Examples of Draw Requisition in a sentence
The final Draw Requisition shall not be submitted before completion of the Project, including any correction of material defects in workmanship or materials (other than the completion of punch list items).
At the time of submission of each Draw Requisition, other than the final Draw Requisition, the Public Entity shall submit to MnDOT such supporting evidence as may be requested by MnDOT to substantiate all payments which are to be made out of the relevant Draw Requisition or to substantiate all payments then made with respect to the Project.
Each Draw Requisition with respect to construction items shall be limited to amounts equal to: (i) the total value of the classes of the work by percentage of completion as approved by the Public Entity and MnDOT, plus (ii) the value of materials and equipment not incorporated in the Project but delivered and suitably stored on or off the Real Property in a manner acceptable to MnDOT, less (iii) any applicable retainage, and less (iv) all prior Advances.
Each Draw Requisition shall be submitted on or between the 1st day and the 15th day of the month in which an Advance is requested, and shall be submitted at least 7 calendar days before the date the Advance is desired.
Whenever the Public Entity desires a disbursement of a portion of the LRIP Grant the Public Entity shall submit to MnDOT a Draw Requisition duly executed on behalf of the Public Entity or its designee.
At the time of submission of each Draw Requisition, other than the final Draw Requisition, the Public Entity shall submit to the State Entity such supporting evidence as may be requested by the State Entity to substantiate all payments which are to be made out of the relevant Draw Requisition or to substantiate all payments then made with respect to the Project.
If on the date an Advance is desired the Public Entity has complied with all requirements of this Agreement and the State Entity approves the relevant Draw Requisition and receives a current construction report from the Inspecting Engineer recommending payment, then the State Entity shall disburse the amount of the requested Advance to the Public Entity.
The State Entity shall have received a Draw Requisition for such Advance specifying the amount of funds being requested, which such amount when added to all prior requests for an Advance shall not exceed the maximum amount of the Grant set forth in Section 1.01.
Each Draw Requisition with respect to construction items shall be limited to amounts equal to: (i) the total value of the classes of the work by percentage of completion as approved by the Public Entity and the State Entity, plus (ii) the value of materials and equipment not incorporated in the Project but delivered and suitably stored on or off the Real Property in a manner acceptable to the State Entity, less (iii) any applicable retainage, and less (iv) all prior Advances.
If on the date an Advance is desired the Public Entity has complied with all requirements of this Agreement and MnDOT approves the relevant Draw Requisition, then MnDOT shall disburse the amount of the requested Advance to the Public Entity.