Construction Order Sample Clauses

Construction Order. An order authorizing the CMR to proceed to construct a Component pursuant to the Component Construction Documents. A Construction Order may often be called a “Construction Component Change Order,” “Component Change Order,” or “CCO” within the industry. A Construction Order does not necessarily change the overall amount of a contract, but it may.
AutoNDA by SimpleDocs
Construction Order. (a) In the case of the initial Construction Order, payment and performance bonds furnished by the CMR in conformance with and in the form set forth in the Contract Documents designating the CMR as the principal obligor and the Owner as the obligee, in an amount of the Change Order Sum covering the Work under that Construction Order and, in the case of subsequent Construction Orders, an endorsement to such bonds increasing the aggregate amount of the bonds to an amount equal to the aggregate of the Change Order Sums of all Construction Orders to this Contract. If in connection with a Construction Order, the CMR has furnished payment and performance bonds in the amount approved by the Board as the reasonably expected aggregate amount of the Change Order Sums of that and any prior Construction Order and all subsequent Construction Orders and covering all such Work, then upon entry of a subsequent Construction Order, no additional endorsement to payment or performance bonds shall be required provided that the aggregate amount of the Change Order Sums of all Construction Orders does not exceed the penal sum of each bond. However, the Board may require written confirmation from the surety that the outstanding bonds cover the Work under a subsequent Construction Order. No election or failure of the Board to request such confirmation shall affect the rights of the board or there under the existing bonds covering such Work.

Related to Construction Order

  • Change Order (5) The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.

  • Drawings and Specifications at the Project Site The Contractor shall keep at the Site at least one copy of the Contract Documents and Change Orders, all in good order and available to the Design Professional and to his representatives.

  • Completion of Concrete Pours and Emergency Work 24.14.1 Except as provided in this sub-clause an employee shall not work or be required to work in the rain.

  • Change Orders and Contract Amendments 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:

  • Construction Safety Prior to contract award, the successful bidder must provide a Certificate of Recognition or Letter of Good Standing issued by an occupational health and safety organization approved by the Workers’ Compensation Board of Nova Scotia.

  • Interconnection Facilities Engineering Procurement and Construction Interconnection Facilities, Network Upgrades, and Distribution Upgrades shall be studied, designed, and constructed pursuant to Good Utility Practice. Such studies, design and construction shall be based on the assumed accuracy and completeness of all technical information received by the Participating TO and the CAISO from the Interconnection Customer associated with interconnecting the Large Generating Facility.

  • Drawings and Specifications 9.1 A complete list of all Drawings that form a part of the Contract Documents are to be found as an index on the Drawings themselves, and/or may be provided to Developer and/or in the Table of Contents.

  • Execution of Change Orders Change Orders shall be signed by the Contractor, ordinarily certified by the Design Professional, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner. No request for payment by the Contractor for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the Owner. In the event of emergency (see Article 1.4.4) or significant impact to the Overall Project Schedule, the Owner shall direct the Change Order to proceed upon a Force Account until the cost and time is resolved in the manner set forth in Paragraph 3.2.7.3 below.

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Construction Completion The related Construction shall have been completed substantially in accordance with the related Plans and Specifications, the related Deed and all Applicable Laws, and such Leased Property shall be ready for occupancy and operation. All fixtures, equipment and other property contemplated under the Plans and Specifications to be incorporated into or installed in such Leased Property shall have been substantially incorporated or installed, free and clear of all Liens except for Permitted Liens.

Time is Money Join Law Insider Premium to draft better contracts faster.