Examples of Project Improvements Construction Schedule in a sentence
Any changes, modifications or amendments to the Project Submission Matters are subject to the Approval of the Authority, with the understanding that it is the intent of the Parties that the Project Improvements be constructed in accordance with the Project Improvements Construction Schedule and within the Project Budget.
Only one (1) Notice from StadCo shall be required with respect to a continuing Force Majeure, except StadCo shall promptly (and in no event less often than every month) give Notice to the Authority Representative of any further changes in the Project Improvements Construction Schedule or the additional time for performance claimed by reason of the continuing delay.
The Project Improvements Construction Schedule shall be provided to the Authority on an advisory basis, and the Authority acknowledges that the dates set forth on the Project Improvements Construction Schedule (other than the Project Completion Date) shall be subject to modifications in StadCo’s discretion and any failure by StadCo to meet target dates (other than the Project Completion Date) shall not in and of itself constitute a StadCo Default.
Without limiting StadCo’s obligations under Section 7.9, Section 7.10 or elsewhere in this Agreement, StadCo shall, prior to the commencement of construction of the Project Improvements (excluding the Enabling Work), provide the Authority with a Project Improvements Construction Schedule.
The Parties shall agree upon a Project Improvements Construction Schedule in connection with the approval of the Final Plans.
Without limiting StadCo’s obligations under Section 7.9, Section 7.10 or elsewhere in this Agreement, StadCo shall, prior to the commencement of construction of the Project Improvements [(excluding the Enabling Work)], provide the Authority with a Project Improvements Construction Schedule.
Electricity has been transported by Extra High Tension (EHT)14 cables from the west to the east.
Any changes, modifications, or amendments to the Project Submission Matters are subject to the Approval of the Authority, with the understanding that it is the intent of the Parties that the Project Improvements be constructed in accordance with the Project Improvements Construction Schedule and within the Project Cash Budget.
Without limiting StadCo’s obligations under Sections 7.8 and 7.9 or elsewhere in this Agreement, StadCo shall, prior to the commencement of construction of the Project Improvements (excluding the Enabling Work), provide the Authority with a Project Improvements Construction Schedule.
The Developer shall deliver to the Owner Representative an updated version of the Hotel Project Improvements Construction Schedule no less frequently than once every thirty (30) calendar days.