Design-Builder’s Right to Stop Work Sample Clauses

Design-Builder’s Right to Stop Work. 15.4.1 Design-Builder may, in addition to any other rights afforded under the Contract Documents or at Law, stop work for Owner’s failure to pay amounts properly due under Design-Builder’s Application for Payment. 15.4.2 If any of the events set forth in Section 15.4.1 above occur, Design-Builder has the right to stop work by providing written notice to Owner that Design-Builder will stop work unless such event is cured within seven (7) Days from Owner’s receipt of Design-Builder’s notice. If Owner fails to cure or reasonably commence to cure such problem and thereafter diligently pursue such cure to completion, then Design-Builder may give a second written notice to Owner of its intent to stop work within an additional seven (7) Day period. If Owner, within such second seven (7) Day period, fails to cure, or reasonably commence to cure such problem and thereafter diligently pursue such cure to completion, then Design-Builder may stop work. In such case, Design-Builder shall be entitled to make a claim for adjustment to the Contract Price and Contract Time(s) to the extent it has been adversely impacted by such stoppage.
AutoNDA by SimpleDocs
Design-Builder’s Right to Stop Work. 15.4.1 Subject to Section 15.4.2, Design-Builder may, in addition to any other rights afforded under the Contract Documents or at Law, stop work for Owner’s failure to pay amounts properly due under Design-Builder’s Application for Payment. 15.4.2 If Owner fails to pay amounts properly due to Design-Builder under an Application for Payment, Design Builder may stop work by providing written notice to Owner that Design-Builder will stop work unless such payment is received within thirty (30) Days from Owner’s receipt of Design-Builder’s notice. If Design-Builder stops work pursuant to this Section 15.4.2, Design-Builder shall be entitled to make a claim for adjustment to the Contract Price and Contract Time(s) to the extent it has been adversely impacted by such stoppage.
Design-Builder’s Right to Stop Work. 15.4.1 Design-Builder may, in addition to any other rights afforded under the Contract Documents or at law, stop work for the following reasons: a) Owner's failure to provide financial assurances as required under Section 4.3: or b) Owner's failure to pay amounts properly due under Design-Builder's Application for Payment. 15.4.2 If any of the events set forth in Section 15.4.1 above occur Design-Builder has the right to stop work by providing written notice to Owner that Design-Builder will stop work unless such event is cured within seven (7) days from Owner's receipt of Design-Builder's notice. If Owner fails to cure or reasonably commence to cure, such problem, then Design-Builder may give a second written notice to Owner of its intent to stop work within an additional seven (7) day period. If Owner, within such second seven (7) day period, fails to cure, or reasonably commence to cure, such problem, then Design-Builder may stop work. In such case, Design-Builder shall be entitled to make a claim for adjustment to the Contract Price and Contract Time(s) to the extent it has been adversely impacted by such stoppage.
Design-Builder’s Right to Stop Work. 11.3.1 Design-Builder may, in addition to any other rights afforded under the Contract Documents or at law, stop work for the following reasons: .1 Owner's failure to provide financial assurances as required under Section 3.3 hereof; or .2 Owner's failure to pay amounts properly due under Design-Builder's Application for Payment. 11.3.2 Should any of the events set forth in Section 11.3.1 above occur, Design-Builder has the right to provide Owner with written notice that Design-Builder will stop work unless said event is cured within seven (7) days from Owner's receipt of Design-Builder's notice. If Owner does not cure the problem within such seven (7) day period, Design-Builder may stop work. In such case, Design-Builder shall be entitled to make a claim for adjustment to the Contract Price and Contract Time(s) to the extent it has been adversely impacted by such stoppage.
Design-Builder’s Right to Stop Work. Design-Builder may, in addition to any other rights afforded under the Contract Documents or at law, stop work upon the Owner’s failure to pay amounts approved by Owner’s Representative pursuant paragraph 7(a)(i) above. Should the event set forth in Article 15.c.i above occur, Design-Builder has the right to provide the School Board with written notice that Design-Builder will stop work unless said event is cured within fifteen (15) days from the School Board’s receipt of Design-Builder’s notice. If the School Board does not cure the problem within such fifteen (15) day period, Design-Builder may stop work. In such case, Design-Builder shall be entitled to make a claim for adjustment to the Contract Price and Contract Time(s) to the extent it has been adversely impacted by such stoppage.
Design-Builder’s Right to Stop Work. Design-Builder may, in addition to any other rights afforded under the Contract Documents or at law, stop work for the following reasons:
Design-Builder’s Right to Stop Work. 8.1.1 Design-Builder may, without cause and for its convenience, order Design-Build Subcontractor in writing to stop and suspend the Work. Such suspension shall not exceed sixty
AutoNDA by SimpleDocs
Design-Builder’s Right to Stop Work. 15.4.1 Design-Builder may, in addition to any other rights afforded under the Contract Documents or at Law, stop work for Owner’s failure to pay amounts properly due under Design-Builder’s Application for Payment; provided that Design-Builder shall not be entitled to stop Work as a result of non-payment of amounts withheld by Owner pursuant to Section 10.2.6. 15.4.2 If any of the events set forth in Section 15.4.1 above occur, Design-Builder has the right to stop work by providing written notice to Owner that Design-Builder will stop work unless such event is cured within seven (7) Days from Owner’s receipt of Design-Builder’s notice. If Owner fails to cure or reasonably commence to cure such problem and thereafter diligently pursue such cure to completion, then Design-Builder may give a second written notice to Owner of its intent to stop work within an additional seven (7) Day period. If Owner, within such second seven (7) Day period, fails to cure, or reasonably commence to cure such problem and thereafter diligently pursue such cure to completion, then Design-Builder may stop work; provided that Design-Builder shall not be entitled to stop Work as a result of non-payment of amounts withheld by Owner pursuant to Section 10.2.6. In such case, Design-Builder shall be entitled to make a claim for adjustment to the Contract Price and contract time(s) to the extent it has been adversely impacted by such stoppage.
Design-Builder’s Right to Stop Work. 11.3.1 Design-Builder may, in addition to any other rights afforded under the Contract Documents or at law, stop work for the following reasons: .1 Department’s failure to provide financial assurances as required under Section 3.3 hereof; or .2 Department’s failure to pay amounts properly due under Design-Builder’s Application for Payment. 11.3.2 Should any of the events set forth in Section 11.3.1 above occur, before exercising its rights under this section, Design-Builder shall provide Department with written notice that Design-Builder will stop work unless said event is cured within ten (10) days from Department’s receipt of Design-Builder’s notice. If Department does not cure the problem within such ten (10) day period, Design-Builder may stop work. In such case, Design-Builder shall be entitled to make a claim for adjustment to the Contract Price and Contract Time(s) to the extent it has been adversely impacted by such stoppage.
Design-Builder’s Right to Stop Work. 11.3.1 Design-Builder may, in addition to any other rights afforded under the Contract Documents or at law, stop work for the following reason: Owner’s failure to pay amounts properly due under Design-Builder’s Application for Payment. 11.3.2 Should the event set forth in Section 11.3.1 above occur, Design-Builder has the right to provide Owner with written notice that Design-Builder will stop work unless said event is cured within five (5) days from Owner’s receipt of Design-Builder’s notice. If Owner does not cure the problem within such five (5) day period, Design-Builder may stop work. In such case, Design-Builder shall be entitled to make a claim for adjustment to the Contract Price and Contract Time(s) to the extent it has been adversely impacted by such stoppage.