Records of Defined Cost, payments assessments of compensation events to be kept by the Contractor
Records of Defined Cost, payments assessments of compensation events to be kept by the Supplier Read clause 63.2 and 11.2(4) and then state whether the Supplier is required to keep any records of Defined Cost. Include any other constraint which may be required in regard to format and filing of the records, and whether access for the Supply Manager shall be provided in hard copy or electronically.
Records of Defined Cost, payments assessments of compensation events to be kept by the Supplier Early warning to be given by any of the Parties as soon either becomes aware of matters that could increase the total of total Prices, delay Completion etc. All the Compensation events will be implemented through the raising of an early warning. See NEC Core clause 16.1 and 63.1 and 63.2
Records of Defined Cost, payments assessments of compensation events to be kept by the Contractor In order to substantiate the Defined Cost of compensation events, the Employer requires the Contractor to keep records of amounts paid by him, in the following format: People employed by the Contractor (labour) Signed timesheets Materials Register of materials used Equipment Register of Equipment used 3 Engineering and the Contractor’s Design
3.1 Employer’s design Drakensberg pumped storage scheme consists of four 250 MW Pump-turbine units. Each unit has a Main Inlet Valve (MIV). The main function of the MIV is to isolate the Pump-turbine from the penstock. Each MIV is equipped with bypass line and a hydraulically operated bypass valve. The bypass line is connecting the MIV body with the Pump turbine spiral case extension. The function of the Main Inlet Bypass Valve and Bypass Line is to achieve balance pressure between the upstream and downstream sides of the MIV, prior to the Main Inlet Valve opening. The four MIV’s are located in an underground cavern. Overhead cranes are available to assist with maintenance of the MIV’s. Each of these MIV’s are installed in an open concrete pit, and personnel access is gained by a series of cat-ladders. Due to repeated failures of the existing bypass valves, excessive cavitation damage and the high vibration experienced in the existing bypass line, the replacement of the complete bypass line and valve with a re- designed bypass line configuration and a more modern design hydraulically operated Bypass Valve to be applied. The diameter of the Bypass Line and Bypass Valve to be increased with the new design, and the location of the bypass valve to be such that it shall be fitted directly to the pump-turbine spiral case extension pipe.
3.2 Parts of the works which the Contractor is to design The Contractor is not required to design any part of the works.
Records of Defined Cost, payments assessments of compensation events to be kept by the Contractor
i. No standing time claims will be entertained without the relevant proof of presence and activity in the form of a time sheet.
ii. Proof of expenses must be provided to the Employer as a hard copy as well as a soft copy.