PRODUCT OPTIONS AND SUBSTITUTIONS. 3.10.1 For Products specified by reference standards or by description only, XXXX may provide any Product meeting those standards or description.
3.10.2 For Products specified by naming one or more manufacturers with provision for substitutions or equal, XXXX may submit a request for substitution for any manufacturer not named.
3.10.3 Director will consider requests for substitutions only within the first 15 percent (15%) of Contract Time, or first ninety (90) days after date of Notice to Proceed, whichever is less.
3.10.4 XXXX shall document each request for substitution with complete data substantiating compliance of proposed substitution with the Contract.
3.10.5 A request for substitution constitutes a representation that XXXX:
3.10.5.1 has investigated the proposed Product and determined that it meets or exceeds the quality standard of the specified Product;
3.10.5.2 shall provide the same warranty for the substitution as for the specified Product;
3.10.5.3 shall coordinate installation of the proposed substitution and make changes to other work which may be required for the Work to be completed, with no additional cost or increase in time to the City;
3.10.5.4 confirms that cost data is complete and includes all related costs under the Contract Documents;
3.10.5.5 waives related Claim for additional costs or time extensions that may subsequently become apparent; and
3.10.5.6 shall provide review or redesign services by a design consultant with appropriate professional license and shall obtain re-approval and permits from authorities.
3.10.6 Director will not consider and will not approve substitutions when:
3.10.6.1 they are indicated or implied on Shop Drawing or Product Data submittals without separate written request; or
3.10.6.2 acceptance will require revision to the Contract Documents.
3.10.7 Director may reject requests for substitution, and his decision will be final and binding on the Parties.
PRODUCT OPTIONS AND SUBSTITUTIONS. Contractor's product options:
PRODUCT OPTIONS AND SUBSTITUTIONS. 3.10.1 For Products specified by reference standards or by description only, DESIGN-BUILD CONTRACTOR may provide any Product meeting those standards or description.
3.10.2 For Products specified by naming one or more manufacturers with provision for substitutions or equal, DESIGN-BUILD CONTRACTOR may submit a request for substitution for any manufacturer not named.
3.10.3 Director will consider requests for substitutions only within the first 15 percent (15%) of Contract Time or first ninety (90) days after date of Notice to Proceed, whichever is less.
3.10.4 DESIGN-BUILD CONTRACTOR shall document each request for substitution with complete data substantiating compliance of proposed substitution with the Contract.
3.10.5 A request for substitution constitutes a representation that DESIGN-BUILD CONTRACTOR:
3.10.5.1. has investigated the proposed Product and determined that it meets or exceeds the quality standard of the specified Product;
3.10.5.2. shall provide the same warranty for the substitution as for the specified Product;
3.10.5.3. shall coordinate installation of the proposed substitution and make changes to other work which may be required for the Work to be completed, with no additional cost or increase in time to the City;
3.10.5.4. confirms that cost data is complete and includes all related costs under the Contract Documents;
3.10.5.5. waives related Claim for additional costs or time extensions that may subsequently become apparent; and
3.10.5.6. shall provide review or redesign services by a Designer with appropriate professional license and shall obtain re-approval and permits from authorities.
3.10.6 Director will not consider and will not approve substitutions when:
3.10.6.1. they are indicated or implied on Shop Drawing or Product Data submittals without separate written request; or
3.10.6.2. acceptance will require revision to the Contract Documents.
3.10.7 Director may reject requests for substitution, and his decision will be final and binding on the Parties.
PRODUCT OPTIONS AND SUBSTITUTIONS. 3.10.1 For Products specified by reference standards or by description only, XXXX may provide any Product meeting those standards or description.
3.10.2 For Products specified by naming one or more manufacturers with provision for substitutions or equal, XXXX may submit a request for substitution for any manufacturer not named.
3.10.3 [Intentionally omitted.]
3.10.4 XXXX shall document each request for substitution with complete data substantiating compliance of proposed substitution with the Contract Documents.
3.10.5 A request for substitution constitutes a representation that XXXX: (.
1) has investigated the proposed Product and determined that it meets or exceeds the quality standard of the specified Product; (.
2) shall provide the same warranty for the substitution as for the specified Product; (.
3) shall coordinate installation of the proposed substitution and make changes to other work which may be required for the Work to be completed, with no additional cost or increase in time to HFH; (.
4) confirms that cost data is complete and includes all related costs under the Contract Documents; (.
5) waives related Claim for additional costs or time extensions that may subsequently become apparent; and (.
6) shall provide review or redesign services by a Architect with appropriate professional license and shall obtain re-approval and permits from authorities.
3.10.6 HFH will not consider and will not approve substitutions when they are indicated or implied on Shop Drawing or Product Data submittals without separate written request; or acceptance will require revision to the Contract Documents.
3.10.7 HFH may reject requests for substitution, and its decision will be final and binding on the Parties.
PRODUCT OPTIONS AND SUBSTITUTIONS of specified quality.
PRODUCT OPTIONS AND SUBSTITUTIONS. A. Materials and equipment of equivalent quality may be substituted for those scheduled oridentified by name on the drawings if so reviewed by the Engineer and Owner prior to bidding. This may be done by submitting to the Engineer, at least seven (7) working days prior to the bid date, a letter in triplicate requesting prior review. This submittal shall include all data necessary for complete evaluation of the substitution and publication in written Addenda.