Examples of Performance Time in a sentence
Consultant agrees that if the Services are not completed within the aforementioned Performance Time and/or pursuant to any such Project Milestones developed pursuant to provisions of this Agreement, it is understood, acknowledged and agreed that the City will suffer damage.
Consultant agrees that if the Services are not completed within the aforementioned Performance Time and/or pursuant to any such Performance Milestones developed pursuant to provisions of this Agreement, it is understood, acknowledged and agreed that the City will suffer damage.
Contractor agrees that if the Services are not completed within the aforementioned Performance Time and/or pursuant to any such completion schedule or Project milestones developed pursuant to provisions of this Agreement, it is understood, acknowledged and agreed that the City will suffer damage.
Contractor agrees that if the Services specified in Exhibit “D”, attached hereto and incorporated herein by this reference, are not completed within the aforementioned Performance Time and/or pursuant to any such completion schedule or Project milestones developed pursuant to provisions of this Agreement, it is understood, acknowledged and agreed that the City will suffer damage.
Pursuant to Government Code Section 53069.85, Contractor shall pay to the City as fixed and liquidated damages, and not as a penalty, the sum of [***INSERT WRITTEN DOLLAR AMOUNT***] Dollars ($[***INSERT NUMERICAL DOLLAR AMOUNT***]) per day for each and every calendar day of delay beyond the Performance Time or beyond any completion schedule or Project milestones established pursuant to this Agreement.
Pursuant to Government Code Section 53069.85, Contractor shall pay to the City as fixed and liquidated damages, and not as a penalty, the sum of One Hundred Dollars ($100.00) per day for each and every calendar day of delay beyond the Performance Time or beyond any completion schedule or Project milestones established pursuant to this Agreement.
Pursuant to Government Code Section 53069.85, Consultant shall pay to the City as fixed and liquidated damages the sum of [***INSERT WRITTEN DOLLAR AMOUNT***] Dollars ($[***INSERT NUMERICAL DOLLAR AMOUNT***]) per day for each and every calendar day of delay beyond the Performance Time or beyond any Project Milestones established pursuant to this Agreement.
Pursuant to Government Code Section 53069.85, Contractor shall pay to the City as fixed and liquidated damages the sum of two hundred dollars ($200.00) per day for each and every calendar day of delay beyond the Performance Time or beyond any Project Milestones established pursuant to this Agreement.
Contractor agrees that if the Services are not completed within the aforementioned Performance Time and/or pursuant to any such Project Milestones developed pursuant to provisions of this Agreement, it is understood, acknowledged and agreed that the City will suffer damage.
Contractor agrees that if the Services are not completed within the aforementioned Performance Time and/or pursuant to any such completion schedule or Project milestones developed pursuant to provisions of this Agreement, it is understood, acknowledged and agreed that the District will suffer damage.