Submission of Revised Programmes and Progress Reporting Sample Clauses

Submission of Revised Programmes and Progress Reporting. Once the programme has been accepted by the Project Manager, the Programme must be base- lined and a soft XER copy supplied with a hard copy to the Project Manager. This base-line will be used to monitor actual progress against the base line dates. For any changes/revisions to the original programme, the Project Manager along with Site supervisor and Discipline Manager must sign. These must be accompanied with both hard copy and soft XER copy. Any deviations must be reported within the reporting period so as to ensure there are no delays to the project. Progress updates will be done by the Contractor and given to the Employer so that these can be used to update the Employer’s programme. This is done by supplying actual progress and remaining duration with the actual start and finish dates.
AutoNDA by SimpleDocs
Submission of Revised Programmes and Progress Reporting. The Consultant submits one electronic copy in Primavera P6 (XER) or MS Project (MPP) format, of each revised programme and progress report to the Employer’s Agent for acceptance. The Consultant submits revised programme on monthly basis or as instructed by the Employer’s Agent. The monthly reports shall comply with the progress reporting requirements as stated below.

Related to Submission of Revised Programmes and Progress Reporting

  • Progress Reporting 5. The IP will submit to UNICEF narrative progress reports against the planned activities contained in the Programme Document, using the PDPR. Unless otherwise agreed between the Parties in writing, these reports will be submitted at the end of every Quarter. The final report will be submitted no later than thirty (30) calendar days after the end the Programme and will be provided together with the FACE form.

  • Progress Reports The Recipient shall submit to the OPWC, at the OPWC's request, summary reports detailing the progress of the Project pursuant to this Agreement and any additional reports containing such information as the OPWC may reasonably require.

  • Progress Report 10.1 If required, you shall submit progress reports in connection with the Service (“Report”) on at least a monthly basis, or as we may require. The Report shall include a summary of the activities and accomplishments during the previous reporting period.

  • Quarterly Progress Reports The goal of this task is to periodically verify that satisfactory and continued progress is made towards achieving the objectives of this Agreement on time and within budget. The objectives of this task are to summarize activities performed during the reporting period, to identify activities planned for the next reporting period, to identify issues that may affect performance and expenditures, and to form the basis for determining whether invoices are consistent with work performed. The Recipient shall: • Prepare a Quarterly Progress Report which summarizes all Agreement activities conducted by the Recipient for the reporting period, including an assessment of the ability to complete the Agreement within the current budget and any anticipated cost overruns. Progress reports are due to the CAM the 10th day of each January, April, July, and October. The Quarterly Progress Report template can be found on the ECAMS Resources webpage available at xxxxx://xxx.xxxxxx.xx.xxx/media/4691. Product: • Quarterly Progress Reports

  • Monthly Progress Reports During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.

  • AUDIT REPORT SUBMISSION Audit reports must be submitted no later than 150 days following cancellation, termination or expiration of this Agreement.

  • REPORT SUBMISSION 1. Copies of reporting packages for audits conducted in accordance with 2 CFR Part 200, Subpart F-Audit Requirements, and required by PART I of this form shall be submitted, when required by 2 CFR 200.512, by or on behalf of the recipient directly to the Federal Audit Clearinghouse (FAC) as provided in 2 CFR 200.36 and 200.512

  • SUBMISSION OF REPORTS All applicable study reports shall be submitted in preliminary form for approval by the State before a final report is issued. The State's comments on the Engineer's preliminary report must be addressed in the final report.

  • HUB Subcontracting Plan The Owner has adopted Exhibit H, Policy on Utilization of Historically Underutilized Business ("Policy"), which is incorporated herein by reference. Contractor, as a provision of the Agreement must comply with the requirements of the Policy and adhere to the HUB Subcontracting Plan submitted with Contractor's Proposal and attached as Exhibit I. No changes to the HUB Subcontracting Plan can be made by the Contractor without the prior written approval of the Owner in accordance with the Policy.

  • Monthly Progress Report This report shall include a description of the activities during the reporting period and the activities planned for the ensuing reporting period. The first reporting period consists of the first full month of performance plus any fractional part of the initial month. Thereafter, the reporting period shall consist of each calendar month. The Contractor shall submit a Monthly Progress Report on or before the 15th calendar day following the last day of each reporting period and shall include the following: Title Page: The title page for this report shall include the contract number and title; the type of report and period that it covers; the Contractor’s name, address, telephone number, fax number, and e-mail address; and the date of submission.