of other contractors and Owner's own forces with the Work of the Contract; .2 assume overall responsibility for compliance with the applicable health and construction safety legislation at the Place of the Work; .3 enter into separate contracts with other contractors under conditions of contract which are compatible with the conditions of the Contract;
CONSTRUCTION BY OWNER OR OTHER CONTRACTORS. GC3.2.2 is amended by deleting the first sentence and replacing it with the following:
CONSTRUCTION BY OWNER OR OTHER CONTRACTORS. GC3.2.2is amended by deleting the first sentence and replacing it with the following: When separate contracts are awarded for other parts of the Project, or when work is performed by the Owner's own forces, the Contractor shall:
CONSTRUCTION BY OWNER OR OTHER CONTRACTORS. .1 Delete subparagraph 3.2.2.1 in its entirety .2 Delete subparagraph 3.2.2.2 in its entirety .3 Add new subparagraph 0.0.0.0:
CONSTRUCTION BY OWNER OR OTHER CONTRACTORS. 3.2.1 All materials and equipment shall be supplied by the Contractor with the exception of such material or equipment as the Contract Documents indicate will be supplied by the Region. In all cases where materials or equipment are supplied by the Region, the Region will make every effort to have a sufficient supply of such material or equipment tested, examined, approved and ready for use at such times as they may be required, but in case the Region fails to furnish sufficient supply at any time, the Contractor shall not be entitled to any compensation or additional time for delay except as may be allowed in accordance with GC
CONSTRUCTION BY OWNER OR OTHER CONTRACTORS. 3.2.2 Delete G.C. 3.2.2.1 and G.C. 3.2.2.2.