Partial Completion and Acceptance Sample Clauses

Partial Completion and Acceptance. If at any time prior to the issuance of the final certificate referred to in Acceptance and Final Payment - Section 19, any portion of the permanent construction has been satisfactorily completed, and if the Supervising Professional determines that portion of the permanent construction is not required for the operations of the Contractor but is needed by the City, the Supervising Professional shall issue to the Contractor a certificate of partial completion, and immediately the City may take over and use the portion of the permanent construction described in the certificate, and exclude the Contractor from that portion. The issuance of a certificate of partial completion shall not constitute an extension of the Contractor's time to complete the portion of the permanent construction to which it relates if the Contractor has failed to complete it in accordance with the terms of this Contract. The issuance of the certificate shall not release the Contractor or its sureties from any obligations under this Contract including bonds. If prior use increases the cost of, or delays the work, the Contractor shall be entitled to extra compensation, or extension of time, or both, as the Supervising Professional may determine.
AutoNDA by SimpleDocs
Partial Completion and Acceptance. If at any time prior to the issuance of the final payment, referred to in Section 40 hereinafter, any portion of the permanent construction has been satisfactorily completed, and if the Engineer/Architect determines that such portion of the permanent construction is not required for the operations of the Contractor but is needed by the Owner, the Engineer/Architect shall issue to the Contractor a certificate of partial completion, and thereupon or at any time thereafter the Owner may take over and use the portion of the permanent construction described in such certificate, and exclude the Contractor therefrom. The issuance of a certificate of partial completion shall not be constructed to constitute an extension of the Contractor’s time to complete the portion of the permanent construction to which it relates if he has failed to complete it in accordance with the terms of this contract. The issuance of such a certificate shall not operate to release the Contractor or his sureties from any obligations under this contract or the performance bond. If any prior use increases the cost of or delays the work, the Contractor shall be entitled to extra compensation, or extension of time, or both, as the Engineer/Architect may determine, unless otherwise provided.
Partial Completion and Acceptance. If before the final completion of all the work any portion of the permanent construction has been satisfactorily completed and the same will be immediately useful to the Fund, the latter may, by written notice, advise the Contractor that it accepts such portion of the work. Such action by the Fund shall in no way affect the obligations of the Contractor under the terms and provisions of the Contract with respect to any work not so completed and accepted.
Partial Completion and Acceptance. If at any time prior to Acceptance as referred to in Article 11REQUIREMENTS FOR ACCEPTANCE”, any portion of the Work has been completed and if Owner determines that such portion of the Work is of value, Owner will, if applicable, issue to Consultant a certificate or other written acknowledgement of partial completion. Upon the issuance of such certificate or other written acknowledgement, or at any time thereafter, Owner may take over and use the portion of the Work described in such certificate and may exclude Consultant therefrom. The issuance of a certificate of partial completion or other written acknowledgement will not release the Consultant from any obligations under the Agreement unless such prior use delays the Work or increases its cost. In this event, the Consultant will be entitled to extra compensation or extension of time, or both, as Owner may determine.
Partial Completion and Acceptance. If before the final completion of all the work any portion of the permanent construction has been satisfactorily completed and the same will be immediately useful to the University, the latter may, by written notice, advise the Contractor that it accepts such portion of the work. Such actions by the University shall in no way affect the obligations of the Contractor under the terms and provisions of the Contract with respect to any work not so completed and accepted.

Related to Partial Completion and Acceptance

  • INSPECTION AND ACCEPTANCE (a) LOCKHEED XXXXXX and its customer may inspect all Work at reasonable times and places, including, when practicable, during manufacture and before shipment. SELLER shall provide all information, facilities, and assistance necessary for safe and convenient inspection without additional charge.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Substantial Completion “Substantial Completion” means the stage in the progress of the Work when the Work, or designated portions thereof, may still require minor modifications or adjustments but, in the Owner’s opinion, the Work has progressed to the point such that all parts of the Work under consideration are fully operational and usable for intended purposes, as evidenced by a Certificate of Substantial Completion approved by the Owner. If a Certificate of Occupancy is required by public authorities having jurisdiction over the Work, said certificate shall be issued before the Work or any portion thereof is considered substantially complete. When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall notify Owner’s Designated Representative (sometimes referred to as the “ODR”) and request a determination as to whether the Work or designated portion thereof is substantially complete. If the ODR does not consider the Work substantially complete, the ODR will notify the Contractor giving reasons therefore. Failure on the Owner’s part to list a reason does not alter the responsibility of the Contractor to complete all Work in accordance with the terms of this Agreement. After satisfactorily completing items identified by Owner’s Designated Representative, the Contractor shall then submit another request for the ODR to determine Substantial Completion. If The ODR considers the Work substantially complete, The ODR will prepare and deliver a certificate of Substantial Completion which shall establish the date of Substantial Completion, shall include a punch list of items to be completed or corrected before final completion and final payment, shall establish the time within which the Contractor shall finish the punch list, and shall establish responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, warranty and insurance. Failure to include an item on the punch list does not alter the responsibility of the Contractor to complete all Work in accordance with the terms and conditions of this Agreement. The certificate of Substantial Completion shall be signed by the Owner and the Contractor to evidence acceptance of the responsibilities assigned to them in such certificate. Substantial Completion (as defined in this agreement) for all stages of the Work shall be achieved on or before the following Substantial Completion date: DATE FOR SUBSTANTIAL COMPLETION: TBD Under no circumstances will the time for Substantial Completion exceed this date without a written amendment to this Agreement. THE TIMES SET FORTH IN THE CONSTRUCTION DOCUMENTS ARE AN ESSENTIAL ELEMENT OF THE AGREEMENT. TIME LIMITS STATED IN THE CONTRACT DOCUMENTS ARE OF THE ESSENCE OF THIS AGREEMENT.

  • Final Acceptance When the Project/Service or any portion thereof, as designated by the COUNTY, is ready for its intended use, the COUNTY and any other invited parties shall make an inspection of the Project/Service, to verify its completeness and develop a punch list of items needing completion or correction before final payment will be made. CONTRACTOR shall have ten (10) calendar days to correct all deficiencies. An eighty-dollar ($80.00) re-inspection fee shall be applied for the third inspection and any required re-inspection thereafter. The COUNTY shall have the right to exclude CONTRACTOR from those portions of the work designated as complete after the inspection; provided, however, that CONTRACTOR will have reasonable access for the time allotted by the COUNTY to complete or correct items on the punch list. When the work provided for under this Agreement has been completely performed by CONTRACTOR, and the final inspection has been made by the COUNTY, a final invoice will be prepared by the CONTRACTOR. The amount of this invoice, less any sums that may have been deducted or retained under the provisions of this Agreement, will be paid to CONTRACTOR in accordance with this Agreement, and after CONTRACTOR has agreed in writing to accept the balance due, as determined by the COUNTY, as full settlement of the account under the contract and of all claims in connection therewith. Occupancy by the COUNTY alone does not constitute final acceptance.