Final Payment Certificate Sample Clauses

Final Payment Certificate. 19.15.1 Within 30 (thirty) days after receipt of the Final Payment Statement for Works under Clause 19.13, and the written discharge under Clause 19.14, and there being no disputed items of claim, the Authority’s Engineer shall deliver to the Authority, with a copy to the Contractor, a final payment certificate (the “Final Payment Certificate”) stating the amount which, in the opinion of the Authority’s Engineer, is finally due under this Agreement or otherwise. For the avoidance of doubt, before issuing the Final Payment Certificate, the Authority’s Engineer shall ascertain from the Authority all amounts previously paid by the Authority and for all sums to which the Authority is entitled, the balance, if any, due from the Authority to the Contractor or from the Contractor to the Authority, as the case may be. 19.15.2 The Authority shall, in accordance with the provisions of Clause 19.9, pay to the Contractor the amount which is stated as being finally due in the Final Payment Certificate.
AutoNDA by SimpleDocs
Final Payment Certificate. 1Within 30 (thirty) days after receipt of the Final Payment Statement under Clause 17.10, and the written discharge under Clause 17.11, and there being no disputed items of claim, the Authority Engineer shall deliver to the Authority, with a copy to the Contractor, a final payment certificate (the “Final Payment Certificate”) stating the amount which, in the opinion of the Authority Engineer, is finally due under this Agreement or otherwise. For the avoidance of doubt, before issuing the Final Payment Certificate, the Authority Engineer shall ascertain from the Authority all amounts previously paid by the Authority, all sums due to the Authority, and the balance, if any, due from the Authority to the Contractor or from the Contractor to the Authority, as the case may be.
Final Payment Certificate. Prior to the compilation of the final payment certificate the engineer shall ensure that all items on the Client’s checklist are complied with. The signed off checklist shall be submitted with the final payment certificate. The engineer shall only compile and submit the final payment certificate once the Final Approval Certificate has been issued by the Client and all unfulfilled financial obligations have been resolved.
Final Payment Certificate. 17.12.1 Within 30 (thirty) days after receipt of the Final Payment Statement under Clause 17.10, and the written discharge under Clause 17.11, and there being no disputed itemsof claim, the Authority Engineer shall deliver to the Authority, with a copy to the Contractor,a final payment certificate (the “Final Payment Certificate”) stating the amount which, in the opinion of the Authority Engineer, is finally due under this Agreement or otherwise. For the avoidance of doubt, before issuing the Final Payment Certificate, the Authority Engineer shall ascertain from the Authority all amounts previously paid by the Authority, all sums due to the Authority, and the balance, if any, due from the Authority to the Contractor or from the Contractor to the Authority, as the case may be. 17.12.2 The Authority shall, in accordance with the provisions of Clause 17.7, pay to the Contractor the amount which is specified as being finally due in the Final PaymentCertificate.
Final Payment Certificate. 19.15.1 Within 30 (thirty) days after receipt of the Final Payment Statement for Works under Clause 19.13, and the written discharge under Clause 19.14, and there being no disputed items of claim, the Employer’s Engineer shall deliver to the Employer, with a copy to the Contractor, a final payment certificate (the “Final Payment Certificate”) stating the amount which, in the opinion of the Employer’s Engineer, is finally due under this Agreement or otherwise. For the avoidance of doubt, before issuing the Final Payment Certificate, the Employer’s Engineer shall ascertain from the Employer all amounts previously paid by the Employer and for all sums to which the Employer is entitled, the balance, if any, due from the Employer to the Contractor or from the Contractor to the Employer, as the case may be. 19.15.2 The Employer shall, in accordance with the provisions of Clause 19.9, pay to the Contractor the amount which is stated as being finally due in the Final Payment Certificate.
Final Payment Certificate. Final Payment Certificate" means the payment certificate issued under Sub-Clause 15.10
Final Payment Certificate. Within 30 (thirty) days after receipt of the Final Payment Statement for Works under Clause 10.4, and the written discharge under Clause 10.5, and there being no disputed items of claim, the DTA shall deliver to the Authority, with a copy to the Contractor, a final payment certificate (the “Final Payment Certificate”) stating the amount which, in the opinion of the DTA, is finally due under this Agreement or otherwise. For the avoidance of doubt, before issuing the Final Payment Certificate, the DTA shall ascertain from the Authority all amounts previously paid by the Authority and for all sums to which the Authority is entitled, the balance, if any, due from the Authority to the Contractor or from the Contractor to the Authority, as the case may be.
AutoNDA by SimpleDocs
Final Payment Certificate. Not later than 56 days after the issue of the Performance Certificate, the Contractor shall submit to the Engineer three copies of a draft final statement with supporting documents showing in detail, in a form approved by the Engineer:
Final Payment Certificate. 14.7.1 Within 30 (thirty) days after receipt of the Final Payment Statement for Works, and the written discharge, and there being no disputed items of claim, the EIC/PMC shall deliver to the RSCL, with a copy to the Contractor, a final payment certificate (the “Final Payment Certificate”) stating the amount which, in the opinion of the EIC/PMC, is finally due under this Agreement or otherwise. For the avoidance of doubt, before issuing the Final Payment Certificate, the EIC/PMC shall ascertain from the RSCL all amounts previously paid by the RSCL and for all sums to which the RSCL is entitled, the balance, if any, due from the RSCL to the Contractor or from the Contractor to the RSCL, as the case may be. 14.7.2 Pre Requisites for Payment of Final Bill 1) Contractor should Remove the temporary structures, labor camps, & dispose surplus materials, debris etc lying at work site within 30 days from handing of the work. 2) Contractor should submit No Dues Certificate from revenue authorities related to payment against Royalty for Miscellaneous materials. 14.7.3 The RSCL shall, pay to the Contractor the amount which is stated as being finally due in the Final Payment Certificate and in that event no further amount shall ever become due and payable to the contractor in respect of this contract save and except as indicated in the final payment certificate.
Final Payment Certificate. Within 30 (thirty) days after receipt of the Final Payment Statement for Works under Clause 19.13, and the written discharge under Clause 19.14, and there being no disputed items of claim, the Authority’s Engineer shall deliver to the Authority, with a copy to the Contractor, a final payment certificate (the “Final Payment Certificate”) stating the amount which, in the opinion of the Authority’s Engineer, is finally due under this Agreement or otherwise. For the avoidance of doubt, before issuing the Final Payment Certificate, the Authority’s Engineer shall ascertain from the Authority all amounts previously paid by the Authority and for all sums to which the Authority is entitled, the balance, if any, due from the Authority to the Contractor or from the Contractor to the Authority, as the case may be.