Test schedule Sample Clauses

Test schedule. 6.4.1. To evaluate the vehicle stability control function the tests used shall be agreed between the system/vehicle manufacturer and the Technical Service and shall include conditions, appropriate to the function being evaluated, that would without the intervention of the stability control function result in loss of directional control or roll-over. The dynamic manoeuvres, test conditions and results shall be included in the test report.
AutoNDA by SimpleDocs
Test schedule. The testing covered by this agreement begins when each of the three tests—Caterpillar C13, Cummins ISB, and Xxxx T-12—have been formally affirmed "ready for matrix testing" by the ASTM HDEOCP and all other conditions shown above under Scope have been met. The targeted completion date for each engine test for the ASTM PC-10 test matrix is ? months after its commencement date. The commencement date is the date that the first test begins. Extension of the timing past this targeted completion date must be approved by the PC-10 NCDT and DEOAP.
Test schedule. Seller shall submit its start-up and test schedule for the Project for PPUC's review at least sixty (60) Days prior to start up and testing to establish the Commercial Operation Date as contemplated by Section 4.3 and Schedule 2.
Test schedule. Within ___ days of the date of this Agreement; Consultant shall deliver to Client a test schedule designed to identify when such unit and integrated testing of the Technology shall occur in order to meet the time frames identified by the parties. ____________ guarantees that it shall make available to Client testing resources (including equipment and staff) necessary to perform the testing identified in the Schedule at the identified times.
Test schedule. Phase 1 – Establish starting conditions: Bring Project to 0% State of Charge.
Test schedule. The test procedure comprises a number of consecutive braking cycles each containing a number of X braking intervals of 5 seconds brake applied followed by 10 seconds brake released. No of cycle Number of brake application s X Initial brake rotor temperature (EC) Forced cooling 1 5 100 yes 2 5 increasing # 200 no 3 5 200 no 4 5 increasing # 300 no 5 5 300 no 6 3 250 yes 7 3 200 yes 8 3 150 yes 9 10 100 yes 10 5 increasing # 300 no 11 5 300 no

Related to Test schedule

  • Contract Schedule The information set forth in the Contract Schedule is true and correct.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Delivery Schedule The scheduled months of delivery of the Aircraft are listed in the attached Table 1. Exhibit B describes certain responsibilities for both Customer and Boeing in order to accomplish the delivery of the Aircraft.

  • Development Schedule The Project shall substantially comply with the specific timetables and triggers for action set forth in Article 5 of this Agreement. The parties acknowledge that, as provided in G.S. 160A-400.25(b), the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of this Agreement pursuant to G.S. 160A-400.27 but must be judged based upon the totality of the circumstances.

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Work Schedule A 4/10 work schedule is four (4) ten hour days in a seven (7) day period, for a total of forty (40) hours per week.

  • Punchlist Upon completion of the Performance Tests and prior to Substantial Completion of a Subproject, Owner and Contractor shall inspect the Subproject, and Contractor shall prepare a proposed Punchlist of items identified as needing to be completed or corrected as a result of such inspection. Contractor shall promptly provide the proposed Punchlist to Owner for its review, together with an estimate of the time and cost necessary to complete or correct each Punchlist item. Contractor shall add to the proposed Punchlist any Punchlist items that are identified by Owner within ten (10) Days after Owner’s receipt of the proposed Punchlist from Contractor, and Contractor shall immediately initiate measures to complete or correct, as appropriate, any item on Contractor’s proposed Punchlist (including those items identified by Owner during Owner’s review) that are not of a Punchlist nature. Notwithstanding anything to the contrary in this Agreement, Contractor and Owner are not required as a condition of Substantial Completion of a Subproject to agree upon and identify every Punchlist item and include it on the Punchlist, but Contractor is required to complete as a condition of Substantial Completion of such Subproject that does not meet the definition of Punchlist as provided in Section 1.1. In the event of a dispute regarding whether a specific item of Work meets the definition of Punchlist under Section 1.1, the Parties shall resolve such dispute in accordance with Section 18.1A. Owner shall provide Contractor with access to the Work after Substantial Completion of a Subproject sufficient to enable Contractor to complete all Punchlist items, so long as such access does not unreasonably interfere with operation of a Subproject after Substantial Completion of the Subproject or the Existing Facility and subject to any reasonable security or safety requirements of Owner. Upon Contractor’s completion or correction of any items necessary to achieve Substantial Completion of a Subproject, as modified by any Owner additions, such Punchlist shall govern Contractor’s performance of the Punchlist items up to Final Completion. All Work on the Punchlist shall be completed by the date required for Final Completion, as specified in Section 5.3C, or Owner may, in addition to any other rights that it may have under this Agreement, complete such Punchlist Work at the expense of Contractor. In the event Owner elects to complete such Punchlist Work, Contractor shall pay Owner, within ten (10) Days after receipt of written notice from Owner, all reasonable costs and expenses incurred by Owner in performing such Punchlist Work, or, at Owner’s sole discretion, Owner may withhold or offset amounts owed to Contractor or collect on the Letter of Credit in accordance with Section 7.8 in the amount of such costs and expenses. Any Defective Work identified after agreement between the Parties of the Punchlist shall be corrected by Contractor as a Warranty item under Article 12.

  • Rent Schedule Borrower has prepared a prospective Unit absorption and rent collection schedule with respect to the Project substantially in the form attached as an exhibit to the Construction Funding Agreement, which schedule takes into account, among other relevant factors (i) a schedule of minimum monthly rentals for the Units, and (ii) any and all concessions including free rent periods, and on the basis of such schedule, Borrower believes it will collect rents with respect to the Project in amounts greater than or equal to debt service on the Borrower Loan.

  • Statement of Work The Contractor shall provide the services and staff, and otherwise do all things necessary for or incidental to the performance of work, as set forth below:

  • Aircraft Description The Option Aircraft are described by Boeing Detail Specification D6-38808, Revision E, dated September 15, 1995, as amended and revised pursuant to the Agreement.

Time is Money Join Law Insider Premium to draft better contracts faster.