Maximum Payment Schedule Sample Clauses

Maximum Payment Schedule. The Project Schedule shall provide for payment to be made solely on the basis of progress by DB Contractor, subject to a cap on payments shown on the Maximum Payment Schedule established for the Project. The Maximum Payment Schedule shall not limit payment for Change Order Work unless otherwise specified in the Change Order. In other words, at no time shall DB Contractor’s cumulative total progress payments (including mobilization payments but exclusive of payments for Change Order Work) exceed the cumulative total expenditure permitted by the Maximum Payment Schedule. The Maximum Payment Schedule shall be calculated based on the monthly expenditure rate set forth in Exhibit 5 for the Project. If DB Contractor and TxDOT mutually agree in writing to a different expenditure rate at any time, then such revised rate shall thereafter be the Maximum Payment Schedule for the Project. The Maximum Payment Schedule shall be revised from time to time thereafter upon request by TxDOT or by DB Contractor on its own initiative, as appropriate to account for any changes in the Price as evidenced by Change Orders and/or amendments. The aggregate amount of progress payments to DB Contractor hereunder shall not exceed the amount allowed by the Maximum Payment Schedule at any time, exclusive of payments for Change Order Work, without the prior written approval of TxDOT, which approval may be withheld in its sole discretion.
AutoNDA by SimpleDocs
Maximum Payment Schedule. The Maximum Payment Schedule for the Project is set forth in Exhibit 10 to this DBA.
Maximum Payment Schedule. The Project Schedule shall provide for payment to be made solely on the basis of progress by DB Contractor, subject to a cap on payments shown on the Maximum Payment Schedule established for the Project. The aggregate amount of progress payments to DB Contractor hereunder shall not exceed the amount allowed by the Maximum Payment Schedule at any time, exclusive of payments for Change Order Work, without the prior written approval of TxDOT, which approval may be withheld in its sole discretion. The Maximum Payment Schedule shall be calculated based on the monthly expenditure rate set forth in Exhibit 5 for the Project.
Maximum Payment Schedule. The Maximum Payment Schedule is set forth in Exhibit 10 to this DBA. Unless and until TxDOT issues a DWC NTP, the Maximum Payment Schedule shall be the schedule set forth in Exhibit 10-1. In the event TxDOT elects to exercise its right to issue a DWC NTP, the Price shall be increased by the DWC Price for each such DWC in accordance with Section 4.1 of this DBA. In such event, the Maximum Payment Schedule shall also be increased by adding the amounts set forth in the applicable DWC Maximum Payment Schedule set forth in Exhibit 10-2 to the corresponding months in the then current Maximum Payment Schedule. In such event, the payment for the last month of the Maximum Payment Schedule shall also be increased by adding the remaining amounts set forth in the applicable DWC Maximum Payment Schedule set forth in Exhibit 10-2 that come after the Substantial Completion Deadline. Upon such amendment thereof, all references to the Maximum Payment Schedule set forth in the Contract Documents shall mean the schedule as amended hereby. TxDOT shall have the right, but not the obligation, to prepare and deliver a revised Maximum Payment Schedule adjusted as described herein to incorporate the applicable DWC Price and related DWC Maximum Payment Schedule.
Maximum Payment Schedule. (Engineering Work and Site Preparation Work) See Attachment 3 to this Exhibit 3
Maximum Payment Schedule. DWC2 MAXIMUM PAYMENT SCHEDULE – DWC3
Maximum Payment Schedule. The Project Schedule shall provide for payment of the Price to be made solely on the basis of progress by DB Contractor, subject to a cap on progress payments shown on the Maximum Payment Schedule established for each Segment of the Project. The Maximum Payment Schedule shall not limit payment for Compensable Utility Adjustment Costs or for Change Order Work unless otherwise specified in the Change Order. In other words, at no time shall DB Contractor’s cumulative total progress payments (including mobilization payments but exclusive of payments for Compensable Utility Adjustment Costs and Change Order Work) exceed the cumulative total expenditure permitted by the Maximum Payment Schedule for the applicable Segment. The Maximum Payment Schedule for Work authorized by NTPs shall be calculated based on the monthly expenditure rate set forth in Exhibit 5A (as such exhibit may be replaced by Exhibit 5C in accordance with Section 12.1.2) for Segment 1 and Exhibit 5B for Segment 2. The applicable Maximum Payment Schedule will be adjusted to account for any Price adjustment made pursuant to Section 12.1.7 or Section 12.1.8 and any extension of a Completion Deadline made pursuant to Section 4.2.1.2
AutoNDA by SimpleDocs
Maximum Payment Schedule. The Project Schedule shall provide for payment to be made solely on the basis of progress by DB Contractor, subject to a cap on payments shown on the Maximum Payment Schedule established for the Project. The Maximum Payment Schedule shall not limit payment for Change Order Work unless otherwise specified in the Change Order. In other words, at no time shall DB Contractor’s cumulative total progress payments (including mobilization payments but exclusive of payments for Change Order Work) exceed the cumulative total expenditure permitted by the Maximum Payment Schedule. The Maximum Payment Schedule shall be calculated based on the monthly expenditure rate set forth in Exhibit 5 for the Project. If a Limited NTP2 is issued, the monthly expenditure rate in the Maximum Payment Curve will be adjusted to account for the early Work, as well as any Price adjustment made pursuant to Section 12.1.7.2 and any extension of Completion Deadlines made pursuant to Section 4.2.1.

Related to Maximum Payment Schedule

  • Payment Schedule The purchase price for timber sold under this contract shall be paid in advance as follows: The first payment shall be paid within 30 days of the notification of high bid or before operating, whichever occurs first. The first payment shall be 10 percent of the total estimated bid value. The total estimated bid value shall be the sum obtained by multiplying the estimated timber volumes by the prices given in Section 44 less the amount of the project work. Cash bid deposits shall be applied to the initial payment. Subsequent payments shall be made in advance of timber removal when log hauling begins. Each payment shall be made before the value of timber removed equals one-half an advance payment or within the time period stated on the billing if PURCHASER is more than one-half of a payment in advance. The amount of each advance payment shall be calculated by dividing the total estimated bid value less the initial payment by 9; with the total estimated bid value being the sum obtained by multiplying the estimated timber volumes by the prices given in Section 44 less the amount of the project work. STATE may accept partial payment, upon written request, if logging is inactive. However, the full amount of advance payment is paid before logging resumes. Partial payment must be sufficient to maintain a payment deposit equal to one-half of a regular advance payment. The total purchase price shall be calculated after all log scale is reported by multiplying prices in Section 44 by the scaled volume. STATE shall refund any advance payment in excess of the total price, or PURCHASER shall pay any deficit within 30 days of notice. PURCHASER's deposit account shall not accrue interest payable to PURCHASER.

  • Salary Schedule The salaries of employees covered by this agreement are set forth in the salary schedule in Appendix A which is attached to and incorporated into this agreement.

  • Salary Schedules (a) The salary schedules shall be incorporated into this Agreement as Appendix V. (b) Salary schedules will contain Career Enhancement/Growth steps as described in Section 45.6.

  • Additional Fee on Late Payments For any payments thirty (30) calendar days or more overdue under this Agreement, Registry Operator shall pay an additional fee on late payments at the rate of 1.5% per month or, if less, the maximum rate permitted by applicable law.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!