FACILITY MECHANICAL COMPLETION Sample Clauses

FACILITY MECHANICAL COMPLETION. 19.1.1 Upon satisfaction of the conditions set forth in this Section 19.1, Contractor shall give Notice to Owner that Facility Mechanical Completion has occurred, which shall only be when all of the following items set forth in this Section 19.1 have occurred: (a) all the conditions for LNG Production System Mechanical Completion for all the LNG Production Systems set forth in Section 18.1 have been met, and Owner has received and accepted the LNG Production System RFSU Certificate for all of the LNG Production Systems in accordance with Section 18.2; (b) Contractor has certified to Owner that the Facility has been designed (to the extent included in the Work), integrated and constructed and is ready for operation or operating in accordance with the requirements set forth in Exhibit A, applicable Laws and Permits and Owner Standards, and has performed all of its obligations under this Agreement then to be performed, and the Work is free of all Defects and Deficiencies (other than the Punch List Items); (c) Owner has received from Contractor all final Permits required to be obtained by Contractor and, if final Permits are not available, all temporary Permits to enable Owner to operate the Facility uninterrupted until such time as such final Permits are obtained; (d) Contractor has performed all other provisions hereof and delivered all items required hereby to achieve Facility Mechanical Completion in a manner reasonably satisfactory to Owner; and (e) Contractor has delivered to Owner a certificate certifying the satisfaction of each of the foregoing items in this Section 19.1.1. 19.1.2 At such time as Owner and the Independent Engineer have confirmed that each of the foregoing matters have been completed, Owner shall issue to Contractor a certificate stating the Facility Mechanical Completion Date. Facility Mechanical Completion shall be deemed to occur on the date the final item set forth in Section 19.1.1 occurs, as determined by Owner, and not the date such certification is received.
AutoNDA by SimpleDocs
FACILITY MECHANICAL COMPLETION. 19.1.1 Upon satisfaction of the conditions set forth in this Section 19.1, Contractor shall give Notice to Owner that Facility Mechanical Completion has occurred, which shall only be when all of the following items set forth in this Section 19.1 have occurred: (a) all the conditions for LNG Production System Mechanical Completion for all the LNG Production Systems set forth in Section 18.1 have been met, and Owner has received and accepted the LNG Production System RFSU Certificate for all of the LNG Production Systems in accordance with Section 18.2;
FACILITY MECHANICAL COMPLETION. Mechanical Completion shall be deemed to have occurred when all of the following have occurred: (a) Contractor has demonstrated that the Facility was constructed in accordance with the requirements of Exhibit A; (b) Contractor has demonstrated that the Facility has been completed in accordance with the plans and specifications and all equipment has passed all standard and required electrical testing, [hypot, meggar] testing, flushing, and pressure testing of piping, and all other applicable testing per codes and guides; (c) Contractor has corrected all defects, deficiencies, and/or discrepancies identified by Owner in the Work with respect to the Facility, pursuant to the provisions of Section 12.02, and Owner has accepted such corrections in writing; (d) the Facility is ready to be tested, commissioned, and started-up consistent with the requirements of this Contract and Industry Standards; (e) Contractor has prepared and delivered a Punchlist (Mechanical Completion) containing a list of Work items that were not completed at the time of Mechanical Completion. The Punchlist shall include a projected date when each unfinished work item shall be completed and the expected price of each unfinished work item.

Related to FACILITY MECHANICAL COMPLETION

  • Substantial Completion 9.8.1 When the Contractor considers that the Work, or a designated portion thereof which has been accepted in writing to by the State, is substantially complete as defined in Subparagraph

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Project Completion The Contractor agrees to schedule a final job walk with the County. If required, the County will prepare a list of incomplete items, the “Punch List”. The Contractor agrees to complete the “Punch List” corrections and schedule a final project completion job walk. The County will sign the “Punch List” as completed when determined, the project is finished. The Contractor agrees to submit the following along with its final payment request: