Ninety Day Schedule Sample Clauses

The Ninety Day Schedule clause establishes a requirement for parties to submit or adhere to a detailed project schedule covering the upcoming ninety days. Typically, this schedule outlines key tasks, deadlines, and milestones that must be met within that period, and may require regular updates or approvals as the project progresses. By mandating a rolling ninety-day plan, the clause ensures ongoing project management, facilitates coordination among stakeholders, and helps prevent delays by maintaining clear short-term objectives.
POPULAR SAMPLE Copied 6 times
Ninety Day Schedule. 8.4.1 No later than the twenty-fifth (25th) Day of each Month, Seller shall issue a forward plan of deliveries for the three (3)-Month period commencing on the first (1st) Day of the following Month thereafter (e.g., the Ninety Day Schedule for the three (3)-Month period commencing on May 1st shall be issued no later than the twenty-fifth (25th) Day of April) (such plan, as amended from time to time in accordance with procedures set forth in this Agreement, the “Ninety Day Schedule”). The Ninety Day Schedule shall set forth by cargo the forecast pattern of deliveries, including the Delivery Window, LNG Tanker and Scheduled Cargo Quantity for each cargo. In the absence of agreement between the Parties otherwise, the Ninety Day Schedule will maintain the Scheduled Cargo Quantities and Delivery Windows as identified in the ADP. 8.4.2 Seller shall combine the Ninety Day Schedule with the ninety day schedules of all other Driftwood LNG Terminal buyers and provide to Buyer a combined schedule (the “Composite Ninety Day Schedule”) showing all delivery windows and scheduled cargo quantities that have been committed by Seller, along with available, uncommitted loading windows at the Driftwood LNG Terminal. Seller shall promptly update the Composite Ninety Day Schedule as the Ninety Day Schedule is changed pursuant to Section 8.3 or 8.4.1 or other Driftwood LNG Terminal buyers’ ninety day schedules are changed pursuant to their respective LNG sale and purchase agreements.
Ninety Day Schedule. No later than the twenty-fifth (25th) Day of each Month, Seller shall issue a forward plan of deliveries for the three (3)-Month period commencing on the first Day of the following Month thereafter (e.g., the Ninety Day Schedule for the three (3)-Month period commencing on May 1st shall be issued no later than the twenty-fifth (25th) Day of April) (such plan, as amended from time to time in accordance with procedures set forth in this Agreement, the “Ninety Day Schedule”). The Ninety Day Schedule shall set forth by cargo the forecast pattern of deliveries, including the Delivery Window, LNG Tanker and Scheduled Cargo Quantity for each cargo. In the absence of agreement between the Parties otherwise, the Ninety Day Schedule will maintain the Scheduled Cargo Quantities and Delivery Windows as identified in the Annual Delivery Program.
Ninety Day Schedule. (a) Each month, beginning with the first month following the Reactivation Date, if Seller delivers to Buyer, no later than the fifth (5th) calendar day of the applicable month, a proposed schedule for the three-month period beginning on the first day of the next calendar month (and any changes to the Annual Program beyond such three-month period made necessary by such proposed schedule) that has been agreed to in writing by each of the Scheduling Parties, Buyer shall adopt such proposed schedule as the Ninety-Day Schedule for such period unless Buyer determines, in Buyer=s reasonable discretion, that such proposed schedule or changes to the Annual Program (i) does not comply with the Scheduling Principles, or (ii) would have a material adverse effect on Buyer. If Buyer determines that such proposed schedule or changes to the Annual Program does not comply with the Scheduling Principles or would have a material adverse effect on Buyer, Buyer shall, within three (3) business days after receiving such proposed schedule, notify Seller of the deficiencies in such proposed schedule and allow Seller to submit a revised proposed schedule within two (2) business days after receiving Buyer's response. (b) In the event that Seller does not deliver a schedule that complies with Section 5.1(a) on or before the deadline specified therein, the schedule of Arrival Windows for the Ninety-Day Schedule for the applicable period shall be as set forth in the Annual Program (as such Annual Program may have been previously revised pursuant to Section 5.1(c)). (c) In the event Buyer adopts a Ninety-Day Schedule and other changes to the Annual Program pursuant to Section 5.1(a), the Annual Program shall be revised, to the extent necessary, to reflect such Ninety-Day Schedule and such other changes and Buyer shall deliver to Seller such Ninety-Day Schedule and such revised Annual Program no later than the fifteenth (15th) day of the applicable month or, in the event Seller has re-submitted a revised proposed schedule pursuant to Section 5.1(a), within two (2) business days after Buyer=s receipt of such revised proposed schedule.