Construction Phase Services Provided after the Original Construction Completion Date. 8.3.1 If construction of the Work, or of a project construction phase and/or separate bidding package has not reached substantial completion within the original construction period (as set forth in the Owner-Contractor or Owner-CM at Risk Agreement and as agreed to by the Designer), there shall be added to said construction period a period of sixty (60) calendar days, during which period the Designer shall continue to provide construction phase services for which no extra compensation shall be paid for the services described in Article 7.9 and 7.10.1 through 7.10.4 in a CM at Risk Project or for the services described in Articles 7.8 and 7.9.1 through 7.9.4 in a DBB Project.
8.3.2 If construction has not reached Substantial Completion after the 60 additional calendar days, the Designer shall thereafter be entitled to Extra Services compensation for providing the services described in Articles 7.10.3 (which are fully defined under Article 7.9.2) and 7.10.4 in a CM at Risk Project or for the services described in Articles 7.9.3 (which are fully defined under Article 7.8.2) and 7.9.4
Construction Phase Services Provided after the Original Construction Completion Date. 6.3.1 If construction has not reached substantial completion within the original construction period (as set forth in the Owner Contractor Agreement), there shall be added to said construction period a period of 60 calendar days, during which period the Designer shall continue to provide construction phase services for which no extra compensation shall be paid.
6.3.2 If construction has not reached substantial completion after the 60 additional calendar days, the Designer shall thereafter be entitled to additional compensation for attending job meetings, and preparing and distributing job meeting minutes until construction is completed. Other construction phase services during this period shall be considered basic services, for which the Designer shall not be entitled to extra compensation, except for services that are extra services described in paragraph 6.2. In no event shall the Designer, be entitled to any additional compensation on account of an extended construction period, if the Authority and the Department have determined that the Designer's acts or inactions have caused the construction period to be extended.
Construction Phase Services Provided after the Original Construction Completion Date. 6.3.1 If construction has not reached substantial completion within the original construction period (as set forth in the Owner-Contractor Agreement), there shall be added to said construction period a period of 60 calendar days, during which period the Designer shall continue to provide construction phase services for which no extra compensation shall be paid.
6.3.2 If construction has not reached substantial completion after the 60 additional calendar days, the Designer shall thereafter be entitled to additional compensation only for attending job meetings, and preparing and distributing job meeting minutes until construction is completed. In no event shall the Designer be entitled to any additional compensation on account of an extended construction period, if the Authority and the Department have determined that the Designer's acts or inactions have caused the construction period to be extended.
Construction Phase Services Provided after the Original Construction Completion Date. 8.3.1 If construction of the Work, or of a project construction phase and/or separate bidding package has not reached substantial completion within the original construction period (as set forth in the Owner-Contractor and as agreed to by the Designer), there shall be added to said construction period a period of sixty (60) calendar days, during which period the Designer shall continue to provide Construction Administration Phase services for which no extra compensation shall be paid for the services described in Articles 7.8 and 7.9.1 through 7.9.4.
8.3.2 If construction has not reached Substantial Completion after the 60 additional calendar days, the Designer shall thereafter be entitled to Extra Services compensation for providing the services described in Articles 8.2.10 (which are fully defined under Article 7.9) or for the services described in Articles 7.9.3 and 7.9.
Construction Phase Services Provided after the Original Construction Completion Date. If construction of the Work, or of a project construction phase and/or separate bidding package has not reached substantial completion within the original construction period (as set forth in the Owner-Contractor or Owner-CM at Risk Agreement and as agreed to by the Designer), there shall be added to said construction period a period of sixty (60) calendar days, during which period the Designer shall continue to provide construction phase services for which no extra compensation shall be paid for the services described in Article 7.9 and 7.10.1 through 7.10.4 in a CM at Risk Project or for the services described in Articles 7.8 and 7.9.1 through 7.9.4
Construction Phase Services Provided after the Original Construction Completion Date. (a) If construction of the Work, or of a project construction phase and/or separate bidding package has not reached substantial completion within the original construction period (as set forth in the Owner-Contractor or Owner-CM at Risk Agreement and as agreed to by the A/E), there shall be added to said construction period a period of 30 calendar days, during which period the A/E shall continue to provide construction phase services for which no additional compensation shall be paid for the services described in Article 7.
(b) If construction has not reached Substantial Completion after the 30 additional calendar days, the A/E shall thereafter be entitled to Additional Services compensation for providing the services described in Article 7.29. The A/E is required to identify and present the anticipated Additional Services in accordance with Articles 8.1, 8.2, and 8.3.
(c) In no event shall the A/E be entitled to any additional compensation on account of an extended construction period if and to the extent that a binding agreement or decision that results from a dispute resolution proceeding determines that the A/E’s acts or inactions caused the construction period to be extended.