Examples of Scheduled Turnaround in a sentence
In the event such actual Aggregate Major Turnaround Cost is less than 80% of the Accrued Major Turnaround Cost for such Scheduled Turnaround, then Owner will pay to Customer a turnaround reimbursement equal to the amount by which such actual Aggregate Major Turnaround Cost is less than 80% of the Accrued Major Turnaround Cost (the “Major Turnaround Reimbursement”) in order to allow Customer to recover a portion of the Accrued Major Turnaround Cost in excess of the actual Aggregate Major Turnaround Cost.
The Tolling Fee shall be increased for the 18-Month period immediately preceding and including the month of the commencement of such Scheduled Turnaround to include the Turnaround Fee shown on such Turnaround Budget to be assessed on each Barrel of Feedstock (using the Minimum Contract Quantity) in order to allow Owner to earn the Accrued Turnaround Cost.
Owner anticipates the next Scheduled Turnaround will commence on or around January 19, 2019 and, because such Scheduled Turnaround will occur less than 18 Months from the Effective Date, the Tolling Fees assessed beginning on the Effective Date shall include the Turnaround Fee set forth on the Turnaround Budget provided to Customer contemporaneous with execution of this Agreement.
Not less than 18 Months prior to the commencement of each Scheduled Turnaround during the Term, Owner shall provide written notice of such Scheduled Turnaround to Customer, which written notice shall include a Turnaround Budget in accordance with Section 6.3 of this Agreement.
In the event such actual Aggregate Major Turnaround Cost is greater than 120% of the Accrued Major Turnaround Cost for such Scheduled Turnaround, then Customer will pay to Owner a turnaround surcharge equal to the amount by which such actual Aggregate Major Turnaround Cost is greater than 120% of the Accrued Major Turnaround Cost (the “Major Turnaround Surcharge”) in order to allow Owner to recover a portion of the actual Aggregate Major Turnaround Cost in excess of the Accrued Major Turnaround Cost.
In the event such actual Aggregate Minor Turnaround Cost is less than 80% of the Accrued Minor Turnaround Cost for such Scheduled Turnaround, then Owner will pay to Customer a turnaround reimbursement equal to the amount by which such actual Aggregate Minor Turnaround Cost is less than 80% of the Accrued Minor Turnaround Cost (the “Minor Turnaround Reimbursement”) in order to allow Customer to recover a portion of the Accrued Minor Turnaround Cost in excess of the actual Aggregate Minor Turnaround Cost.
During the first Scheduled Turnaround that occurs after eighteen months following completion of the Initial PRV Leak Survey of any unit that houses any PRV listed in Appendix C - 2.2, Settling Defendants shall repair or replace each leaking PRV in that unit.
After each Scheduled Turnaround on the Facilities during the Term, Owner will calculate its actual Aggregate Major Turnaround Cost incurred in connection therewith.
Unless in violation of applicable Law, the Sellers shall provide the Buyer with periodic, detailed updates on the status of the consummation of the Xxxxxx Xxxxx Company Contract Renewal (including participation in reasonably requested meetings with Buyer copies of draft and final agreements unless precluded by a confidentiality agreement with a Third Party) and the undertaking of the Scheduled Turnaround and the Special Projects.