SERVICES – APPLICATION MAINTENANCE AND ENHANCEMENT. The provisions of this Article 7 shall only apply to the extent that Contractor is required under a Work Order to deliver a Deliverable to District.
SERVICES – APPLICATION MAINTENANCE AND ENHANCEMENT. The provisions of this Article 7 shall only apply to the extent that Contractor is required under this Agreement to deliver a Deliverable to District. DocuSign Envelope ID: 57FE9282-E46A-43D1-831B-4F549CBE8B96
7.1 Development of Schedule and Acceptance Testing Criteria
(a) Staged milestones (each a “Key Milestone”) for the development of each Deliverable and objective criteria for measuring Contractor’s progress toward achieving each Key Milestone.
(b) A schedule for the development of each Deliverable, including the dates that Contractor will achieve each Key Milestone and dates for the completion and delivery of each Deliverable, including any Final Deliverable(s).
(c) Specifications and proposed acceptance criteria and/or review periods, as appropriate, for each Deliverable and each Final Deliverable (each a set of “Final Criteria”).
(d) Specification of a timeframe following Contractor’s delivery of a Deliverable to District during which the Deliverable will be subject to acceptance testing against its Final Criteria by the District (the “Initial Acceptance Period”). While a Deliverable Work Plan may specify a longer period of time for the Initial Acceptance Period, the Initial Acceptance Period shall be no shorter than sixty (60) days. The Deliverable Work Plan will be subject to District’s review, comment, and approval and will be approved by the parties in writing. Contractor will not commence development of any System Deliverable until the parties have approved the Deliverable Work Plan in writing, or, in the absence of such approval, the District has specifically authorized Contractor in writing to commence development.