CONTRACTOR’S CONSTRUCTION SCHEDULE. The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner’s and Architect’s information a Contractor’s construction schedule for the Work.
CONTRACTOR’S CONSTRUCTION SCHEDULE. 2.1 Contractor’s Construction Schedule
CONTRACTOR’S CONSTRUCTION SCHEDULE. The Contractor, promptly after being awarded the contract, shall prepare and submit for the Owner’s and Engineer’s information a Contractor’s construction schedule for the Work
CONTRACTOR’S CONSTRUCTION SCHEDULE. A. Contractor's Construction Schedule Updating: At weekly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
3. As the Work progresses, indicate Actual Completion percentage for each activity.
CONTRACTOR’S CONSTRUCTION SCHEDULE. The CM shall provide a copy of the Master Schedule to the bidders. THE CM SHALL PREPARE A CONSTRUCTION SCHEDULE AND ALL UPDATES IN ACCORDANCE WITH THE OWNER’S SCHEDULING REQUIREMENTS. THE OWNER SHALL PROVIDE THE CM WITH ITS SCHEDULING REQUIREMENTS PRIOR TO RECEIPT OF BIDS FOR THE PROJECT. As part of the Notice of Award, the CM shall inform each Contractor of the requirements for the preparation of a construction schedule. The Contractor shall prepare its own
CONTRACTOR’S CONSTRUCTION SCHEDULE. 4.10.1 Within ten (10) calendar days after receipt of Notice to Proceed, the Contractor shall submit a Construction Schedule in CPM (Critical Path Method) form to the Project Manager for approval. The Construction Schedule shall be sufficiently detailed to accurately depict all the work required by the contract and include all features per paragraph 4.12 of Section 00 72 00 – General Conditions of the Contract for Construction. CPM Construction Schedule shall reflect shop drawings; submittals due and return dates, fabrication and delivery times, crew mix, and equipment loading data. The Contractor shall thereafter adhere to the Project Construction Schedule, as regularly updated, including any revisions therein made by the County during the course of construction. "Slack" or "float" time on the CPM Construction Schedule is not for the sole benefit of the County or Contractor and shall be apportioned according to the needs of the project and as accepted by the County.
4.10.2 Within ten (10) calendar days after the Notice to Proceed, the Contractor shall provide a Submittal and Procurement Schedule indicating time periods for review of Shop Drawings, Data, Samples, and procurement of material and equipment required for the Work, per paragraph 4.12 of Section 00 72 00 – General Conditions of the Contract for Construction . All items that require approval by the Project Manager and/or are not readily available from stock and requiring more than 35 days’ lead time shall be included in the Submittal and Procurement Schedule. Items listed in the Submittal and Procurement Schedule shall also be identified as activities on the CPM Construction Schedule.
4.10.3 The working day to calendar date correlation shall be based upon the Contractor's proposed work week with adequate allowance for legal holidays, days lost due to weather, and any special requirements of the project.
4.10.4 The Construction Schedule and Submittal and Procurement Schedule shall be prepared and maintained by the Contractor.
4.10.5 The County, Project Manager, Contractor and other Contractor(s) shall jointly review the progress of the work weekly. Should this review, in the opinion of the Project Manager, indicate that the work is behind the schedule established by currently approved Construction Schedule, the Contractor shall either 1) provide a plan to the Project Manager indicating the steps the Contractor intends to take in order to recover the time behind schedule and conform to the approved...
CONTRACTOR’S CONSTRUCTION SCHEDULE. The CM shall ADJUST AND UPDATE THE review each Contractor’s Construction Schedule and shall verify that the schedule is prepared in accordance with the requirements of the Contract Documents OWNER NOTED IN PARAGRAPH 3.4.2.2 and that it establishes completion dates that comply with the requirements of the Master Schedule. THE CM AGREES THAT THE CONSTRUCTION SCHEDULE IS FOR THE BENEFIT OF THE ENTIRE PROJECT TEAM AND BY EXECUTION OF THIS AGREEMENT GIVES PERMISSION AND DIRECTION TO ITS SCHEDULING CONSULTANT TO PROVIDE COPIES OF THE SCHEDULE IN A FORMAT AS REQUIRED BY THE OWNER.
CONTRACTOR’S CONSTRUCTION SCHEDULE. A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and ac- tivity durations.
3. As the Work progresses, indicate Actual Completion percentage for each activity.
B. Distribution: Distribute copies of approved schedule to Architect, Owner, separate con- tractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1. Post copies in Project meeting rooms and temporary field offices.
2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have com- pleted their assigned portion of the Work and are no longer involved in perfor- xxxxx of construction activities.
CONTRACTOR’S CONSTRUCTION SCHEDULE. Contractor shall provide Owner and Project Manager with a progress and completion schedule within seven (7) calendar days following the execution of this Agreement. In the event of any unforeseen changes or delays in Contractor’s schedule, Contractor shall promptly provide an updated schedule to Owner and Project Manager for review and approval.
CONTRACTOR’S CONSTRUCTION SCHEDULE. A. Procedures: Comply with procedures required by the Owner.
B. Time Frame: Extend schedule from date established for commencement of the Work or the Notice to proceed to date of Final Completion.
1. Contractor shall indicate specific dates which may require the Designer’s attention to proceed on a critical path.