Extensions of Time for Abnormal Weather Delay Days Sample Clauses

Extensions of Time for Abnormal Weather Delay Days. The CM/GC shall be entitled to a contract extension due to Weather Delay Days whenever the number of Weather Delay Days incurred in a month is greater than the total number of Anticipated Weather Delay Days for that month.
AutoNDA by SimpleDocs
Extensions of Time for Abnormal Weather Delay Days. The Design-Builder shall be entitled to a contract extension due to weather delay days whenever the number of weather delay days incurred is greater than the total number of anticipated weather delay days for the project, The Design Professional shall determine if each subsequent weather delay day impacts the critical path.

Related to Extensions of Time for Abnormal Weather Delay Days

  • Extensions of Time 34.1 If at any time during performance of the Contract, the Supplier or its subcontractors should encounter conditions impeding timely delivery of the Goods or completion of Related Services pursuant to GCC Clause 13, the Supplier shall promptly notify the Procuring Entity in writing of the delay, its likely duration, and its cause. As soon as practicable after receipt of the Supplier's notice, the Procuring Entity shall evaluate the situation and may at its discretion extend the Supplier's time for performance, in which case the extension shall be ratified by the parties by amendment of the Contract.

  • Extension of Time Limits The time limits referred to in this Article may be extended by mutual agreement of the parties in writing.