Notice and Report of Substantial Completion Sample Clauses

Notice and Report of Substantial Completion. When Contractor determines that it has satisfied the conditions for Substantial Completion in accordance with Section 6.7.2, Contractor shall deliver a Notice of such determination (“Notice of Substantial Completion”) to Owner in the form set forth in Appendix I-4. The Notice of Substantial Completion will contain a certification by Contractor that it has satisfied all of the conditions for Substantial Completion pursuant to this Section 6.7 and a report with sufficient detail (including preliminary laboratory results sufficient for a reasonable person to conclude that there is a high probability that the final laboratory results will confirm that the applicable conditions of Substantial Completion have been achieved) to enable Owner to determine whether Contractor has achieved such requirements. Contractor shall provide to Owner final laboratory results promptly upon receipt, but in no case later than thirty (30) days after the Completed Performance Test.
AutoNDA by SimpleDocs
Notice and Report of Substantial Completion. When Contractor believes that it has achieved Substantial Completion, it shall deliver to Client a notice thereof (the “Notice of Substantial Completion”). The Notice of Substantial Completion shall contain (i) a report, including the results of the completed Performance Test, in a form with sufficient detail to enable Client to determine whether Substantial Completion has been achieved and (ii) the updated Punch List including a complete description and an estimate of the cost to complete and/or correct each remaining Punch List item. * Certain confidential information on this page has been omitted and filed separately with the Securities and Exchange Commission.
Notice and Report of Substantial Completion. When Contractor determines that it has satisfied the conditions for Substantial Completion of a Unit in accordance with Section 6.2.1, Contractor shall deliver a Notice of such determination (“Notice of Substantial Completion”) to PSGC in the form set forth in Appendix R-4. The Notice of Substantial Completion will contain a certification by Contractor that it has satisfied all of the conditions for Substantial Completion for the Unit pursuant to this Section 6.2 and a report with sufficient detail (including preliminary laboratory results sufficient for a reasonable person to conclude that there is a high probability that the final laboratory results will confirm that the applicable conditions of Substantial Completion have been achieved) to enable PSGC to determine whether Contractor has achieved such requirements with respect to such Unit.
Notice and Report of Substantial Completion. When Contractor believes that it has achieved Substantial Completion for Phase 1 or Phase 2, as applicable, Contractor shall deliver a written notice of such determination (“Notice of Substantial Completion”) to Owner for the applicable phase. The Notice of Substantial Completion shall contain a report in form reasonably acceptable to Owner and with sufficient detail to enable Owner to determine whether Substantial Completion of Phase 1 or Phase 2, as applicable, has been achieved.
Notice and Report of Substantial Completion. When Contractor determines that it has satisfied the conditions for Substantial Completion in accordance with Section 6.2.1, Contractor shall deliver a Notice of such determination (“Notice of Substantial Completion”) to Owner in the form set forth in Appendix I-4. The Notice of Substantial Completion will contain a certification by Contractor that it has satisfied all of the conditions for Substantial Completion pursuant to this Section 6.2 and a report with sufficient detail (including preliminary laboratory results sufficient for a reasonable person to conclude that there is a high probability that the final laboratory results will confirm that the applicable conditions of Substantial Completion have been achieved) to enable Owner to determine whether Contractor has achieved such requirements.
Notice and Report of Substantial Completion. When Contractor believes that it has achieved Substantial Completion, it shall deliver to Client a notice thereof (the “Notice of Substantial Completion”). The Notice of Substantial Completion shall contain (i) a report, including the results of the completed Performance Test, in a form with sufficient detail to enable Client to determine whether Substantial Completion has been achieved and (ii) the updated Punch List including a complete description and an estimate of the cost to complete and/or correct each remaining Punch List item.

Related to Notice and Report of Substantial Completion

  • Certificate of Substantial Completion The certificate prepared by the Designer and approved by the Owner to the effect that the Work has reached Substantial Completion.

  • Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.

  • Substantial Completion Section 7.4.1 When Supplier believes that it has achieved the requirements of Substantial Completion, Supplier shall provide written notice (the “Notice of Substantial Completion”) to System Owner stating that Supplier has achieved Substantial Completion, together with copies of all documents (as identified in the definition of Substantial Completion) that are required to be delivered to System Owner to meet Substantial Completion that have not been previously delivered. Section 7.4.2 Upon receipt of the Notice of Substantial Completion, System Owner shall promptly proceed to obtain Independent Engineer’s review and approval of the Notice of Substantial Completion and the Commissioning Report within a reasonable time, but in no event more than ten (10) Business Days following receipt of the Notice of Substantial Completion and all accompanying documents or such longer period of time as specified in the Construction Schedule (the “Substantial Completion Review Period”). Section 7.4.3 Supplier shall provide System Owner with reasonable notice of the date and time of the inspection or review of the System by a representative of the applicable Governmental Authority or Host Utility, if required, for purposes of achieving Substantial Completion, and System Owner shall have the right to have one or more representatives and the Independent Engineer present during such inspection or review. If the representative of the applicable Governmental Authority or Host Utility notifies Supplier or System Owner that the requirements for achieving Substantial Completion have not been achieved, then Supplier shall promptly take such action as necessary to achieve such requirements and, to the extent applicable, schedule another inspection or review of the System. Such procedure shall be repeated until such inspection or review has been satisfactorily completed and approved. Section 7.4.4 If System Owner and the Independent Engineer approve the Notice of Substantial Completion, System Owner shall, within the Substantial Completion Review Period, (a) notify Supplier of its approval and (b) issue written notice to Supplier to complete the Work (the “Notice to Complete”). Section 7.4.5 If System Owner or the Independent Engineer has a reasonable basis not to approve the Notice of Substantial Completion because the requirements for Substantial Completion have not been met, System Owner shall, within the Substantial Completion Review Period, notify Supplier of its non-approval and include a detailed explanation for the basis thereof. Supplier shall promptly undertake such action or work as necessary to achieve such requirements and shall then issue another Notice of Substantial Completion to System Owner stating that Supplier believes that such requirements have been achieved. Such procedure shall be repeated until Substantial Completion is achieved. If Supplier disputes the reasons stated in System Owner’s notification, then such dispute shall be resolved in accordance with Article XIX.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Project Completion Report At the completion of construction and once a Project is placed in service, the Subrecipient must submit a Project Completion Report that includes the total number of units built and leased, affordable units built and leased, DR-MHP units built and leased, an accomplishment narrative, and the tenants names, demographics and income for each DR-MHP unit.

  • Notice to Proceed - Site Improvements The Recipient shall not commence, or cause to be commenced, any site improvements or other work on the Land until the Director has issued a Notice to Proceed to the Recipient. Such Notice to Proceed will not be issued until the Director is assured that the Recipient has complied with all requirements for the approval of a grant under Revised Code Sections 164.20 through 164.27 and has completed any land acquisition required by the Project. A Notice to Proceed shall be required for all Project prime contractors or direct procurement initiated by the Recipient following execution of this Agreement.

  • Satisfactory Completion of Due Diligence The Company and the Shareholders shall have completed their legal, accounting and business due diligence of the Parent and the results thereof shall be satisfactory to the Company and the Shareholders in their sole and absolute discretion.

  • Completion of Concrete Pours and Emergency Work (a) Except as provided in this sub-clause an Employee shall nor work or be required to work in the rain. (b) Employees shall not be required to start a concrete pour in Inclement Weather. (c) Where a concrete pour has been commenced prior to the commencement of a period of Inclement Weather Employees may be required to complete such concrete pour to a practical stage and for such work shall be paid at the rate of double time calculated to the next hour, and in the case of wet weather shall be provided with adequate wet weather gear. (d) If an Employee’s clothes become wet as a result of working in the rain during a concrete pour the Employee shall, unless the Employee has a change of dry working clothes available, be allowed to go home without loss of pay. (e) The provisions of clauses 32.7(c) and 32.7(d) hereof shall also apply in the case of emergency work where the Employees concerned and their delegates agree that the work is of an emergency nature and can start and/or proceed.

  • DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be: § 3.2 The Contract Time shall be measured from the date of commencement of the Work.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!