Progress Reports and Mid-term Reviews Sample Clauses

Progress Reports and Mid-term Reviews. 1. The Borrower shall: (i) prepare and furnish to the Bank semi-annual progress reports, integrating the results of the implementation of the Project; (ii) review the reports jointly with the Bank; and (iii) thereafter take all measures required to ensure the efficient completion of the Project and the achievement of the objectives thereof, based on the conclusion and recommendations of the said reports and the Bank’s views on the matter.
AutoNDA by SimpleDocs

Related to Progress Reports and Mid-term Reviews

  • Progress Reports The Recipient shall submit to the OPWC, at the OPWC's request, summary reports detailing the progress of the Project pursuant to this Agreement and any additional reports containing such information as the OPWC may reasonably require.

  • Progress Reporting 5. The IP will submit to UNICEF narrative progress reports against the planned activities contained in the Programme Document, using the PDPR. Unless otherwise agreed between the Parties in writing, these reports will be submitted at the end of every Quarter. The final report will be submitted no later than thirty (30) calendar days after the end the Programme and will be provided together with the FACE form.

  • Progress Report 10.1 If required, you shall submit progress reports in connection with the Service (“Report”) on at least a monthly basis, or as we may require. The Report shall include a summary of the activities and accomplishments during the previous reporting period.

  • Progress Reports and Invoices The goals of this subtask are to: (1) periodically verify that satisfactory and continued progress is made towards achieving the project objectives of this Agreement; and (2) ensure that invoices contain all required information and are submitted in the appropriate format. The Recipient shall: • Submit a monthly Progress Report to the CAM. Each progress report must: o Summarize progress made on all Agreement activities as specified in the scope of work for the preceding month, including accomplishments, problems, milestones, products, schedule, fiscal status, and an assessment of the ability to complete the Agreement within the current budget and any anticipated cost overruns. See the Progress Report Format Attachment for the recommended specifications. • Submit a monthly or quarterly Invoice that follows the instructions in the “Payment of Funds” section of the terms and conditions, including a financial report on Match Fund and in-state expenditures. Products: • Progress Reports • Invoices

  • Monthly Progress Reports During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include:

  • Project Reports 1. The Borrower shall monitor and evaluate the progress of the Project and prepare Project Reports in accordance with the provisions of Section 5.08 of the General Conditions and on the basis of the indicators agreed with the Bank. Each Project Report shall cover the period of one calendar semester, and shall be furnished to the Bank not later than one month after the end of the period covered by such report.

  • Project Monitoring Reporting Evaluation 1. The Project Implementing Entity shall monitor and evaluate the progress of the Project and prepare Project Reports in accordance with the provisions of Section 4.08(b) of the General Conditions and on the basis of indicators agreed with the Association. Each such Project Report shall cover the period of one calendar semester, and shall be furnished to the Recipient not later than eight (8) weeks after the end of the period covered by such report for incorporation and forwarding by the Recipient to the Association of the overall Project Report.