Schedule Milestone definition

Schedule Milestone an event to be achieved by Contractor for payment of a Schedule Bonus pursuant to and in accordance with Article 7, as described on Appendix 2 of Exhibit D.
Schedule Milestone means a milestone date or timeframe identified in a Submittal. “Shutdown” means turning off, or interrupting, a Customer’s water supply other than for a Test Shutdown.
Schedule Milestone means an event or series of events in the execution of the Work as set forth in Exhibit B, which shall include Key Contractor Schedule Milestones and Key Owner Schedule Milestones.

Examples of Schedule Milestone in a sentence

  • If an extension or contraction of any Milestone or Completion Date is authorized by any Change Order, the Contractor shall revise his Construction Schedule, Milestone and Completion Dates accordingly.

  • Contractor shall post all Primavera files and data associated with the Project Schedule and any revisions thereto to the Princeton University PCS site.CLAUSE E3 PROGRESS AND COMPLETION(a) Time is of the essence for all provisions of the Contract.(b) Contractor shall achieve Schedule Milestone dates and the Substantial Completion Date in accordance with the (Updated) Project Schedule.

  • The Project Schedule shall be of sufficient detail to identify (i) a clear critical path of the overall Project Work; (ii) critical path through each of the Schedule Milestone elements; and (iii) major sub-critical paths, from the data date to the end of the Project.

  • Contractor shall submit a Cost and Schedule Milestone Plan (CDRL A007) for government review and approval 10 days after contract award.

  • In support of the contract’s Quality Assurance Surveillance Plan (QASP) and Contractor Performance Assessment Reporting System (CPARS), the contractor shall provide the following documents: Cost and Schedule Milestone Plan (CDRL A014) and Contractor CPARS Draft Approval Document (CDAD) Report (CDRL A015).

  • In support of the TO’s Quality Assurance Surveillance Plan (QASP) and Contractor Performance Assessment Reporting System (CPARS), the contractor shall provide the following documents: Cost and Schedule Milestone Plan for each task described in this PWS (CDRL A015)) submitted 30 days after Task Order award, and Contractor CPARS Draft Approval Document (CDAD) Report (CDRL A016) submitted monthly.

  • Listed below are the definitions and acceptance criteria for each Schedule Milestone (SM), Annual Milestone (AM) and Performance Incentive (PI).

  • Fee Calculation:The Schedule Milestone Fee dollars from the Maximum Fee amount (i.e. max fee date achievement through the min fee date) to the Min Fee amount will be calculated on a sliding scale per calendar day basis.

  • This will include traffic and revenue studies, revenue generation technology plan, preliminary design and engineering plans, and structure(s), operation and maintenance Reports with exhibits/ Schedule Milestone Deliverable Name Reference to Exhibits D, E, F, G and (Tasks) Summary Description Submittal Format DeliveryDate/ Deadline* management plans, specific warranties and guarantees, specific risk management, mitigation and allocation plans, system supply plans, anticipated 3rd party agreements.

  • Fee Calculation:The Schedule Milestone Fee dollars from the Maximum Fee amount (i.e. max fee date achievement through the target fee date) to the Target Fee amount will be calculated on a sliding scale per calendar day basis.

Related to Schedule Milestone

  • Milestone means an event or task described in the Implementation Plan which must be completed by the corresponding date set out in such plan;

  • Milestones means control points in the project that help to chart progress. Milestones may correspond to the completion of a key deliverable, allowing the next phase of the work to begin. They may also be needed at intermediary points so that, if problems have arisen, corrective measures can be taken. A milestone may be a critical decision point in the project where, for example, the consortium must decide which of several technologies to adopt for further development.

  • Progress Schedule means a schedule of the Work, in a form satisfactory to Owner, as further set forth in Section 3.02.

  • Project Schedule means a document that, with respect to each Phase of the Project, identifies, coordinates and integrates the anticipated design and construction schedules, the Contracting Authority’s and Owner's responsibilities, government authority reviews and other activities as are necessary for the timely completion of the Work.